Tennessee Valley Authority 1101 Market Street, LP 3R Chattanooga, Tennessee 37402-2801 R. M. Krich Vice President Nuclear Licensing January 20, 2011 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328
Subject:
Revised Response to NRC Regulatory Issue Summary 2010-08, Preparation and Scheduling of Operator Licensing Examinations
References:
- 1. NRC Regulatory Issue Summary 2010-08, "Preparation and Scheduling of Operator Licensing Examinations," dated June 28, 2010
- 2. Letter from TVA to NRC, 'Response to NRC Regulatory Issue Summary 2010-08, Preparation and Scheduling of Operator Licensing Examinations," dated August 5, 2010 Nuclear Regulatory Commission's (NRC's) Regulatory Issue Summary (RIS) 2010-08 (Reference 1) requested specific information regarding the Sequoyah Nuclear Plant projected operator licensing examination schedules and the estimated number of applicants. The Enclosure to this letter addresses NRC's request and provides a revised estimate (from that previously provided in Reference 2) of the examination requirements for Sequoyah Nuclear Plant on NRC Form 536, "Operator Licensing Examination Data." The revised estimate consists of an initial operator license examination proposed for May 13, 2013. In addition, a generic fundamentals examination is proposed for 15 candidates in December 2011.
0A DOb3 printed on recycled paper
U.S. Nuclear Regulatory Commission Page 2 January 20, 2011 There are no regulatory commitments associated with this submittal. If you have any questions related to this response, please contact Beth A. Wetzel at (423) 843-7170.
Respectfully, R. M. Krich
Enclosure:
NRC Form 536, Operator Licensing Examination Data cc (Enclosure):
NRC Regional Administrator - Region II NRC Senior Resident'Inspector - Sequoyah Nuclear Plant
ENCLOSURE NRC Form 536 Operator Licensing Examination Data Tennessee Valley Authority Sequoyah Nuclear Plant Docket Nos. 50-327 and 50-328
NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 10/31/2011 (10-2008)
Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden OPERATOR LICENSING estimate to the Records and FOIA/Privacy Services Branch (T-5 F53), U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information EXAMINATION DATA and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503.
If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
FACILITY NRC REGION Sequoyah Nuclear Plant Region II A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2012 Cy 2012 Cy 2013 Cy 2013 ESTIMATED NUMBER OF LICENSEE-PREPARED 1
1 1
1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0
0 0
0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2012 CY 2 0 12 Cy 2013 CY 2013 NUMBER OF REACTOR 2
10 10 10 OPERATORS NUMBER OF SENIOR REACTOR 9
5 5
5 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR 2
OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR 0
0 0
0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE 01/17/2012 11/26/2012 05/13/2013 12/02/2013 ALTERNATE DATE 01/23/2012 12/03/2012 05/20/2013 12/09/2013 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2012 CY 2013 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0
18 0
0 0
18 0
0 CANDIDATES NRC FORM 536 (10-2008)
PRINTED ON RECYCLED PAPER
NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 10/31/2011 (10-2008)
Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden OPERATOR LICENSING estimate to the Records and FOIA/Privacy Services Branch (T-5 F53), U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information EXAMINATION DATA and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503.
If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
FACILITY NRC REGION Sequoyah Nuclear Plant Region II A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2014 Cy 2015 CY CY ESTIMATED NUMBER OF LICENSEE-PREPARED 1
1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0
0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 20 1 4 CY 2 0 1 5 CY CY NUMBER OF REACTOR 10 4
OPERATORS NUMBER OF SENIOR REACTOR 8
4 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR 2
2 OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR 0
0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE 12/01/2014 10/12/2015 ALTERNATE DATE 12/08/2014 10/19/2015 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY CY PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF CANDIDATES NRC FORM 536 (10-2008)