ML110050111

From kanterella
Jump to navigation Jump to search
2010 Fermi Initial License Examination ES-201-1
ML110050111
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 09/03/2010
From: David Reeser
Operations Branch III
To:
Detroit Edison
References
50-341/10-301
Download: ML110050111 (1)


Text

ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Fermi 2 Date of Examination: Aug 30, 2010 Developed by: Written - Facility NRC

// Operating - Facility NRC Target Date*

Task Description (Reference)

Chief Examiners Initials 1/13/2010

1.

Examination administration date confirmed (C.1.a; C.2.a and b)

DWR - 1/11/10 1/22/2010

2.

NRC examiners and facility contact assigned (C.1.d; C.2.e)

DWR - 1/11/10 1/22/2010

3.

Facility contact briefed on security and other requirements (C.2.c)

DWR - 1/11/10 1/22/2010

4.

Corporate notification letter sent (C.2.d)

DWR - 1/20/10 2/12/2010

[5.

Reference material due (C.1.e; C.3.c; Attachment 3)]

DWR - 2/5/10 3/15/2010

6.

Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and ES-401-4, as applicable (C.1.e and f; C.3.d)

DWR - 3/10/10 N/A

{7.

Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e)}

N/A 7/26/2010

8.

Proposed examinations (including written, walk-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any Form ES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d)

DWR - 8/4/10 7/30/2010

9.

Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; ES-202)

DWR - 8/6/10 8/13/2010

10.

Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; ES-202)

DWR - 8/20/10 8/6/2010

11.

Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f)

DWR - 8/6/10 8/9/2010

12.

Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g)

DWR - 8/13/10 8/23/2010

13.

Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h)

DWR - 8/26/10 8/23/2010

14.

Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; Attachment 5; ES-202, C.2.e; ES-204)

DWR - 8/26/10 8/23/2010

15.

Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k)

DWR - 9/3/10 8/23/2010

16.

Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i)

DWR - 8/26/10

  • Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.

[Applies only] {Does not apply} to examinations prepared by the NRC.