Bellefonte Nuclear Plant, Units 3 & 4 COL Application Part 2, FSAR Revision 3 16-i CHAPTER 16 TECHNICAL SPECIFICATIONS TABLE OF CONTENTS Section Title Page 16.1 TECHNICAL SPECIFICATIONS....................................................... 16.1-1 16.
1.1 INTRODUCTION
TO TECHNICAL SPECIFICATIONS............... 16.1-1 16.2 DESIGN RELIABILITY ASSURANCE PROGRAM........................... 16.2-1 16.3 INVESTMENT PROTECTION........................................................... 16.3-1 16.3.1 INVESTMENT PROTECTION SHORT-TERM AVAILABILITY CONTROLS................................................................................. 16.3-1 16.3.2 COMBINED LICENSE INFORMATION....................................... 16.3-1
Bellefonte Nuclear Plant, Units 3 & 4 COL Application Part 2, FSAR Revision 3 16.1-1 CHAPTER 16 TECHNICAL SPECIFICATIONS 16.1 TECHNICAL SPECIFICATIONS Subsections 16.1.1 and 16.1.2 of the DCD are incorporated by reference with the following departures and/or supplements. The generic technical specifications and bases in Chapter 16 of the DCD are not considered Tier 2 information; therefore they are not incorporated by reference within this FSAR. However, the generic technical specifications and bases provided with Chapter 16 of the DCD are incorporated directly into the plant-specific technical specifications and bases provided in Part 4 of this COL application.
The plant-specific Technical Specifications include an allowable primary containment leakage rate of 0.09% of primary containment air weight per day.
This departure from the DCD Generic Technical Specifications and Bases is described and justified in Parts 4 and 7 of the COL application.
16.
1.1 INTRODUCTION
TO TECHNICAL SPECIFICATIONS Combined License Information This COL Item (i.e., information addressing each of the remaining brackets [ ] in the AP1000 generic technical specifications) is addressed in Part 4 of the COLA.
Bellefonte Nuclear Plant, Units 3 & 4 COL Application Part 2, FSAR Revision 3 16.2-1 16.2 DESIGN RELIABILITY ASSURANCE PROGRAM This section of the referenced DCD is incorporated by reference with no departures or supplements.
Bellefonte Nuclear Plant, Units 3 & 4 COL Application Part 2, FSAR Revision 3 16.3-1 16.3 INVESTMENT PROTECTION This section of the referenced DCD is incorporated by reference with the following departures and/or supplements.
16.3.1 INVESTMENT PROTECTION SHORT-TERM AVAILABILITY CONTROLS Add the following paragraph after the bulleted items at the end of the second paragraph of DCD Subsection 16.3.1:
Station procedures govern and control the operability of investment protection systems, structures, and components, in accordance with Table 16.3-2 of the DCD, and provide the operating staff with instruction for implementing required actions when operability requirements are not met. Procedure development is addressed in FSAR Section 13.5.
16.3.2 COMBINED LICENSE INFORMATION This COL Item is addressed in Subsection 16.3.1.