UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 December 23. 2010 MN No.11-001 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF LICENSEE MEETING Licensee:
Dominion Nuclear Connecticut, Inc.
Facility:
Millstone Power Station Unit 2 and 3 Docket Nos:
50-336,50-423 DatelTime:
January 6, 2011 10:00 a.m. to 12:00 p.m.
Location:
NRC Region I Office, Public Meeting Room 475 Allendale Road King of Prussia, PA 19406
Purpose:
Dominion Nuclear Connecticut, Inc. requested a Regulatory Conference with the NRC to discuss a potential greater-than-Green security-related NRC identified finding identified on August 18, 2010. The nature of security-related greater-than-Green findings is considered to be sensitive information and is not included in this notice.
Category:
This meeting will be closed to the public because the staff has determined that the information is security-sensitive in nature.
Attendees:
NRC:
W. Dean, Regional Administrator, Region I D. Roberts, Director, Division of Reactor Safety, Region I J. Trapp, Chief, Plant Support Branch 1, Region I D. Jackson, Chief, Projects Branch 5, Region I D. Holody, Team Leader, Enforcement, Region I M. McLaughlin, Senior Enforcement Specialist, Region I J. Willis, Security Specialist, Office of Nuclear Security and Incident Response K. Farrar, Regional Counsel, Region I D. Caron, Senior Physical Security Inspector, Region I J. Cherubini, Physical Security Inspector, Region I
~------------...... ---~ - -
2 Licensee:
A.J. Jordan, Site Vice President R. MacManus, Director Nuclear Safety and Licensing W. Bartron, Supervisor Licensing J. Curling, Manager of Nuclear Protection Services M. Brown, Supervisor, Security Operations L. Hart, Vice President Nuclear Support Services P. Blasioli. Director Nuclear Protection Services and Emergency Preparedness N. Martin, Manager Nuclear Fleet Protection Services Meeting
Contact:
James M. Trapp, Chief, Plant Support Branch 1 610-337-5186 E-mail: James.Trapp@nrc.gov Handicapped persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than 2 business days prior to the meeting.
Attendance by NRC personnel at this meeting should be made known by December 27,2010, via telephone to the NRC meeting contact.
Approved BY~'.f<sy James M. Trapp. Chief Plant Support Branch 1 Division of Reactor Safety cc w/encl: Distribution via ListServ
Agenda Regulatory Conference Millstone Power Station January 6, 2011 10:00 am - 12:00 pm Introductions.......................................................................................... NRC (5 minutes)
Discussion of Regulatory Process............................................................ NRC (5 minutes)
SOP Determination.....................................................................NRC (10 minutes)
Dominion Staff Provides Additional Information............................... Millstone (60 minutes)
NRC Questions and Dialogue.......................................................... Millstone (30 minutes)
Closing Remarks................................................................................
NRC (10 minutes)
2 Licensee:
S. Jordan, Site Vice President R. MacManus, Director Nuclear Safety and licensing
. W. Bartron, Supervisor Licensing J. Curling, Manager of Nuclear Protection Services M. Brown, Supervisor, Security Operations L Hart, Vice President Nuclear Support Services P. Blasioli, Director Nuclear Protection Services and Emergency Preparedness N. Martin, Manager Nuclear Fleet Protection Services Meeting
Contact:
James M. Trapp, Chief, Plant Support Branch 1 610-337-5186 E-mail: James.Trapp@nrc.gov Handicapped persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than 2 business days prior to the meeting.
Attendance by NRC personnel at this meeting should be made known by December 27,2010, via telephone to the NRC meeting contact.
IRA by Peter R. Wilson Acting ForI Approved By: __~~_--::-::-:--::--__
James M. Trapp. Chief Plant Support Branch 1 Division of Reactor Safety cc w/encl: Distribution via ListServ SUNSI Review Complete: _.....i.:..:rc=--__ (Reviewer's Initials)
ML103570323 DOCUMENT NAME: G:\\DRS\\PLANT SUPPORT BRANCH 1\\SECURITy\\MILLSTONE REG CONFERENCE AND PUBLIC MTG NOTICE\\MILLSTONE PUBLIC MEETING NOTICE 2010.DOCX After declaring this document "An Official Agency Record" it will be released to the Public.
OFFICE RI/DRS RIIOPA RIIORA NAME DCaron/dcc DScrenci/d s M.McLaughlin/mmm DATE 12/22/10 12/22110 12/22110 OFFICIAL RECORD COpy
3 Distribution w/encl: (via emaH)
Executive Director for Operations, OEDO (RIDSEDOMAILCENTER RESOURCE)
Deputy Executive Director for Reactor Programs, OEDO (RIDSEDOMAILCENTER RESOURCE)
Director, Office of Nuclear Reactor Regulation, NRR (RIDSNRROD)
Associate Director, Office of Operating Reactor Oversight and Licensing, NRRlADRO (RIDSNRRADRO)
Director, Division of Inspection and Regional Support, NRRlDIRS (RIDSNRRDIRS)
Director, Division of Operating Reactor Licensing, NRRlDORL (RIDSNRRDORL)
Project Directorate 1-1 (PD1/2), NRR (RIDSNRRDORILPI1-2)
Asst. General Counsel Materials Litigation and Enforcement, OGC (RIDSOGCMAILCENTER)
W. Dean, RA (R10RAMAIL RESOURCE)
M. Dapas, ORA (R10RAMAIL RESOURCE)
D. Lew, DRP (R1DRPMAIL RESOURCE)
J. Clifford, DRP (R1DRPMAIL RESOURCE)
D. Roberts, DRS
{R1DRSMAIL RESOURCE}
P. Wilson, DRS (R1DRSMAIL RESOURCE)
D. Jackson, DRP T. Setzer, DRP D. Dodson, DRP S. Shaffer, DRP, SRI B. Haagensen, RI J. Krafty, DRP, RI C. Kowalyshyn, OA G. Miller, RI OEDO D. Bearde, DRS RidsNRRPM Millstone Resource Ridsl\\lRRDorlLpl1-2 Resource ROPreportsResource@nrc.gov RI Receptionist