ML110040670

From kanterella
Jump to navigation Jump to search
Bellefonte Units 3 & 4 Cola (Final Safety Analysis Report), Rev. 3 - FSAR Chapter 02 Figure 2.4.12-207
ML110040670
Person / Time
Site: Bellefonte  
Issue date: 12/22/2010
From: Arent G
Tennessee Valley Authority
To:
Document Control Desk, Office of New Reactors
Spink T
References
BELLEFONTE.P02.NP, BELLEFONTE.P02.NP.3, TENNVALLEY, TENNVALLEY.SUBMISSION.6, +reviewedmmc1
Download: ML110040670 (1)


Text

BLN COL 2.4-4 Rev 1 Bellefonte Nuclear Plant, Units 3 & 4 COL Application Part 2, FSAR March 2005 Groundwater Potentiometric Surface Map FIGURE 2.4.12-207 Note: The March 2005 reading from Well W29 is considered an anomalous reading, and the water level and interpretation of the groundwater elevations in the vicinity of Well W29 depicted in this figure are not considered in current groundwater evaluations.