ML102980471
| ML102980471 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 07/22/2010 |
| From: | Arthur Burritt Reactor Projects Branch 3 |
| To: | Leonard Cline Reactor Projects Branch 3 |
| References | |
| FOIA/PA-2010-0334 | |
| Download: ML102980471 (2) | |
Text
Burritt, Arthur From:
Burritt, Arthur Sent:
Thursday, July22, 10 11:16 AM To:
Cline, Leonard
Subject:
FW: Inspection Schedule Change FYI From: Kaufman, Paul Sent: Thursday, July 22, 2010 9:55 AM To: OHara, Timothy Cc: Conte, Richard; Burritt, Arthur; Schroeder, Daniel
Subject:
RE: Inspection Schedule Change Your Salem PI&R sample is now scheduled in RPS for Sept. 20-24, 2010 related to root cause for buried piping.
Paul From: 01lr, ioh Sent: Tuesday, July 20, 2010 10:51 AM To: Kaufman, Paul
Subject:
RE: Inspection Schedule Change
- Paul, I scheduled this sample for the week of 7/26 as a place holder - so it may not be scheduled correctly at present. PSEG has not provided all of the documents for the sample yet - (1) EQ:ACE for corroded AFW piping (I have this), and (2) Root Cause for missing the IWA-5244 pressure tests of buried piping (we don't have this yet). I have a list of comments/observations/concerns which we weren't permitted to document because the cause determinations weren't done at the time.
This is under our branch and was agreed to by Projects (Art Burritt). We couldn't end the ISI until we got these documents but the licensee wasn't done with them yet. So we exited on 6/28 with the understanding that we' would do a PI&R sample when these documents were completed - to ensure that PSEG addressed all the PI&R concerns.
What else do you need?
Tim From: Kaufman, Paul Sent: Tuesday, July 20, 2010 10:22 AM To: OHara, Timothy
Subject:
RE: Inspection Schedule Change Could you please provide me with more info related to the Salem PI&R sample that you want changed from the week of July 26 to the week of September 20. What does the PI&R sample pertain to and which DRS branch was it assigned to after the EOC meeting?
- Thanks, Paul while on Annual Leave 11
From: OHara, Timothy Sent: Tuesday, July 20, 2010 7:24 AM To: Kaufman, Paul
Subject:
Inspection Schedule Change Hello Paul, I know you're on leave at present. When you're back, can you please reschedule the PI&R sample at Salem from the week of July 26 to the week of September 20. I'll be the inspector. Thanks.
Tim 12