MONTHYEARML23178A0352023-06-27027 June 2023 Senior Reactor and Reactor Operator Initial License Examinations RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23005A1062023-01-0505 January 2023 Requalification Program Inspection ML22235A7202022-06-14014 June 2022 Administrative Files ML22299A0102022-05-11011 May 2022 Final Qa/Related Forms RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML21105A6592021-04-20020 April 2021 March 10, 2021, NRC Generic Fundamentals Examination Results for Peach Bottom Atomic Power Station, Units 2 and 3 (Cover Letter Publicly Available, Enclosures Withheld from Public) ML21069A1432021-03-10010 March 2021 Senior Reactor and Reactor Operator Initial License Examinations ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML21012A0542021-01-12012 January 2021 Requalification Program Inspection ML20261H4032020-09-17017 September 2020 Senior Reactor and Reactor Operator Initial License Examinations ML20260H1632020-06-30030 June 2020 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML21056A2202020-06-30030 June 2020 Final Qa/Related Forms (Folder 1) ML20260H1672020-06-30030 June 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML20260H1662020-06-30030 June 2020 Draft Written Examination (Folder 2), Test Answer Key ML20184A2482020-06-30030 June 2020 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML20260H1642020-06-30030 June 2020 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML20184A2472020-06-30030 June 2020 Final Operating Test (Sections a, B, and C) (Folder 3) ML20260H1652020-06-30030 June 2020 Draft Written Examination and Operating Test Outlines (Folder 2) ML21056A2212020-06-30030 June 2020 Final Qa/Related Form - Form ES-401-6 (Folder 1) ML21056A2232020-06-30030 June 2020 Final Written Examination and Operating Test Outlines (Folder 3) ML20147A1662020-05-26026 May 2020 Operator Licensing Examination Approval ML20105A1822020-04-14014 April 2020 March 4, 2020, NRC Generic Fundamentals Examination Results for Peach Bottom Atomic Power Station, Units 2 and 3 (Cover Letter Publicly Available, Enclosures Withheld from Public) ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML19275E4622019-09-30030 September 2019 Senior Reactor and Reactor Operator Initial License Examinations RS-19-053, Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations2019-05-16016 May 2019 Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML19120A3312019-04-29029 April 2019 March 6, 2019, NRC Generic Fundamentals Examination Results for Peach Bottom Atomic Power Station (Cover Letter Publicly Available, Enclosures Withheld from Public) ML19079A0232019-03-19019 March 2019 Licensed Operator Positive Fitness-For-Duty Test ML19045A3702019-02-12012 February 2019 March 2019 GFE Cover Letter Ri ML18128A0062018-05-0707 May 2018 Senior Reactor and Reactor Operator Initial License Examinations RS-18-057, Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations2018-04-25025 April 2018 Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18086B0252018-02-16016 February 2018 Facility Cover Letter - Ri - March 2018 - GFE ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML18207A8602017-12-0808 December 2017 Response to Questions Pertaining to Licensed Operator ML17277A1532017-10-0303 October 2017 September 6, 2017, NRC Generic Fundamentals Examination Results for Peach Bottom Atomic Power Station (Cover Letter Publicly Available, Enclosures Withheld from Public) IR 05000277/20173012017-05-23023 May 2017 Initial Operator Licensing Examination Report 05000277/2017301 and 05000278/2017301 RS-17-070, Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations2017-05-0303 May 2017 Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17186A3172017-05-0303 May 2017 Final Qa/Related Forms (Folder 1) ML17072A3262017-03-10010 March 2017 Units 2 and 3 Initial Operator Licensing Operating Test and Written Examination Approval ML17034A4662017-02-0202 February 2017 Requalification Program Inspection - Peach Bottom Atomic Power Station, Units 2 and 3 ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 IR 05000277/20153012015-05-18018 May 2015 Er 05000277/2015301; 05000278/2015301; March 23-30, 2015 and April 16, 2015; Peach Bottom Atomic Power Station, Units 2 and 3; Initial Operator Licensing Examination Report ML15131A2552015-05-0707 May 2015 Final Operating Exam (Sections a, B, and C) (Folder 3) ML15131A2562015-05-0707 May 2015 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML15174A0532015-05-0707 May 2015 Final Qa/Related Forms (Folder 1) ML15169A6482015-04-16016 April 2015 Handouts to Applications (Folder 3) ML15169A6512015-04-11011 April 2015 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML15103A1322015-04-10010 April 2015 Initial Operator Licensing Written Examination Approval (Peach Bottom, Units 2 and 3) ML15169A6462015-03-13013 March 2015 Final Outlines (Folder 3) ML15169A6542015-02-19019 February 2015 Draft Written Exam (Folder 2) 2023-06-27
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML23178A0352023-06-27027 June 2023 Senior Reactor and Reactor Operator Initial License Examinations RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML22235A7202022-06-14014 June 2022 Administrative Files ML22299A0102022-05-11011 May 2022 Final Qa/Related Forms RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML21069A1432021-03-10010 March 2021 Senior Reactor and Reactor Operator Initial License Examinations ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML20261H4032020-09-17017 September 2020 Senior Reactor and Reactor Operator Initial License Examinations ML20184A2482020-06-30030 June 2020 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML20260H1632020-06-30030 June 2020 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML20260H1642020-06-30030 June 2020 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML21056A2212020-06-30030 June 2020 Final Qa/Related Form - Form ES-401-6 (Folder 1) ML20260H1672020-06-30030 June 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML21056A2202020-06-30030 June 2020 Final Qa/Related Forms (Folder 1) ML21056A2232020-06-30030 June 2020 Final Written Examination and Operating Test Outlines (Folder 3) ML20184A2472020-06-30030 June 2020 Final Operating Test (Sections a, B, and C) (Folder 3) ML20260H1652020-06-30030 June 2020 Draft Written Examination and Operating Test Outlines (Folder 2) ML20260H1662020-06-30030 June 2020 Draft Written Examination (Folder 2), Test Answer Key ML20147A1662020-05-26026 May 2020 Operator Licensing Examination Approval ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML19275E4622019-09-30030 September 2019 Senior Reactor and Reactor Operator Initial License Examinations RS-19-053, Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations2019-05-16016 May 2019 Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML18128A0062018-05-0707 May 2018 Senior Reactor and Reactor Operator Initial License Examinations RS-18-057, Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations2018-04-25025 April 2018 Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17277A1532017-10-0303 October 2017 September 6, 2017, NRC Generic Fundamentals Examination Results for Peach Bottom Atomic Power Station (Cover Letter Publicly Available, Enclosures Withheld from Public) IR 05000277/20173012017-05-23023 May 2017 Initial Operator Licensing Examination Report 05000277/2017301 and 05000278/2017301 ML17186A3172017-05-0303 May 2017 Final Qa/Related Forms (Folder 1) RS-17-070, Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations2017-05-0303 May 2017 Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17072A3262017-03-10010 March 2017 Units 2 and 3 Initial Operator Licensing Operating Test and Written Examination Approval ML17034A4662017-02-0202 February 2017 Requalification Program Inspection - Peach Bottom Atomic Power Station, Units 2 and 3 ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 IR 05000277/20153012015-05-18018 May 2015 Er 05000277/2015301; 05000278/2015301; March 23-30, 2015 and April 16, 2015; Peach Bottom Atomic Power Station, Units 2 and 3; Initial Operator Licensing Examination Report ML15131A2552015-05-0707 May 2015 Final Operating Exam (Sections a, B, and C) (Folder 3) ML15174A0532015-05-0707 May 2015 Final Qa/Related Forms (Folder 1) ML15131A2562015-05-0707 May 2015 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML15169A6482015-04-16016 April 2015 Handouts to Applications (Folder 3) ML15169A6512015-04-11011 April 2015 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML15103A1322015-04-10010 April 2015 Initial Operator Licensing Written Examination Approval (Peach Bottom, Units 2 and 3) ML15169A6462015-03-13013 March 2015 Final Outlines (Folder 3) ML15169A6542015-02-19019 February 2015 Draft Written Exam (Folder 2) ML15169A6492015-02-13013 February 2015 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML15169A6562015-01-23023 January 2015 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML15169A6522015-01-23023 January 2015 Draft - Outlines (Folder 2) ML15012A0212015-01-0808 January 2015 Requalification Program Inspection-Peach Bottom Atomic Power Station, Units 2 and 3 ML14302A0202014-10-28028 October 2014 Senior Reactor and Reactor Operator Initial License Examinations: Peach Bottom Atomic Power Station, Units 2 and 3 ML13312A0542013-11-0707 November 2013 September 4, 2013,NRC Generic Fundamentals Examination Results for Peach Bottom (Cover Ltr) IR 05000277/20133012013-05-0909 May 2013 Er 05000277-13-301 & 05000278-13-301, March 25-28, 2013, and April 4, 2013, Peach Bottom Atomic Power Station, Units 2 and 3, Initial Operator Licensing Examination Report ML13182A5742013-04-16016 April 2013 Final Qa/Related Forms (Folder 1) ML13098A2562013-04-0101 April 2013 Final Written Examination with Answer Key (401-5 Format) (Folder 3) 2023-06-27
[Table view] Category:Letter
MONTHYEARML24022A2262024-01-22022 January 2024 (PBAPS) Unit 3 - Submittal of the Inservice Inspection (ISI) Owner'S Activity Report (OAR) for the 24th Refueling Outage for Unit 3 ML23346A2412024-01-17017 January 2024 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information (EPID L-2019-PMP-0061) - Letter IR 05000277/20234022024-01-11011 January 2024 Security Baseline Inspection Report 05000277/2023402 and 05000278/2023402 and Independent Spent Fuel Storage Installation Security Inspection 07200029/2023401 ML23354A1922024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML23355A0622023-12-18018 December 2023 Independent Spent Fuel Storage Installation (Isfsi), Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23334A2502023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23305A3472023-11-0101 November 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) IR 05000277/20230032023-10-30030 October 2023 Integrated Inspection Report 05000277/2023003 and 05000278/2023003 and Exercise of Enforcement Discretion ML23286A0012023-10-13013 October 2023 Reply to a Notice of Violation (NOV) - NOV 05000277, 05000278/2023010-01 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23271A1342023-10-11011 October 2023 Dtf Analysis Letter IR 05000277/20244012023-10-0505 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000277/2024401 and 05000278/2024401 ML23265A1502023-09-22022 September 2023 License Amendment Request Revise a License Condition and Certain Technical Specifications to Remove Restrictions in Support of Decommissioning Activities ML23264A8682023-09-21021 September 2023 Independent Spent Fuel Storage Installation Registration of Dry Storage Canister WC-EOS-37PTH-008-B4L, WC-EOS-37PTH-007-B4L, and WC-EOS-37PTH-002-B4L IR 05000277/20230102023-09-15015 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000277/2023010 and 05000278/2023010 and Notice of Violation ML23251A2022023-09-11011 September 2023 Cover Letter W/Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement IR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23232A0012023-08-19019 August 2023 Revision of One Procedure That Implements the Radiological Emergency Response Plan (Rerp). Includes EPP 06-009, Rev. 13 IR 05000277/20230112023-08-15015 August 2023 Comprehensive Engineering Team Inspection Report 05000277/2023011 and 05000278/2023011 ML23226A1112023-08-14014 August 2023 10 CFR 50.46 Annual Report IR 05000277/20230022023-08-0808 August 2023 Integrated Inspection Report 05000277/2023002 and 05000278/2023002 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor IR 05000277/20230402023-07-17017 July 2023 95001 Inspection Supplemental Report 05000277/2023040 and Follow-Up Assessment Letter ML23188A0532023-07-0707 July 2023 Registration of Use of Independent Spent Fuel Storage Installation (ISFSI) Casks ML23186A1272023-07-0606 July 2023 Response to Disputed Non-Cited Violation Documented in Peach Bottom Atomic Power Station, Units 2 and 3, Inspection Report 05000277/2022004 and 05000278/2022004 ML23178A0352023-06-27027 June 2023 Senior Reactor and Reactor Operator Initial License Examinations RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23151A4162023-05-31031 May 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) ML23150A2052023-05-30030 May 2023 Independent Spent Fuel Storage Installation (Isfsi), Annual Radiological Environmental Operating Report 80 January 1, 2022 Through December 31, 2022 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23142A1602023-05-23023 May 2023 Summary of April 11, 2023, Public Observation Meeting with Constellation Energy Generation, LLC Re Proposed Exemption Request from Work Hour Requirements ML23132A1582023-05-18018 May 2023 Correction to Technical Specification 3.4.7 (Page 3.4-16) Issued in Amendment No. 337 ML23132A1532023-05-12012 May 2023 Transmittal of 2022 Annual Financial Reports WM 23-0009, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2023-05-10010 May 2023 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) IR 05000277/20230012023-05-0808 May 2023 Integrated Inspection Report 05000277/2023001 and 05000278/2023001 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI 2024-01-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSTA, PA 19406-1415 January Zj,, 201,1 Mr. MichaelJ. Pacilio Senior Vice President, Exelon Generation Company, LLC President and Ghief Nuclear Officer, Exelon Nuclear 4300 Winfield Rd.
Warrenville, lL 60555
SUBJECT:
OPERATOR LICENSING EXAMINATION APPROVAL -
PEACHBoTToMAToMlcPoWERSTATloN,UNlTS2AND3
Dear Mr. Pacilio:
operator The purpose of this letter is to confirm the final arrangements for the upcoming Units 2 and 3' ticensing examinations at Peach Bottom Atomic Power station in connection The NRC has completed its review of the operator license applications submitted t9 lvlt A' Wasong' with this examination and separately provided a list of approved applicants have been Director of Training. Note that any examination waivers and application denials addressed in separate correspondence.
you to administer the The NRC has approved the subject examinations and hereby authorizes Licensing Examination written examinations in accordahce with NUREG-1021, "Operator The NRC Standards for Power Reactors," Revision 9, Supplement 1, on February 10,?011' February 7 ' 2011' staff will administer the operating tests during the weeks of January 31 and responsible This examination has undergone extensive 6view by my staff and representatives this review, I have concluded that the for licensed operatoitrainini at your facility. Based on
-1021for content, operational,3ld discrimination examination meets tnl guioltines of NUREG u"fiOity. By administeririg this examination, you also a_gree that it meets NUREG-1021 applicants at guiOefines, and is approfriate for measuring tne qualifiiations of licensed operator is not appropriate for^licjnsing operators at lour facility. lf you deteimine that this exariination your facility, do not administer the examination and contact me at (610) 337-5046' if you have Please contact your Chief Examiner, Mr. Joseph M. D'Antonio, at (610) 337-5085, any questions or identify any errors or changes in the license level (RO or SRO) or type of examination (partial o, written exJmination and/or operating test) specified for each applicant. "orptete
/
.]- A___er)
Samuel L. Hansell, Jr., Chief Operations Branch Division of Reactor SafetY Docket Nos. 50-277', 50-278 License Nos.: DPR-44, DPR-56 cc: Distribution via ListServ
January 21,2011 Mr. MichaelJ. Pacilio Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Rd.
Warrenville, lL 60555
SUBJECT:
OPERATOR LICENSING EXAMINATION APPROVAL -
PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3
Dear Mr. Pacilio:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at Peach Bottom Atomic Power Station Units 2 and 3.
The NRC has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to Mr. A. Wasong, Director of Training. Note that any examination waivers and application denials have been addressed in separate correspondence.
The NRC has approved the subject examinations and hereby authorizes youlo administer the written examinations in accordance with NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 9, Supplement 1, on February 10,2011 . The NRC staff will administer the operating tests during the weeks of January 31 and February 7,2011.
This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guideiines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. lf you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at (610) 337-5046.
Please contact your Chief Examiner, Mr. Joseph M. D'Antonio, at (610) 337-5085, if you have any questions oi identify any errors or changes in the license level (RO or SRO) or type of eximination (partial or complete written examination and/or operating test) specified for each applicant.
Sincerely,
/RN Samuel L. Hansell, Jr., Chief Operations Branch Division of Reactor Safety Docket Nos. 50-277: 50-278 License Nos.: DPR-44. DPR-56 cc: Distribution via ListServ SUNSI Review Complete: SLH (ReviewePs Initials)
ADAMS PKG: MLlO222O2O1 ADAMS NO.: ML110210429 DOCUMENT NAME: G:\DRS\Operations Branch\DANTONIO\Exam 11-PB Jan 11 (U01769)\PBExamApprovalltr.doc After declarinq this document "An OfficialAqencv Record," it will be released to the Public.
DATE 112112011 RECORD COPY
M. J. Pacilio Distribution w/encl: (via E-mail)
W. Dean, RA D. Lew, DRA J. Clifford, DRP G. Dentel, DRP D. Roberts, DRS P. Wilson, DRS S. Hansell, DRS J. D'Antonio, Chief Examiner, DRS P. Krohn, DRP A. Rosebrook, DRP S. lbarrola, DRP E. Torres, DRP F. Bower, DRP, SRI A. Ziedonis, DRP, Rl S. Schmitt, DRP, OA G. Miller, Rl OEDO D. Bearde, DRS RidsNrrPMPeachBottom Resource RidsNrrDorlLpl 1 -2Resource RO Prepo rtsResou rce@ n rc. q ov DRS Master Exam File (C. Bixler) (w/concurrences)