Schroeder, Daniel From:
Conte, Richard Sent:
Friday, April 23, 2010 4:31 PM To:
Burritt, Arthur; OHara, Timothy; Gray, Harold; Schroeder, Daniel; Balian, Harry; Cahill, Christopher Cc:
Cline, Leonard; Douglas, Christopher; Lew, David; Clifford, James; Roberts, Darrell; Lupold, Timothy
Subject:
RE: Salem AFW Priorities/Next Steps nice job well coordinated effort; no surprises.
From: Burritt, Arthur Sent: Friday, April 23, 2010 4:27 PM To: Conte, Richard; OHara, Timothy; Gray, Harold; Schroeder, Daniel; Balian, Harry; Cahill, Christopher Cc: Cline, Leonard; Douglas, Christopher; Lew, David; Clifford, James
Subject:
Salem AFW Priorities/Next Steps Why is Unit 2 Ok Testing Confirm the PSEG risk assessment to delay AFW testing is reasonable - Cahill Evaluate pressure drop testing resolution" Operability Evaluate the Unit 2 AFW extent of condition operability assessment (focus on the differences between Unit 1 & 2) -
Schroeder/O'Hara Confirm the finite element analysis for the Unit 1 as found condition is acceptable including the use of appropriate methods and assumptions - O'Hara/HQ Confirm the technical evaluation that supports 1275 psig is bounding (including a faulted S/G scenario) - complete no concerns What Needs to be Done Prior to Unit Startup Verify hydro/pressure test is code compliant - O'Hara Evaluate the 50.59 for AFW modifications - O'Hara Verify the ANI reviews and accepts repairs including testing - O'Hara Smart samples o
Verify repairs to the control air system elbow that was replaced (how will PSEG certify the repair) - O'Hara o
Verify control air pipe coating are repaired including at the support clamps (visual check of the as left condition) - O'Hara Long Term Concerns AFW coating cure time acceptability I.
Schroeder, Daniel From:
Schroeder, Daniel Sent:
Monday, April 26, 2010 11:26 AM To:
Conte, Richard
Subject:
RE: Salem AFW Priorities/Next Steps
- Rich, I copied Wayne and Chris on the updated risk assessment when I sent it to Art.
Dan From: Conte, Richard Sent: Monday, April 26, 2010 11:24 AM To: Burritt, Arthur; OHara, Timothy; Gray, Harold; Schroeder, Daniel; Balian, Harry; Cahill, Christopher
Subject:
RE: Salem AFW Priorities/Next Steps I never got the revised risk assessment or Unit 2 operability determination from Friday, I only have the one related to 7 day extension.
Did our SRAs Chris or Wayne get the one that extends them to next outage and is that acceptable in light of never doing the test - there is a TIA for another plant found by John Richmond that accepts this even though the test was never done.
From: Burritt, Arthur Sent: Friday, April 23, 2010 4:27 PM To: Conte, Richard; OHara, Timothy; Gray, Harold; Schroeder, Daniel; Balian, Harry; Cahill, Christopher Cc: Cline, Leonard; Douglas, Christopher; Lew, David; Clifford, James
Subject:
Salem AFW Priorities/Next Steps Why is Unit 2 Ok Testing Confirm the PSEG risk assessment to delay AFW testing is reasonable - Cahill Evaluate pressure drop testing resolution Operability Evaluate the Unit 2 AFW extent of condition operability assessment (focus on the differences between Unit 1 & 2) -
Schroeder/O'Hara Confirm the finite element analysis for the Unit 1 as found condition is acceptable including the use of appropriate methods and assumptions - O'Hara/HQ Confirm the technical evaluation that supports 1275 psig is bounding (including a faulted S/G scenario) - complete no concerns What Needs to be Done Prior to Unit Startup Verify hydro/pressure test is code compliant - O'Hara Evaluate the 50.59 for AFW modifications - O'Hara Verify the ANI reviews and accepts repairs including testing - O'Hara Smart samples o
Verify repairs to the control air system elbow that was replaced (how will PSEG certify the repair) - O'Hara o
Verify control air pipe coating are repaired including at the support clamps (visual check of the as left condition) - O'Hara Long Term Concerns AFW coating cure time acceptability 1