Schedule for the Conduct of Review of the South Texas Project, Units 1 and 2 License Renewal Application
ML110340478
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 02/28/2011
From: Brian Holian
Division of License Renewal
To: Gerry Powell
South Texas
Daily J
References
Download: ML110340478 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON. D.C. 20555*0001 February 28. 2011 Mr. G. T. Powell Vice President, Technical Support and Oversight South Texas Project, Units 1 and 2 STP Nuclear Operating Company P.O. Box 289 VVadsworth, TX 77483

SUBJECT:

SCHEDULE FOR THE CONDUCT OF REVIEVVOF THE SOUTH TEXAS PROJECT, UNITS 1 AND 2, LICENSE RENEVVAL APPLICATION

Dear Mr. Powell:

Enclosed is the U.S. Nuclear Regulatory Commission (NRC) staffs safety and environmental review schedule for the South Texas Project (STP). Units 1 and 2, license renewal application (LRA). This customized schedule has been established to accommodate a timely review of your application along with all other concurrent reviews of applications for license renewal. Due consideration was also given to your staff's input regarding the units' outage schedules and your ability to accommodate the safety and environmental on-site audits, which resulted in later audit dates than anticipated. The NRC staff will follow established review procedures and the enclosed schedule to complete the reviews required by Parts 54 and 51 of Title 10 of the Code of Federal Regulations.

VVe would like to emphasize that the staff will perform a very detailed and thorough review of your LRA. The NRC staff will make every effort to meet the scheduled milestones. To support this effort, your responses to the staffs requests for additional information (RAls) must be complete and provided in a timely manner. You will be afforded an adequate timeframe to respond to each group of RAls (typically 30 days). The timeliness of your responses is necessary to maintain the schedule, and delays could result in revisions to the enclosed established schedule. VVe request that you inform the NRC staff as early as possible should potential delays arise in your support of this schedule.

G. Powell 2 If you have any questions on the established schedule. please contact Mr. John Daily, Senior Project Manager. for the review of the STP LRA by telephone at 301-415-3873 or bye-mail at John.Daily@nrc.gov.

Sincerely, Brian E. Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499

Enclosure:

As stated cc w/encl: Distribution via Listserv

SOUTH TEXAS PROJECT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestone Schedule Receive license renewal application (LRA) 10/26/10 Publish Federal Register Notice (FRN) - LRA receipt and availability 12/09/10 Publish FRN - LRA acceptability and opportunity for hearing 01/13/11 Publish FRN - intent to conduct environmental scoping 01/31/11 Public Meeting -license renewal process and environmental scoping 03/02/11 Deadline for filing hearing requests and petitions for intervention 03/14/11 Environmental scoping periods ends 04/01/11 05/16/11 Audit - scoping and screening methodology 05/20/11 i Audit - aging management programs (AMPs) 06/13/11 06/24/11 l

Audit - environmental 07/11/11 07/15/11 Inspection - scoping, screening, and AMPs 08/2011 I

Issue draft supplemental environmental impact statement (SEIS) 03/2012 i Public Meeting - draft SEIS 05/2012 I

Issue safety evaluation report (SER) with open item(s) 06/2012 End of comment period for the draft SEIS 06/2012 ACRS subcommittee meeting on SER with open item(s) 08/2012 Issue final SEIS 10/2012 Issue SER 10/2012 ACRS full committee meeting on SER 12/2012 NRR decision 02/2013 Commission decision (if hearing granted) TBD ENCLOSURE

G. Powell 2 If you have any questions on the established schedule, please contact Mr. John Daily, Senior Project Manager, for the review of the STP LRA, by telephone at 301-415-3873 or bye-mail at John. Daily@nrc.gov.

Sincerely, IRA!

Brian E. Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499

Enclosure:

As stated cc w/encl: Distribution via Listserv DISTRIBUTION:

See next page ADAMS Accession No'.. ML110340478 OFFICE LA:DLR PM: RPB1:DLR PM: RPB1:DLR D:DLR NAME YEdmonds JDaily BPham BHolian DATE 02/04/11 02/09/11 02/09/11 02/28/11 OFFICIAL RECORD COpy

Letter to G. Powell From B. Holian dated February 28, 2011

SUBJECT:

SCHEDULE FOR THE CONDUCT OF REVIEW OF THE SOUTH TEXAS PROJECT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource RidsOgcMailCenter TTran CFelis ICouret, PA MThadani, DORL GPick, RIV

..IDixon, RIV VDricks, RIV WMaier, RIV CTucci RCaniano, RIV DChamberlain, RIV EWiliiamson, OGC