AEROTEST OPERATIONS, INC.
3455 FOSTORIA WAY - SAN RAMON, CA 94583 - (925) 866-1212 - FAX (925) 866-1716 15 July 2010 Director of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C. 20555
Subject:
Annual Summary of Changes, Tests, and Experiments at Aerotest Radiography and Research Reactor (ARRR), Docket No. 50-228, for the period of 1 July 2009 to 30 June 2010.
Gentlemen:
The enclosed report summarizes the ARRR operations from July 1, 2009 through June 30, 2010. This submittal complies with the requirements set forth in 10 CFR 50.59, "Authorization of Changes, Tests and Experiments." Summary forms of monthly operations and unscheduled power reductions are included.
No new or unusual problems have been noted during the year and reactor operations have remained stable with respect to safety and reliability.
Sincerely, Alfredo W. Meren Reactor Supervisor Aerotest Operations, Inc.
10, A subsidiary of Autoliv ASP, INC.
ANNUAL
SUMMARY
OF CHANGES, TESTS AND EXPERIMENTS PERFORMED AT THE AEROTEST RADIOGRAPHY AND RESEARCH REACTOR (ARRR)
DOCKET NO. 50-228 FOR THE PERIOD ENDING JUNE 30, 2010 BY ALFREDO W. MEREN REACTOR SUPERVISOR APPROVED BY SANDRA L. WARREN GENERAL MANGER AEROTEST OPERATIONS, INC.
A subsidiary of Autoliv ASP, INC.
SECTION I Part I - Changes
- 1.
Updated Procedures and Safety Analysis Report have previously been submitted to the Nuclear Regulatory Commission as part of the facility's relicensing application package. No changes have yet been implemented.
Part 2 - Experiments No new experiments were performed during the year. The experiments performed in this reporting period were as follows:
Experiment No. 114: Neutron radiography performed in the radiography facilities.
SECTION II ARRR MONTHLY OPERATING
SUMMARY
Date Operating Hours 7-09 136 8-09 135 9-09 125 10-09 132 11-09 127 12-09 142 1-10 119 2-10 129 3-10 148 4-10 150 5-10 140 6-10 145 Kilowatt-Hours 21,794 21,668 20,049 24,230 23,347 26,082 21,857 23,679 27,252 28,018 26,116 27,110 Accumulated kW-h 13,838,466 13,860,134 13,880,183 13,904,413 13,927,760 13,953,842 13,975,699 13,999,378 14,026,630 14,054,648 14,080,764 14,107,874 Expts &
Irradiations 23 23 22 23 23 23 18 23 27 23 26 26 Unscheduled Shutdowns 0
0 0
3 1
5 0
1 0
0 0
1 Totals 1628 291,202 14,107,874 280 1
ARRR UNSCHEDULED POWER REDUCTIONS TYPE OF SCRAM CHANNEL AFFECTED NO.
DATE AUTO MAN Spurious OP. ERROR CAL 1
2 3
4 Earthquake H20 COMMENTS 1
10-13-09 X
X X X X X power outage 2
10-14-09 X
X X X X X shim rod drop 3
10-29-09 X
X X
X X X
power surge 4
11-23-09 X
X X X X X
no visible alarm
,5 12-10-09 X
X X
X X X
shim rod drop 6
12-15-09 X
X X
X X X
no visible alarm 7
12-16-09 X
X I
X X X X
no visible alarm 8
12-17-09 X
X X
X X X
no visible alarm 9
12-17-09 X
X X
X X X
no visible alarm 10 2-10-10 X
X X
X X X
power surge 11 6-1-10 X
X X
X X X
reg rod drop due 12 to loose bulb in 13 CONT/ON lamp 14 15 16 17 18 19 20 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 VNPOWREI).XLS