Text

IPRenewal NPEmails From: Stuyvenberg, Andrew Sent: Tuesday, August 31, 2010 9:34 AM To: Gray, Dara F Cc: IPRenewal NPEmails

Subject:

RE: Permit Updates No problem, Dara.

FYI - We are working on the schedule change letter to issue today. The schedule change will likely go farther than the board notice on 8/3 indicated. I will follow-up once weve finalized the schedule change. Also, if I dont hear back from you today - which I dont expect because youre out of town - I will follow up with someone else in Entergy license renewal to give a heads-up about the schedule change.

Were now looking at mid November. Again, this is due to the time necessary to finalize this very large document. We currently plan to have three volumes. The total size - in pages - will likely be several times that of Vermont Yankees FSEIS (which all couldve fit in one volume), for comparison.

Please call with any questions.

Best, Drew From: Gray, Dara F [1]

Sent: Monday, August 30, 2010 8:22 PM To: Stuyvenberg, Andrew

Subject:

RE: Permit Updates Drew I'm out of town until Thursday and don't have access to the files now. But I will make sure that you have the most recent version or, if it was my goof (likely) I will get them to you.

Also, should any changes on the FSEIS scheduling arise, I would appreciate hearing asap.

Talk to you Thursday.

From: Stuyvenberg, Andrew [2]

Sent: Sat 8/28/2010 9:30 PM To: Gray, Dara F Cc: IPRenewal NPEmails

Subject:

RE: Permit Updates Dara -

I noticed that the SPDES permits for the Simulator Transformer Vault and the Buchanan Gas Turbine both appear to have expired in March of 2008. This is consistent with the LRA, but would appear to show that both permits have expired without having been extended or renewed. Please let me know whether this is correct, or whether Ive missed something. Thanks.

Best regards, Drew From: Gray, Dara F [3]

Sent: Tuesday, August 24, 2010 8:17 AM 1

To: Stuyvenberg, Andrew

Subject:

Permit Updates Hi Drew

[Sorry for the delay, I started putting together the listing of permit updates and got distracted.]

As we discussed, here is the updated information regarding our environmental permits.

Using the listing of permits in Appendix E of the DSEIS as the basis, the following is the listing of permits which have been updated IP2 Pesticide Business Registration [attached here]

IP3 Pesticide Business Registration [attached here]

Simulator Transformer Vault SPDES Permit [attached here]

Tank Farm SPDES Permit (this permit has been terminated)

Buchanan Gas Turbine SPDES Permit [attached here]

ISFSI Stormwater SPDES General Permit for Construction Activities (this permit has been terminated)

WCDOH Air Permit for IP2 GT1 WCDOH Air Permit for IP2 GT2 WCDOH Air Permit for IP2 GT3 WCDOH Air Permit for IP2 Vapor Extractor USDOT IP2 Hazardous Materials Certificate of Registration USDOT IP3 Hazardous Materials Certificate of Registration WCDOH IP3 Petroleum Bulk Storage Registration SCDHEC IP2 Radioactive Waster Transport Permit (this permit has been terminated)

SCDHEC IP3 Radioactive Waster Transport Permit (this permit has been terminated)

TDEC IP2 Radioactive Waste License for Delivery TDEC IP3 Radioactive Waste License for Delivery I will attach some here and followup with the rest in following emails to avoid clogging any mailboxes.

Please let me know if you have any questions.

Dara Gray, REM Chemistry/Environmental Indian Point Energy Center (914) 736-8414 DGray@Entergy.com This e-mail and any attachments thereto are intended only for the use by the addressee(s) named herein and contain proprietary and confidential information. If you are not the intended recipient of this e-mail, you are hereby notified 2

Hearing Identifier: IndianPointUnits2and3NonPublic_EX Email Number: 2022 Mail Envelope Properties (AF843158D8D87443918BD3AA953ABF7818617D59AC)

Subject:

RE: Permit Updates Sent Date: 8/31/2010 9:34:12 AM Received Date: 8/31/2010 9:34:15 AM From: Stuyvenberg, Andrew Created By: Andrew.Stuyvenberg@nrc.gov Recipients:

"IPRenewal NPEmails" <IPRenewal.NPEmails@nrc.gov>

Tracking Status: None "Gray, Dara F" <DGray@entergy.com>

Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 3882 8/31/2010 9:34:15 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: