Withdrawal of Amendment Request for Approval of the Cyber Security Plan
ML102230352
Person / Time
Site: River Bend Entergy icon.png
Issue date: 08/12/2010
From: Wang A
Plant Licensing Branch IV
To:
Entergy Operations
Wang, A B, NRR/DORL/LPLIV, 415-1445
References
TAC ME2632
Download: ML102230352 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 12, 2010 Vice President, Operations Entergy Operations, Inc.

River Bend Station 5485 US Highway 61 N St. Francisville, LA 70775

SUBJECT:

RIVER BEND STATION, UNIT 1, WITHDRAWAL OF AN AMENDMENT REQUEST FOR APPROVAL OF THE CYBER SECURITY PLAN (TAC NO.

ME2632)

Dear Sir or Madam:

By letter dated November 19, 2009 (non-publicly available), as supplemented by letter dated December 9, 2009 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML093480161), Entergy Operations, Inc. (Entergy), applied for an amendment to the River Bend Station, Unit 1 (RBS) Facility Operating License No. NPF-47.

The license amendment request included the Cyber Security Plan (CSP), proposed changes to the Facility Operating License, and a proposed CSP implementation schedule for RBS. The proposed CSP was submitted in accordance with Title 10 of the Code of Federal Regulations, Section 73.54, "Protection of digital computer and communication systems and networks."

Subsequently, by letter dated July 22,2010 (ADAMS Accession No. ML102080483), Entergy withdrew the amendment request.

The purpose of this letter is to advise that the application dated November 19, 2009, as supplemented by letter dated December 9,2009, is being treated as withdrawn. Notice of Consideration of Issuance of the proposed amendment had not been published in the Federal Register.

Sincerely, Alan B. Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-458 cc: Distribution via Listserv

August 12, 2010 Vice President, Operations Entergy Operations, Inc.

River Bend Station 5485 US Highway 61 N St. Francisville, LA 70775

SUBJECT:

RIVER BEND STATION, UNIT 1, WITHDRAWAL OF AN AMENDMENT REQUEST FOR APPROVAL OF THE CYBER SECURITY PLAN (TAC NO.

ME2632)

Dear Sir or Madam:

By letter dated November 19, 2009 (non-publicly available), as supplemented by letter dated December 9,2009 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML093480161), Entergy Operations, Inc. (Entergy), applied for an amendment to the River Bend Station, Unit 1 (RBS) Facility Operating License No. NPF-47.

The license amendment request included the Cyber Security Plan (CSP), proposed changes to the Facility Operating License, and a proposed CSP implementation schedule for RBS. The proposed CSP was submitted in accordance with Title 10 of the Code of Federal Regulations, Section 73.54, "Protection of digital computer and communication systems and networks."

Subsequently, by letter dated July 22,2010 (ADAMS Accession No. ML102080483), Entergy withdrew the amendment request.

The purpose of this letter is to advise that the application dated November 19, 2009, as supplemented by letter dated December 9, 2009, is being treated as withdrawn. Notice of Consideration of Issuance of the proposed amendment had not been published in the Federal Register.

Sincerely, IRA!

Alan B. Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-458 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsNrrDorlLpl4 Resource RidsRgn4MailCenter Resource LPLIV Reading RidsNrrPMRiverBend Resource PPederson, NSIR RidsAcrsAcnw_MailCTR Resource RidsNrrLAJBurkhardt Resource RidsNrrDorlDpr Resource RidsOgcRp Resource ADAMS Accession No* ML102230352

  • via email OFFICE NRR/LPL4/PM NRR/LPL4/LA NRR/LPL4/BC NRR/LPL4/PM NAME AWang JBurkhardt*

MMarkley AWang CFLyon for DATE 8/11/10 8/11/10 8/12/10 8/12/10 OFFICIAL AGENCY RECORD