MONTHYEARIR 05000458/20230402024-01-18018 January 2024 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter RBG-48271, Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk2024-01-12012 January 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML24011A1742024-01-11011 January 2024 Security Baseline Inspection Report (Cover Letter) ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection IR 05000458/20230102023-12-12012 December 2023 Biennial Problem Identification and Resolution Inspection Report 05000458/2023010 RBG-48267, Reply to a Notice of Violation, NRC Inspection Report 05000458/20230032023-12-0707 December 2023 Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1432023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23310A0322023-11-13013 November 2023 Integrated Inspection Report 05000458/2023003 IR 05000458/20230032023-11-13013 November 2023 Integrated Inspection Report 05000458/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23311A4322023-11-0909 November 2023 Notification of NRC Supplemental Inspection (95001) and Request for Information RBG-48264, Core Operating Limits Report (COLR) - Cycle 23, Revision 12023-11-0606 November 2023 Core Operating Limits Report (COLR) - Cycle 23, Revision 1 RBG-48260, Notification of Readiness for Supplemental Inspection2023-10-12012 October 2023 Notification of Readiness for Supplemental Inspection ML23278A2402023-10-0606 October 2023 Regulatory Audit Plan in Support of License Amendment Requests to Revise TSs to Adopt Risk-Informed Completion Times and Implement the Provisions of 10 CFR 50.69 RBG-48258, Notification of Readiness for Supplemental Inspection2023-10-0505 October 2023 Notification of Readiness for Supplemental Inspection RBG-48259, Revision to Reply to Notice of Violation; EA-23-0552023-10-0303 October 2023 Revision to Reply to Notice of Violation; EA-23-055 ML23270B9932023-09-29029 September 2023 Request to Update ASME Boiler & Pressure Vessel Code Relief Request SE with NRC-Approved Revision of Bwrip Guidelines (GG-ISI-020 & RBS-ISI-019) (EPID L-2022-LLR-0090) - Non-Proprietary ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000458/20234012023-09-26026 September 2023 Cyber Security Inspection Report 05000458/2023401 IR 05000458/20230012023-09-21021 September 2023 NRC Inspection Report 05000458/2023001, Disputed Non-Cited Violation Rescinded RBG-48254, Report of Changes and Errors to 10CFR50.462023-09-21021 September 2023 Report of Changes and Errors to 10CFR50.46 IR 05000458/20234032023-09-21021 September 2023 NRC Security Inspection Report 05000458/2023403 (Cover Letter) RBG-48249, Reply to a Notice of Violation, EA-23-0712023-09-14014 September 2023 Reply to a Notice of Violation, EA-23-071 RBG-48253, Submittal of Owner'S Activity Report Form for Cycle 222023-09-12012 September 2023 Submittal of Owner'S Activity Report Form for Cycle 22 IR 05000458/20230122023-09-0101 September 2023 Comprehensive Engineering Team Inspection Report 05000458/2023012 IR 05000458/20230052023-08-21021 August 2023 Updated Inspection Plan for River Bend Station (Report 05000458/2023005) - Mid Cycle Letter RBG-48247, Reply to Notice of Violation; EA-23-0552023-08-21021 August 2023 Reply to Notice of Violation; EA-23-055 IR 05000458/20230922023-08-15015 August 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023092 IR 05000458/20230022023-08-0909 August 2023 Integrated Inspection Report 05000458/2023002 ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23195A0692023-07-24024 July 2023 2023 River Bend Station Notification of Biennial Problem Identification and Resolution Inspection and Request for Information IR 05000458/20230912023-07-20020 July 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023091 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23195A0222023-07-11011 July 2023 4-2022-012 Letter - OI Closure to Licensee IR 05000458/20234042023-07-11011 July 2023 NRC Security Inspection Report 05000458/2023404 (Cover Letter Only) IR 05000458/20230902023-06-26026 June 2023 NRC Inspection Report 05000458/2023090 and Preliminary White Finding ML23159A2302023-06-0808 June 2023 Response to Request for Additional Information Concerning Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined RBG-48226, Core Operating Limits Report (COLR) - Cycle 23, Revision 02023-05-31031 May 2023 Core Operating Limits Report (COLR) - Cycle 23, Revision 0 RBG-48237, Response to NRC Integrated Inspection Report 05000458/20230012023-05-25025 May 2023 Response to NRC Integrated Inspection Report 05000458/2023001 ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23116A2352023-05-0101 May 2023 Integrated Inspection Report 05000458/2023001 RBG-48220, Submittal of 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report 2024-01-18
[Table view] |
See also: IR 05000458/2010006
Text
UNITED STATES
NUCLEAR REGULATORY COMMI SSI ON
R E G I ON I V
612 EAST LAMAR BLVD, SUITE 400
ARLINGTON, TEXAS 76011-4125
August 18, 2010
Michael Perito
Vice President, Operations
Entergy Operations, Inc.
River Bend Station
5485 US Highway 61N
St. Francisville, LA 70775
SUBJECT: RESPONSE TO RIVER BEND STATION REPLY TO NOTICE OF VIOLATION
EA-10-095 IN NRC TRIENNIAL FIRE PROTECTION INSPECTION REPORT
05000458/2010006
Dear Mr. Perito:
This acknowledges receipt of your letter and attachments (RBG-47046) dated, July 19, 2010, in
which you responded to a notice of violation NOV 05000458/2010006-01, "Failure to Ensure at
Least One Train of Equipment Necessary to Achieve Hot Shutdown Conditions is Free of Fire
Damage."
The notice of violation requested that your response include information about decisions to
extend the completion of necessary plant modifications beyond the October 2009 refueling
outage. The decision-making process described in the letter was consistent with our
understanding from the inspection. However, your response did not specifically address your
assessment of the appropriateness of the decisions to extend the completion of necessary plant
modifications beyond the October 2009 refueling outage. This information is required to
determine whether the corrective actions for this violation were appropriate.
In a telephone conversation on August 13, 2010, with Roy Caniano, Director, Division of
Reactor Safety, you agreed to submit a supplemental response to the Notice of Violation to
address your assessment of the appropriateness of the decisions to extend the schedule for
completing the plant modification and to provide additional information concerning the
engineering quality problems and parts availability that caused the delays in completing timely
corrective actions.
The response letter stated that although you agreed with the finding related to the fire protection
requirements for a main control room fire, you requested that the NRC reconsider the issuance
of the notice of violation and that the portion of the notice of violation involving timeliness of
corrective actions be re-characterized. We have reviewed the information provided in your letter
and noted that no new information was provided beyond what was reviewed as part of the
inspection. After reviewing your letter and our finding, the NRC has concluded that the violation
was appropriate.
Entergy Operations, Inc. -2-
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document system
(ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Neil OKeefe, Chief
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-458
License No. NPF-47
Entergy Operations, Inc. -3-
cc w/Enclosure:
Senior Vice President and COO
Entergy Operations, Inc
P. O. Box 31995
Jackson, MS 39286-1995
Vice President, Oversight
Entergy Operations, Inc.
P. O. Box 31995
Jackson, MS 39286-1995
Senior Manager, Nuclear Safety & Licensing
Entergy Nuclear Operations
P. O. Box 31995
Jackson, MS 39286-1995
Manager, Licensing
Entergy Operations, Inc.
5485 US Highway 61N
St. Francisville, LA 70775
Attorney General
State of Louisiana
P. O. Box 94005
Baton Rouge, LA 70804-9005
Ms. H. Anne Plettinger
3456 Villa Rose Drive
Baton Rouge, LA 70806
President of West Feliciana
Police Jury
P. O. Box 1921
St. Francisville, LA 70775
Mr. Brian Almon
Public Utility Commission
William B. Travis Building
P. O. Box 13326
Austin, TX 78701-3326
Mr. Jim Calloway
Public Utility
Commission of Texas
1701 N. Congress Avenue
Austin, TX 78711-3326
Entergy Operations, Inc. -4-
Louisiana Department of Environmental Quality
Radiological Emergency Planning and
Response Division
P. O. Box 4312
Baton Rouge, LA 70821-4312
Joseph A. Aluise
Associate General Counsel - Nuclear
Entergy Services, Inc.
639 Loyola Avenue
New Orleans, LA 70113
Chief, Technological Hazards
Branch
FEMA Region VI
800 N. Loop 288
Denton, TX 76209-3606
Entergy Operations, Inc. -5-
Electronic distribution by RIV:
Regional Administrator (Elmo.Collins@nrc.gov )
Deputy Regional Administrator (Chuck.Casto@nrc.gov )
DRP Director (Anton.Vegel@nrc.gov )
DRP Deputy Director (Troy.Pruett@nrc.gov )
DRS Director (Roy.Caniano@nrc.gov )
DRS Deputy Director (Jeff.Clark@nrc.gov
Senior Resident Inspector (Grant.Larkin@nrc.gov )
Resident Inspector (Charles.Norton@nrc.gov )
Branch Chief, DRP/C (Vincent.Gaddy@nrc.gov )
RBS Administrative Assistant (Lisa.Day@nrc.gov )
Senior Project Engineer, DRP/C (Bob.Hagar@nrc.gov )
Project Engineer, DRP/C (Rayomand.Kumana@nrc.gov )
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov )
Project Manager (Alan.Wang@nrc.gov )
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov )
RITS Coordinator (Marisa.Herrera@nrc.gov )
Regional Counsel (Karla.Fuller@nrc.gov )
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
Senior Enforcement Specialist Ray.Kellar@nrc.gov
OEMail Resource
OEDO RIV Coordinator (Margie.Kotzales@nrc.gov )
R:REACTORS\RB NOV Response Acknowledgement 2010006-STG ADAMS:
ADAMS: No ;Yes ; SUNSI Review Complete Reviewer Initials:
- Publicly Available ; Non-Sensitive
Non-publicly Available Sensitive
DRS:RI DRS:C:EB2
S. Graves N. OKeefe
8/18/10 8/18 /10
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax