G20100532/LTR-10-0384/EDATS: SECY-2010-0422 - Janet Wolf Ltr. Diablo Canyon Power Plant Earthquake Fault Hazard
ML102510216
Person / Time
Site: Diablo Canyon  
Issue date: 09/23/2010
From: Brian Holian
Division of License Renewal
To: Wolf J
Santa Barbara County, CA
Ferrer, N B, NRR/DLR, 415-1045
Shared Package
ML102510203 List:
References
EDATS: SECY-2010-0422, LTR-10-0384, G20100532
Download: ML102510216 (4)


Text

September 23, 2010 Ms. Janet Wolf Santa Barbara County Board of Supervisors 105 East Anapamu Street Santa Barbara, CA 93101

Dear Supervisor Wolf:

On behalf of the U.S. Nuclear Regulatory Commission (NRC or the staff), I am responding to the Santa Barbara County Board of Supervisors (Board) letter dated August 4, 2010. In the letter, the Board requested that the NRC wait until the completion of the proposed three dimensional (3-D) geophysical mapping of the Shoreline Fault before relicensing Diablo Canyon Power Plant, Units 1 and 2 (DCPP). Currently, the staff is reviewing Pacific Gas & Electric Co.s (PG&Es) application to renew the operating licenses for DCPP. The NRC has not yet made a decision on the application and will not do so until safety and environmental reviews are complete and any outstanding adjudicatory hearing items have been resolved.

Delaying the license renewal review does not enhance the staffs ability to address seismic issues at DCPP. The NRC addresses seismic safety issues, including those related to the Shoreline Fault, through its ongoing oversight process. It is important to note that the license renewal review does not affect the ongoing safety oversight process. The NRC staff is involved on a daily basis in monitoring and inspecting the operations at DCPP. By addressing seismic issues within the agencys continuing safety oversight of the power plant, the NRC staff can quickly respond to new information, as the agency demonstrated when it monitored PG&Es response to the discovery of the Shoreline Fault, and then conducted preliminary assessments to determine whether the new fault threatens safe plant operation.

Should information, including the results of ongoing 3-D mapping, show that there is a basis to question the continued safe operation of DCPP, then the NRC will take the appropriate actions as part of the agencys ongoing safety oversight. The NRC staff will continue to monitor assessments of the Shoreline Fault and other seismic issues around DCPP and will ensure that the power plants safety systems remain capable of safely shutting the plant down in case of a seismic event.

I appreciate your time, interest, and concern in contacting the NRC. If you have additional questions about the DCPP license renewal review process or concerns about the NRCs oversight of the plants safe operation, I invite you to contact Mr. David Wrona, Chief of Renewal Projects Branch 2, in the Division of License Renewal at (301) 415-2292.

Sincerely,

/RA/

Brian E. Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation cc: Distribution via Listserv

I appreciate your time, interest, and concern in contacting the NRC. If you have additional questions about the DCPP license renewal review process or concerns about the NRCs oversight of the plants safe operation, I invite you to contact Mr. David Wrona, Chief of Renewal Projects Branch 2, in the Division of License Renewal at (301) 415-2292.

Sincerely,

/RA/

Brian E. Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation cc: Distribution via Listserv DISTRIBUTION: G20100532/LTR-10-0384/EDATS: SECY-2010-0422 See next page Accession Nos.: ML10251023 (Package) ML102320184 (Incoming) ML102510216 (Letter)

OFFICE LA:RPOB:DLR Tech Editor

  • PM:RPB2:DLR PM:RPB2:DLR OGC (NLO)

NAME IKing KAzariah-Kribbs NFerrer DStuyvenberg SUttal DATE 09/14/10 09/16/10 09/16/10 09/16/10 09/23/10 OFFICE BC:RPB2:DLR D:DLR NAME DWrona BHolian DATE 09/23/10 09/23/10 OFFICIAL RECORD COPY

Letter to Janet Wolf from Brian E. Holian dated September 23, 2010

SUBJECT:

RESPONSE TO JANET WOLF LETTER REGARDING DIABLO CANYON POWER PLANT EARTHQUAKE FAULT HAZARD DISTRIBUTION: G20100532/LTR-10-0384/EDATS: SECY-2010-0422 HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsEdoMailCenter RidsNrrOd RidsOGCMailCenter RidsSecyMailCenter RidsRgn4MailCenter RidsNrrMail Center N. Ferrer K. Green A. Stuyvenberg D. Wrona A. Wang M. Peck, RIV T. Brown, RI G. Miller, RIV N. OKeefe, RIV I. Couret, OPA V. Dricks, OPA W. Maier, RIV J. Weil, OCA E. Williamson, OGC S. Uttal, OGC R. Rihm, EDO