MONTHYEARML24032A0252024-02-0505 February 2024 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026-2023009 ML24010A0712024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports and Recordkeeping and Suspicious Activity Reporting) ML24031A6102024-01-31031 January 2024 Cyber Security Inspection Report 05200026/2024401 - Public ML24029A0592024-01-30030 January 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report Enclosure 2, GAE-NRCD-RF-LR-000002 P-Attachment, Rev. 0 ML24016A1132024-01-30030 January 2024 Correction of Unit 1 Amendment Nos. 96 and 190 and Unit 2 Amendment Nos. 74 and 173 Adoption of Standard Technical Specifications Westinghouse Plants NL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R232024-01-29029 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 IR 05000424/20244032024-01-26026 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000424/2024403; 05000425/2024403 NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23347A2092024-01-17017 January 2024 Voluntary Requests for Data, Information, And/Or Observation ML23279A0042024-01-17017 January 2024 Amendment No. 194 to Remove Combined License Appendix C NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) ML23317A2072023-12-22022 December 2023 Issuance of Amendments 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-1448 ML23335A1222023-12-19019 December 2023 Safety Evaluation Regarding Implementation of Mitigating Strategies Related to Order EA-12-049 (EPID L-2023-LRQ-0002) - Letter ML23353A1702023-12-19019 December 2023 LAR-22-002, TS 3.8.3 Inverters Operating Completion Time Extension Letter ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23338A2182023-12-0606 December 2023 Project Manager Reassignment NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 ML23318A4582023-11-14014 November 2023 Integrated Inspection Report 05200025/2023003 ML23312A3502023-11-14014 November 2023 Integrated Inspection Report 05200026/2023003 ML23306A3552023-11-0808 November 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 052000/262023008 ML23268A0572023-11-0707 November 2023 Issuance of Amendments 194 & 191 Request for License Amendment Relocation of Technical Specification 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003) IR 05000424/20234022023-11-0606 November 2023 Security Baseline Inspection Report 05000424/2023402 and 05000425/2023402 IR 05000424/20230032023-10-27027 October 2023 Integrated Inspection Report 05000424/2023003 and 05000425/2023003 ML23291A1512023-10-18018 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 0520026/2024401 ML23263A9852023-10-12012 October 2023 Issuance of Amendments Nos. 221 and 204, Regarding Technical Specification 5.5.11.C, Acceptance Criteria for Charcoal Filter Testing ML23283A0472023-10-0808 October 2023 Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0745, Refueling Outage 1R24 Steam Generator Tube Inspection Report2023-09-22022 September 2023 Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23254A2032023-09-13013 September 2023 Initial Test Program and Operational Programs Inspection Report 05200025/2023013 ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report ML23234A2352023-09-0808 September 2023 Request for Withholding Information from Public Disclosure Notification of Full Compliance of Required Action for NRC Order EA-12-049 Mitigation Strategies for Beyond-Design-Basis External Events IR 05000424/20230912023-09-0505 September 2023 Plan Units 1 and 2 - NRC Investigation Report 2-2022-006 and Notice of Violation - NRC Inspection Report 05000424/2023091 and 05000425/2023091 ML23234A3002023-09-0101 September 2023 NRC Integrated Inspection Report 05200026/2023003 ML23243A0092023-08-31031 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 & 4 (Report 05200025 2023005 & 05200026 2023005) NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2) ML23243B0252023-08-30030 August 2023 Exam Corporate Notification Letter (210 Day) IR 05000424/20230052023-08-29029 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2023005 and 05000425/2023005 NL-23-0666, License Amendment Request: Remove Combined License Appendix C (LAR 23-008)2023-08-28028 August 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-008) 2024-02-05
[Table view] |
Text
October 15, 2010 Mr. Mark J. Ajluni Director, Nuclear Licensing 40 Inverness Center Parkway P.O. Box 1295 Birmingham, AL 35201
Dear Mr. Ajluni:
On behalf of the U.S. Nuclear Regulatory Commission (NRC), I am responding to your July 14, 2010, letter requesting an exemption of licensing fees under 10 CFR 170.11(a)(1)(iii) for Vogtle Electric Generating Plant (VEGP) participating as a Improved Standard Technical Specifications (ISTS) pilot plant for the implementation of Risk Informed Technical Specification Task Force (RITSTF) Initiative 4B, Risk Informed Completion Times with Configuration Risk Management Program or Maintenance Rule Backstop. As explained below, while I am unable to grant a fee waiver under that part of our regulations since your request does not qualify as a special project, I am granting the fee waiver request in accordance with 10 CFR 170.11(b).
Your fee exemption request states that as part of the pilot program, Southern Nuclear Operating Company (SNC) will submit a license amendment request for VEGP Units 1 and 2 requesting NRC approval to implement this risk informed technical specification change. Furthermore, SNC states that the evaluation of this license amendment request is to assist in developing NRC regulatory guidance to endorse implementation of RITSTF Initiative 4B. The NRC staff has reviewed your request and concluded that your request meets the pilot program requirements. Hence, I am able to grant you a fee exemption under the provisions of 10 CFR 170.11(b), which states that the Commission may, grant such exemptions from the requirements of this part as it determines are authorized by law and are otherwise in the public interest.
You requested an exemption under 10 CFR 170.11(a)(1)(iii), which is applicable to special project fees. Our regulations state that a special project refers to a request for review for which fees are not otherwise specified in this chapter. Since licensing fees are specified in our regulations (e.g., staff review of a license amendment request), I was unable to grant you the fee exemption under that part of our regulations.
Although a fee exemption is granted, it is important to emphasize that the NRC is required by law to recover approximately 90 percent of its operating expenses through user fees. While the effort described in this letter is exempt from Part 170 direct fee assessment, NRC resources expended to resolve this issue will be included in annual fees assessed under the provisions of Part 171.
M. Ajluni If you have any technical questions regarding this matter, please contact Andrew Howe at 301-415-3078. Please contact Rebecca Erickson, of my staff, at 301-415-7126, for any fee related questions.
Sincerely,
/RA/
J. E. Dyer Chief Financial Officer
M. Ajluni If you have any technical questions regarding this matter, please contact Andrew Howe at 301-415-3078. Please contact Rebecca Erickson, of my staff, at 301-415-7126, for any fee related questions.
Sincerely,
/RA/
J. E. Dyer Chief Financial Officer Distribution:
R.Elliott, NRR/DIRS/ITSB, R.Suri, OCFO/DOC/ARPB W.Blaney, OCFO/DOC/ARPB OCFO RF (closes CFO-2010-0195)
DOC RF Adams: Yes No Initials: ______ SUNSI Review By: _rie1__
Publicly Available Non-Publicly Available Sensitive Non-Sensitive ADAMS Accession Number: ML Document: G:\DFM\Fee Policy Group\Fee Policy\FeeWaivers\Vogtle Pilot Plant Initiative 4B.docx
- Concurred via email To receive a copy of this document, indicate in the box:
C = Copy without enclosure E = Copy with enclosure N = No copy OFFICE OCFO/DOC/ARPB E OCFO/DOC/ARPB OCFO/DOC NAME RErickson** MWilliams* MKaplan DATE 10/14/10 10/13/10 10/14/10 OFFICE OCFO/DOC DCFO CFO NAME CRheaume MBrown /RA/ JDyer /RA/
DATE 10/14/10 10/14/10 10/15/10