Attachment 6 OBDI 202 - IOLE Process DRAFT OUTLINE COMMENTS Facility: River Bend First Exam Date:
April 16, 2010 Written Exam Outline (2/19/2010)
Comment Resolution 1 No comments None 2
3 4
5 Administrative JPM Outline (2/19/2010)
Comment Resolution 1
Replace RO ADMIN for EP Replace RO Admin JPM A3 was replaced with a new JPM.
2 Replace SRO ADMIN A5 as it is an RO Will reword the JPM so that it is an SRO JPM This was done.
3 Make EP Determination following a scenario 4
5 Control Room / In-Plant System JPM Outline (2/19/2010)
Comment Resolution 1 Replace JPM C2 as it is same as scenario 2.
This was not replaced - the scenario was revised so it no longer has C2.
2 What is ARC?
3 What is safety significance of JPM C1?
This is performed per an EOP attachment.
4 5
Simulator Scenario Outline Comments (2/19/2010)
Comment Resolution 1 Scenario 1 -
Replace event 2 with a TS failure Event 2 has no safety significance. Will be replaced.
OBDI 202 - IOLE Process This event was replaced.
2 Scenario 2 -
Can LPRM be bypassed in simulator?
Remove 5 minutes from event 5.
Does event 7 include BPVs? If so, lower initial power to 70%.
Will replace with a BOP TS event. Looking at inadvertent auto start of RCIC Will remove the 5 minute delay so that it is examiner initiated.
Based on validation, events 3 and 4 were replaced. The 5 minute time delay was removed.
3 Scenario 3 -
What BOP actions for event 5?
What is the operational impact of event 3?
Looks like a spare 4
Scenario 4 -
What are the BOP actions on event 4?
Make sure it is ok to raise power Will add another BOP event.
Event 6 was added to the scenario.
5