MONTHYEARML23242A3382023-11-0606 November 2023 Examination Report Letter No. 50-020/OL-23-01, Massachusetts Institute of Technology ML23242A3392023-11-0606 November 2023 Examination Result Letter No. 50-020/OL-23-01, Massachusetts Institute of Technology ML16313A0092016-11-0909 November 2016 Examination Report No. 50-020/OL-17-01, Massachusetts Instutute of Technology ML13261A0832013-10-0101 October 2013 Examination Results Report, No. 50-20/OL-13-02, Massachusetts Institute of Technology ML13045A2802013-02-19019 February 2013 Examination Report No. 50-020/OL-13-01, Massachusetts Institute of Technology ML1129406062011-10-25025 October 2011 Examination Report, No. 50-020/OL-12-01, Massachusetts Institute of Technology ML1025716602010-09-17017 September 2010 Initial Examination Report, No. 50-020/OL-10-01, Massachusetts Institute of Technology ML1016100692010-06-17017 June 2010 Initial Examination Corporate Notification Letter No. 50-020/OL-10-01, Massachusetts Institute of Technology ML0726303032007-10-17017 October 2007 Initial Examination Report No. 50-020/OL-07-02, Massachusetts Institute of Technology Reactor (MITR-II) ML0710600202007-04-18018 April 2007 Initial Examination Results Letter No. 50-020/OL-07-01, Massachusetts Institute of Technology ML0710600152007-04-18018 April 2007 Initial Examination Report No. 50-020/OL-07-01, Massachusetts Institute of Technology ML0629102192006-10-20020 October 2006 Initial Examination Report No. 50-020/OL-06-01, Massachusetts Institute of Technology ML0527301912005-10-0707 October 2005 Inital Examination Report No. 50-20/OL-05-01, Massachusettes Institutes of Technology ML0427802362004-10-0808 October 2004 Initial Examination Report No. 50-20/OL-04-02, Massachusetts Institute of Technology ML0420803802004-07-30030 July 2004 Retake Examination Report No. 50-020/OL-04-01, Mit ML0406906912004-03-22022 March 2004 Initial Examination Report 50-20/OL-04-01, Massachusetts Institute of Technology ML0303606732003-02-14014 February 2003 Retake Examination Report No. 50-020/OL-03-01, Massachusetts Institute of Technology 2023-11-06
[Table view] Category:Letter
MONTHYEARML24022A0972024-01-22022 January 2024 Massachusetts Institute of Technology Change of Facility Backup Project Manager ML23354A1442024-01-0505 January 2024 Examination Confirmation Letter No. 50-020/OL-24-01, Massachusetts Institute of Technology IR 05000020/20232032023-11-21021 November 2023 Massachusetts Institute of Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000020/2023203 ML23242A3382023-11-0606 November 2023 Examination Report Letter No. 50-020/OL-23-01, Massachusetts Institute of Technology ML23242A3392023-11-0606 November 2023 Examination Result Letter No. 50-020/OL-23-01, Massachusetts Institute of Technology IR 05000020/20232012023-10-12012 October 2023 Massachusetts Institute of Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000020/2023201 IR 05000020/20232022023-09-27027 September 2023 Massachusetts Institute of Technology - U.S. Nuclear Regulatory Commission Security Inspection Report No. 05000020/2023202 ML23194A0412023-07-11011 July 2023 Mit Research Reactor - Duties of Reactor Superintendent ML23103A2632023-05-10010 May 2023 Examination Confirmation Letter No. 50-020/OL-23-01 Massachusetts Institute of Technology ML23094A1102023-03-30030 March 2023 Massachusetts Institute of Technology (Mit), Submittal of Annual Report for 2022, Technical Specification 7.7.1 ML23072A0242023-03-0707 March 2023 Mit, Nuclear Reactor Lab., Proposal for Conversion to Low Enriched Uranium (Leu), Mit Research Reactor IR 05000020/20222012023-02-0707 February 2023 Massachusetts Institute of Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000020/2022201 ML22189A0492022-07-25025 July 2022 Examination Confirmation Letter No.50-020/OL-22-02, Massachusetts Institute of Technology ML22095A2412022-03-31031 March 2022 Annual Report for the Mit Research Reactor for the Period from January 1, 2021, to December 31, 2021 ML22062B0422022-02-10010 February 2022 Proposal for Conversion to Low Enriched Uranium (Leu), Mit Research Reactor, Docket No. 50-20, 10 CFR 50.64 (c)(2)(ii) of That Paragraph ML21328A2342021-11-29029 November 2021 Examination Confirmation Letter No. 50-020/OL-22-01, Massachusetts Institute of Technology IR 05000020/20212032021-11-0909 November 2021 Massachusetts Institutes of Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000020/2021203 IR 05000020/20212012021-09-30030 September 2021 Massachusetts Institute of Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report 05000020/2021201 ML21186A0032021-07-16016 July 2021 Examination Confirmation Letter No. 50-020/OL-21-02, Massachusetts Institute of Technology ML21165A1542021-05-28028 May 2021 Mit - Emergency Plan and Procedures, 10 CFR 50.54(q)(5) ML21140A3622021-05-17017 May 2021 Massachusetts Institute of Technology (Mit) - Supplement to Response to the Request for Additional Information for Battery Upgrade License Amendment Request (EPID: L-2021 -NFA-0000) ML21132A2512021-05-0606 May 2021 Massachusetts Institute of Technology, License No. R-37, Docket No. 50-20, Reportable Occurrence 50-20/2021-: Operation with Less than the Required Staffing on Site; NRC OPS Center Log EN 55212 ML21112A1672021-04-12012 April 2021 Massachusetts Institute of Technology - Physical Security Plan Revision Regarding Biometric Readers ML21105A3602021-04-0707 April 2021 Duties of Reactor Superintendent ML21099A1132021-03-31031 March 2021 Massachusetts Institute of Technology - Annual Report, Docket No. 50-20, License R-37, Technical Specification 7.7.1 ML21091A2082021-03-24024 March 2021 Mit Nuclear Reactor Lab - Response to Request for Additional Information for Battery Upgrade License Amendment Request ML21076A0232021-03-18018 March 2021 Requests for Additional Information - Related to License Amendment Request to Replace Emergency Power System Batteries ML21070A1852021-03-0202 March 2021 Mit Nuclear Reactor Laboratory, License Amendment Request Regarding Emergency Battery Surveillances in Technical Specification 4.6, Docket No. 50-20, License R-37 ML21063A2552021-02-25025 February 2021 Proposal for Conversion to Low Enriched Uranium (Leu), :Mit Research Reactor, Docket No. 50-20, 10 CFR 50.64 (c)(2)(ii) of That Paragraph ML21053A4372021-02-23023 February 2021 Examination Confirmation Letter No. 50-020/OL-21-01, Massachusetts Institute of Technology ML21036A0852021-02-19019 February 2021 Massachusetts Institute of Technology - Acceptance of License Amendment Request to Revise Surveillance Frequency During Extended Reactor Shutdown ML21035A2582021-01-29029 January 2021 Massachusetts Institute of Technology (Mit), Supplement to Technical Specifications Surveillance Frequency Definition Update for Improved Compliance Under 10 CPR 50.36(c)(3) ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20307A4202020-11-0505 November 2020 Granting of Extension Request to Supplement License Amendment to Revise Surveillance Requirement Frequency ML20304A1172020-10-19019 October 2020 Time Extension Request for LAR on Technical Specifications Surveillance Frequency Update for Improved Compliance Under 10 CFR 50.36(c)(3) for the Mit Research Reactor ML20248H5682020-09-22022 September 2020 Mit Research Reactor Routine Inspection Report with Enforcement Discretion (EA-20-109) - August 2020 ML20161A3342020-07-24024 July 2020 Massachusetts Institute of Technology - Issuance of Amendment NO.44 to Renewed Facility Operation License No. R-37 to Amend Technical Specifications Related to Level 1 Position Title Change ML20182A7092020-07-0909 July 2020 Acceptance Review Amendment Request to Revise Surveillance Frequency - Opportunity to Supplement ML20192A0762020-06-30030 June 2020 Mit - Supplemental Information for License Amendment Request for Position Title Change in Technical Specifications for Level 1 Staff ML20070H2672020-06-0404 June 2020 Examination Report No. 50-020/OL-20-01, Massachusetts Institute of Technology ML20119A8272020-05-29029 May 2020 Massachusetts Institute of Technology - Issuance of Amendment No. 43 Extending Time to Implement License Amendment No. 42 to Facility Operating License No. R-37 ML20149K4142020-05-27027 May 2020 NRC LAR Extension Supplemental Letter 2020-05-27 ML20135H1882020-05-15015 May 2020 Massachusetts Institute of Technology - Exemption from Select Requirements of 10 CFR Part 55, Operators' Licenses ML20122A0622020-04-21021 April 2020 Massachusetts Institute of Technology, Regarding the, Amendment No. 42 to Renewed Facility Operating License No. R-37 for the Nuclear Safety System Digital Upgrade (Epdi No. L-2016-LLA-0003) ML20090E2272020-04-16016 April 2020 Massachusetts Institute of Technology - Acceptance of the Application for a License Amendment Level 1 Position Title Change ML20097B6932020-03-31031 March 2020 Amendment No. 42 to Renewed Facility Operating License No. R-37 Regarding the Nuclear Safety System Digital Upgrade (Epdi No. L-2016-LLA-0003) ML20097D2992020-03-27027 March 2020 Massachusetts Institute of Technology (Mit) - Annual Report for the Year 2019 ML20078J4852020-03-12012 March 2020 Massachusetts Institute of Technology (Mit), License Amendment Request for Position Title Change in Technical Specifications for Level 1 Staff ML20055D3322020-02-18018 February 2020 Proposal for Conversion to Low Enriched Uranium (Leu), Mit Research Reactor, Docket No. 50-20, 10 CFR 50.64 (c)(2)(ii) of That Paragraph IR 05000020/20192032020-01-15015 January 2020 Massachusetts Institute of Technology U.S. Nuclear Regulatory Commission Security-Related Inspection Report 05000020/2019203 2024-01-05
[Table view] |
Text
September 17, 2010 Dr. John A. Bernard, Jr.
Director of Reactor Operations Massachusetts Institute of Technology Research Reactor MITNRL-NW 12 138 Albany Street Cambridge, MA 02139
SUBJECT:
INITIAL EXAMINATION REPORT NO. 50-20/OL-10-01, MASSACHUSETTS INSTITUTE OF TECHNOLOGY
Dear Dr. Bernard:
During the week of September 6, 2010, the U. S. Nuclear Regulatory Commission (NRC) administered an operator licensing examination at your Massachusetts Institute of Technology Reactor. The examination was conducted according to NUREG-1478, "Operator Licensing Examiner Standards for Research and Test Reactors," Revision 2. Examination questions and preliminary findings were discussed with those members of your staff identified in the enclosed report at the conclusion of the examination.
In accordance with Title 10 of the Code of Federal Regulations Section 2.390, a copy of this letter and the enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. The NRC is forwarding the individual grades to you in a separate letter which will not be released publicly. Should you have any questions concerning this examination, please contact Mr. Phillip T. Young at 301-415-4094 or via internet e-mail phillip.young@nrc.gov.
Sincerely,
/RA/
Johnny H. Eads, Jr., Chief Research and Test Reactors Oversight Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-20
Enclosures:
- 1. Initial Examination Report No. 50-20/OL-10-01 cc without enclosures: See next page
September 17, 2010 Dr. John A. Bernard, Jr.
Director of Reactor Operations Massachusetts Institute of Technology Research Reactor MITNRL-NW 12 138 Albany Street Cambridge, MA 02139
SUBJECT:
INITIAL EXAMINATION REPORT NO. 50-20/OL-10-01, MASSACHUSETTS INSTITUTE OF TECHNOLOGY
Dear Dr. Bernard:
During the week of September 6, 2010, the U. S. Nuclear Regulatory Commission (NRC) administered an operator licensing examination at your Massachusetts Institute of Technology Reactor. The examination was conducted according to NUREG-1478, "Operator Licensing Examiner Standards for Research and Test Reactors," Revision 2. Examination questions and preliminary findings were discussed with those members of your staff identified in the enclosed report at the conclusion of the examination.
In accordance with Title 10 of the Code of Federal Regulations Section 2.390, a copy of this letter and the enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. The NRC is forwarding the individual grades to you in a separate letter which will not be released publicly. Should you have any questions concerning this examination, please contact Mr. Phillip T. Young at 301-415-4094 or via internet e-mail phillip.young@nrc.gov.
Sincerely,
/RA/
Johnny H. Eads, Jr., Chief Research and Test Reactors Oversight Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-20
Enclosures:
- 1. Initial Examination Report No. 50-20/OL-10-01 cc without enclosures: See next page DISTRIBUTION w/ encls.:
PUBLIC PRTB r/f RidsNRRDPRPRTA RidsNRRDPRPRTB Facility File (CRevelle) O-7 F-08 ADAMS ACCESSION #: ML102571660 TEMPLATE #:NRR-074 OFFICE PROB:CE IOLB:LA E PROB:BC NAME PYoung CRevelle JEads DATE 09/16/2010 09/17/2010 09/17/2010 C = COVER E = COVER & ENCLOSURE N = NO COPY OFFICIAL RECORD COPY
Massachusetts Institute of Technology Docket No. 50-20 cc:
City Manager City Hall Cambridge, MA 02139 Department of Environmental Protection One Winter Street Boston, MA 02108 Mr. Robert Gallagher, Acting Director Radiation Control Program Department of Public Health Schrafft Center, Suite 1M2A 529 Main Street Charlestown, MA 02129 Nuclear Preparedness Manager Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611
U. S. NUCLEAR REGULATORY COMMISSION OPERATOR LICENSING INITIAL EXAMINATION REPORT REPORT NO.: 50-20/OL-10-01 FACILITY DOCKET NO.: 50-20 FACILITY LICENSE NO.: R-37 FACILITY: MITR-II EXAMINATION DATES: September 07 & 08, 2010 SUBMITTED BY: ______________________
Phillip T. Young, Chief Examiner Date
SUMMARY
During the week of September 6, 2010 the NRC administered operator licensing examinations to one Senior Operator Upgrade applicant. The applicant passed all portions of the examination.
REPORT DETAILS
- 1. Examiners:
Phillip T. Young, Chief Examiner, NRC
- 2. Results:
RO PASS/FAIL SRO PASS/FAIL TOTAL PASS/FAIL Written 0/0 0/0 0/0 Operating Tests 0/0 1/0 1/0 Overall 0/0 1/0 1/0
- 3. Exit Meeting:
Phillip T. Young, NRC, Examiner Mr. Ed Lau, MIT, Reactor Superintendent Mr. Frank Warmsley, MIT, Training Supervisor The examiner thanked the facility for all the work and coordination required to conduct the examinations.
ENCLOSURE 1