MONTHYEARSECY-23-0021, Enclosure 3 - Draft Regulatory Analysis2023-03-0101 March 2023 SECY-23-0021: Enclosure 3 - Draft Regulatory Analysis NUREG-1530, SECY-23-0020: Enclosure 2 - Regulatory Analysis2023-02-28028 February 2023 SECY-23-0020: Enclosure 2 - Regulatory Analysis ML20287A4342020-10-13013 October 2020 DG 1377 for RG 1.21, Rev.3 Regulatory Analysis - Measuring, Evaluating, and Reporting Radioactive Material in Liquid and Gaseous Effluents and Solid Waste SECY-17-0027, Proposed Rule: Draft Regulatory Analysis and Backfitting and Issue Finality2019-08-31031 August 2019 Proposed Rule: Draft Regulatory Analysis and Backfitting and Issue Finality ML1104201332011-04-30030 April 2011 Regulatory Analysis, Revision 4 of Regulatory Guide 1.149, Nuclear Power Plant Simulation Facilities for Use in Operator Training, License Examinations, and Applicant Experience Requirements 2023-03-01
[Table view]Some use of "" in your query was not closed by a matching "". Category:Regulatory Guide
MONTHYEARML22276A1542022-10-0303 October 2022 Pre-decisional DG Seismic Isolation Ver 7 ML22276A1492022-10-0303 October 2022 Pre-decisional DG Seismic Design Ver 7 ML22157A3662022-05-27027 May 2022 Draft NRC Regulatory Issue Summary 2022-XX Personnel Access Authorization Requirements for Non-Immigrant Foreign Nationals Working at Nuclear Power Plants ML21280A3592021-10-26026 October 2021 Watermarked for ACRS - RG 1.244 - Control of Heavy Loads -10-7.docx Regulatory Guide 1.1052021-02-28028 February 2021 Rev 4, Setpoints for Safety-Related Instrumentation ML20287A1992021-01-31031 January 2021 Regulatory Guide (RG) 1.191, Rev 1, Fire Protection Program for Nuclear Power Plants During Decommissioning ML20287A4232021-01-31031 January 2021 Draft Regulatory Guide DG-1377, Measuring, Evaluating, and Reporting Radioactive Material in Liquid and Gaseous Effluents and Solid Waste ML20142A4892020-08-31031 August 2020 DG-1351 Rev 1 - Licensee Actions to Address Nonconservative Technical Specifications_FY20 ML20078K9272020-08-0606 August 2020 FRN for DG-1370 for Revision 1 of RG 1.191 Fire Protection Program for Nuclear Power Plants During Decommissioning and Permanent Shutdown ML20017A2652020-04-30030 April 2020 Regulatory Guide (RG) 1.188, Standard Format and Content for Applications to Renew Nuclear Power Plant Operating Licenses. Revision 2 ML19291D4372019-10-17017 October 2019 RITF Public Meeting Talking Points on Regulatory Guide Reviews (October 17, 2019) Regulatory Guide 1.2262019-06-30030 June 2019 Rev. 0, Flexible Mitigation Strategies for Beyond-Design-Basis Events Regulatory Guide 1.2272019-06-30030 June 2019 Rev. 0, Wide-Range Spent Fuel Pool Level Instrumentation ML18129A0802018-06-30030 June 2018 Draft Regulatory Guide (DG)-1336, Monitoring the Effectiveness of Maintenance at Nuclear Power Plants. ML16312A0022017-08-0202 August 2017 Rulemaking: Final Rule: Office of Management and Budget Supporting Statement for Information Collections American Society of Mechanical Engineers Code Cases ML15294A4902017-03-10010 March 2017 Rulemaking: Being Made Public to Support the Regulatory Information Conference - Draft Preliminary Regulatory Basis - Regulatory Improvements for Power Reactors Transitioning to Decommissioning ML16035A4762017-02-28028 February 2017 Draft Regulatory Guide (DG)-2004, Emergency Planning for Research and Test Reactors and Other Non-Power Production and Utilization Facilities ML16211A1672016-11-30030 November 2016 Rev. 0 - Wide-Range Spent Fuel Pool Level Instrumentation Dated November 2016 ML16218A2362016-11-30030 November 2016 Rev. 0 - Integrated Response Capabilities for Beyond-Design-Basis Events Dated November 2016 SECY-16-0048, : Enclosure 3 - Proposed Rulemaking: Non-Power Production or Utilization Facility License Renewal (RIN-350-AI96)2016-04-0707 April 2016 SECY-16-0048: Enclosure 3 - Proposed Rulemaking: Non-Power Production or Utilization Facility License Renewal (RIN-350-AI96) ML16005A1332016-01-19019 January 2016 2/4/2016 ACRS Subcommittee Meeting: Regulatory Guide 1 224 - Establishing Analytical Limits for Zirconium-Alloy Cladding Material ML16005A1342016-01-19019 January 2016 2/4/2016 ACRS Subcommittee Meeting: Regulatory Guide 1.223 - Determining Post Quench Ductility ML16005A1352016-01-19019 January 2016 2/4/2016 ACRS Subcommittee Meeting: Regulatory Guide 1.222 - Measuring Breakaway Oxidation Behavior ML15259A4722015-09-16016 September 2015 Results of Periodic Review of Regulatory Guide 8.35 ML15068A3282015-03-10010 March 2015 ACRS Pre-Decisional DG-1319 Integrated Response Capabilities for Beyond-Design-Basis Events ML15068A3252015-03-10010 March 2015 ACRS Pre-Decisional DG-1317, Wide Range Spent Fuel Pool Level Instrumentation SECY-11-0124, Station Blackout Mitigation Strategies, Final Regulatory Basis - Revision 32013-07-17017 July 2013 Station Blackout Mitigation Strategies, Final Regulatory Basis - Revision 3 ML1104201332011-04-30030 April 2011 Regulatory Analysis, Revision 4 of Regulatory Guide 1.149, Nuclear Power Plant Simulation Facilities for Use in Operator Training, License Examinations, and Applicant Experience Requirements ML1034000082011-01-31031 January 2011 Draft Regulatory Guide, DG-1229, Assuring the Availability of Funds for Decommissioning Nuclear Reactors ML0909705302009-09-30030 September 2009 Draft Regulatory Guide DG-1225, Instrument Lines Penetrating the Primary Reactor Containment ML0916204092009-07-31031 July 2009 DG-4015, Preparation of Environmental Reports for Nuclear Power Plant License Renewal Applications ML0812005932008-04-10010 April 2008 Enclosure 9 - Proposed Guidance to MC0305 to Address Protracted PI Results - NEI, Draft ML0808801432008-03-27027 March 2008 Nesc Reference for the Purpose of TMI License Renewal Environmental Review ML0625404082006-10-11011 October 2006 Draft Regulatory Guide DG-1164, Meteorological Monitoring Programs for Nuclear Power Plants (Proposed Revision 1 of Regulatory Guide 1.23) ML0615202332006-05-29029 May 2006 DG-1145 Section C.I.1 Introduction on and General Description of Plant Regulatory Guide 1.12005-09-0606 September 2005 Net Positive Suction Head for Emergency Core Cooling and Containment Heat Removal System Pumps ML0424600382004-11-0808 November 2004 SECY-040-0211Atch2 - Regulatory Guide 1.101, Revision 5 ML0413400872004-06-30030 June 2004 SECY-04-0109 - Attachment 6 - Regulatory Guide 1.201, Guidelines for Categorizing Structures, Systems, and Components in Nuclear Power Plants According to Their Safety Significance ML0320305282003-06-23023 June 2003 Debris Generation Methodology Guidance, Draft Guide, Attachment 3 ML0320305352003-06-21021 June 2003 PWR Sump Performance Evaluation Methodology: Velocity Calculation, Draft, Attachment 4 ML0037671122000-11-0707 November 2000 Guide for Processing License Amendments ML0037681442000-11-0101 November 2000 G20000453/LTR-00-0600 - Enclosure to Rep. Sue Kelly Policy on Request for Additional Information When Processing License Amendments ML0037604692000-10-25025 October 2000 SECY-00-0212-Attachment 1 - Regulatory Guide 1.186 - Guidance and Examples for Idenfitying 10 CFR 50.2 Design Bases ML0037360972000-08-24024 August 2000 Draft Regulatory Guide DG-1104, Standard Format and Content for Applications to Renew Nuclear Power Plant Operating Licenses ML0734102491978-03-0707 March 1978 Transmittal of Revision 1 to Regulatory Guide 1.97, a Clearer Basis for Development Initial Response ML0124202911976-01-0707 January 1976 License Amendment, Reporting Requirements According to Regulatory Guides 1.10 and 1.16 ML0127703911976-01-0707 January 1976 Amendments 14, Incorporating Technical Specifications Changes to the Reporting Requirements ML0119300121975-12-22022 December 1975 Letter Informing of Issuance of Amendment No. 16, Technical Specification Change No.26 for License No DPR-38 ML0133304361975-11-26026 November 1975 Issuance of Amendments 13 and 12, Incorporating Into Turkey Point Nuclear Generating Units 3 and 4 TS Changes to Reporting Requirements ML0118700651975-11-0101 November 1975 License DPR-35, Amendment 13 2022-05-27
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
REGULATORY ANALYSIS REVISION 4 OF REGULATORY GUIDE 1.149, NUCLEAR POWER PLANT SIMULATION FACILITIES FOR USE IN OPERATOR TRAINING, LICENSE EXAMINATIONS, AND APPLICANT EXPERIENCE REQUIREMENTS.
Statement of the Problem On September 4, 2009, ANSI approved ANSI/ANS-3.5-2009 as the new industry consensus American National Standard. Initially approved in 1979, the 2009 version marks the sixth issuance of the standard. The ANS-3.5 Working Group of the Standards Committee of the ANS developed and prepared the new standard.
Facility licensees that maintain a simulation facility consisting solely of a plant-referenced simulator currently adhere to and use one of three historical versions of ANSI/ANS-3.5:
(1) ANSI/ANS-3.5-1985, (2) ANSI/ANS-3.5-1993, or (3) ANSI/ANS-3.5-1998. Based on recent industry feedback and work with industry representatives through the NEI LOFG, the NRC believes that the use of a single updated standard will greatly enhance facility licensees approach to and standardization of simulator performance testing requirements, as well as the NRCs ability to uniformly inspect for and determine compliance with its plant-referenced simulator fidelity regulations. The staff believes that simulation facility licensees can transition to ANSI/ANS-3.5-2009 with little or no impact to their simulator performance testing programs.
The NRC has revised Regulatory Guide 1.149, originally issued April 1981, three times (April 1987, April 1996, and October 2001) to endorse successive revisions of ANSI/ANS-3.5. The staff specified exceptions to previous standards in the area of performance testing in the initial issuance through Revision 3 to ensure that application of previous standards would support the requirements of the regulations and be responsive to the NRCs concern that simulator fidelity be demonstrated and met, maintained, and assured on a continuing basis.
As a result of regulatory experience gained from oversight and inspection of simulation facilities, as well as feedback from industry stakeholders, the NRC is revising Regulatory Guide 1.149 to update and clarify its position regarding methods acceptable to the staff for complying with those portions of the NRCs regulations associated with approval or acceptance of a simulation facility for use in operator and senior operator training (initial and requalification), for use in NRC license examinations (operating tests), and for use in meeting applicant experience requirements (for performing control manipulations that affect reactivity) to establish eligibility for an operators license.
Revision of Regulatory Guide 1.149 is necessary for (1) the NRC to endorse the use of ANSI/ANS-3.5-2009 as a technical standard to ensure compliance with the Commissions simulation facility scope and fidelity requirements, (2) simulation facility licensees to voluntarily move to a single consensus standard and carry out its requirements, (3) the NRC to communicate its expectations, and (4) facilitation of a common approach and methodology for conducting and documenting simulator scenario-based performance testing.
Objective The objective of this regulatory action is to update and clarify a number of regulatory issues important to the NRC staff and simulation facility licensees as stakeholders for which the current revision (i.e., Revision 3) of Regulatory Guide 1.149 does not provide sufficient guidance.
Alternative Approaches The NRC staff considered the following alternative approaches:
Do not revise Regulatory Guide 1.149.
Revise and update Regulatory Guide 1.149.
Alternative 1: Do Not Revise Regulatory Guide 1.149 Under this alternative, the NRC would not revise this guidance, and the current guidance would be retained. If NRC does not take action, there would not be any changes in costs or benefit to the public, licensees, or the NRC. However, the no-action alternative would not address identified concerns with the current version of the guide. The NRC would continue to review each simulation facility on a case-by-case basis. This alternative provides a baseline condition from which any other alternatives will be assessed.
Alternative 2: Revise and Update Regulatory Guide 1.149 Under this alternative, the NRC would revise Regulatory Guide 1.149, taking into consideration the extensive regulatory experience gained since last revision of Regulatory Guide 1.149 in October 2001.
The benefit of updating and revising Regulatory Guide 1.149 is that it would provide guidance to ensure that nuclear power plant simulation facilities used for operator training, license examinations, and applicant experience requirements are maintained in accordance with the industrys most recent consensus standard, which will preclude negative training and inappropriate operator license evaluations.
Simulation facilities that meet the minimum scope and fidelity requirements of ANSI/ANS-3.5-2009 must be able to demonstrate, on a continuing basis, compliance with the Commissions simulation facility regulations, as described in 10 CFR 55.46.
The impact to the NRC would be the costs associated with preparing and issuing the revised regulatory guide. The impact to the public would be the voluntary costs associated with reviewing and providing comments to the NRC during the public comment period. The impact to facility licensees would be the cost of implementing the new standard. The value to the NRC staff and facility licensees would be the benefits associated with enhanced efficiency and effectiveness in using a common guidance document as the technical basis for demonstrating compliance with the Commissions simulation facility scope and fidelity requirements, as described in 10 CFR 55.46, and during other interactions between the NRC and facility licensees. The staff believes that simulation facility licensees would incur little or no cost (for licensees who have not already moved to ANSI/ANS-3.5-2009, the cost is expected to be minimal, if any, since significant human resource burdens and simulator performance testing time savings are anticipated as a result of moving to one standard, which the proposed guide is advocating).
Conclusion Based on this regulatory analysis, the staff recommends revision of Regulatory Guide 1.149. The staff concludes that the proposed action will reduce unnecessary burden on both the NRC and its licensees and will result in an improved and more uniform process for simulation facility licensees to demonstrate Page 2
compliance with the Commissions plant-referenced simulator regulations. Moreover, the staff sees no adverse effects associated with issuing this regulatory guide.