Senior Reactor and Reactor Operator Initial Examinations - Seabrook Station
ML101940088
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 07/12/2010
From: Hansell S
Operations Branch I
To: O'Keefe M, St.Pierre G
Florida Power & Light Co
Shared Package
ML101870654 List:
References
Download: ML101940088 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406*1415 July 12~ 2010 Mr. Gene St. Pierre Vice President, North Region Seabrook Nuclear Power Plant FPL Energy Seabrook, LLC c/o Mr. Michael O'Keefe P.O. Box 300 Seabrook, NH 03874

SUBJECT:

SENIOR REACTOR AND REACTOR OPERATOR INITIAL EXAMINATIONS SEABROOK STATION

Dear Mr. St. Pierre:

In a telephone conversation on June 24, 2010, between Mr. David Silk, Senior Operations Engineer/Chief Examiner, and Mr. Tim Cassidy, Training Support Supervisor, arrangements were made for the administration of licensing examinations at Seabrook Station during the weeks of November 22 and 29, 2010.

As agreed during the telephone conversation, your staff will prepare the examinations based on the guidelines in NUREG-1021, "Operator Licensing Examination Standards for Power Reactors, n Revision 9, Supplement 1. The NRC's regional office will discuss with your staff any changes that might be necessary before the examinations are administered.

To meet the above schedule, it will be necessary for your staff to furnish the examination outlines by August 30, 2010. The written examinations, operating tests, and the supporting referen<~ materials identified in Attachment 3 of ES-201 will be due by September 24,2010.

Pursuant to Title 10, Section 55.40(b) (3), of the Code of Federal Regulations (10 CFR 55.40(b)

(3>>, an authorized representative of the facility licensee shall approve the outlines, examinations, and tests before they are submitted to the NRC for review and approval. All materials should be complete and ready-to-use. We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.

In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temper;atures, and levels) generated during the dynamic operating tests until the examination results are final. Appendix E of NUREG-1021 contains a number of NRC poliCies and guidelines that will be in effect while the written examinations and operating tests are being administered.

G. St. Pierre 2

To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OM B) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),

and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date, If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The OMB, under approval number 3150-0018, which expires on June 30, 2009, approved these information collections. The public reporting burden for this collection of information is estimated to average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, writing the examinations, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIAlPrivacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, D.C.

20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRC's public Web site at http://www.nrc.gov/reading rm/adams.html.

Thank you for your cooperation in this matter. Mr. Cassidy has been advised of the pOlicies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. David Silk at (610) 337-5372, or me at (610) 337-5046.

Sincerely, Samuel L Hansell, Jr., Chief Operations Branch Division of Reactor Safety Docket No.

50-443 License No.

NPF-86 cc:

Distribution via ListServ

G. St. Pierre 2

To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approvalnumber 3150-0024),

and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The OMB, under approval number 3150-0018, which expires on June 30, 2009, approved these information collections. The public reporting burden for this collection of information is estimated to average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, writing the examinations, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIAIPrivacy Services Branch (T-5 F52), U.S. Nuclear Regulatory CommiSSion, Washington, D.C. 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, D.C.

20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number.

I n accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRC's public Web site at http://www.nrc.gov/reading rm/adams.html.

Thank you for your cooperation in this matter. Mr. Cassidy has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. David Silk at (610) 337-5372, or me at (610) 337 5046.

Sincerely, IRA!

Samuel L. Hansell, Jr., Chief Operations Branch Division of Reactor Safety Docket No.

50-443 License No.

NPF-86 cc: Distribution via ListServ SUNSI Review Complete:

OMS (Reviewer's Initials)

ADAMS PKG: ML101870654 ADAMS ACC #ML101940088 DOCUMENT NAME: G:\\DRS\\Operations Branch\\SILK\\Exam FY11 SB Dec 10 (U01694)\\120dayexamltr.docx After declaring this document "An Official Agency Record," it will be released to the Public.

To receive a co of this document indicate in the box: 'Cn =Co without attachment/enclosure RI/DRS/OB RI/DRS/OB RIIDRS/OB CJBixlerlSLH Silk/DMS SHanselllSLH 07/09/10 7108110 07109/10 OFFICIAL RECORD COPY

G. St. Pierre 3

Distribution w/encl: (via e-mail)

M. Dapas, Acting RA (R10RAMAIL Resource)

D. Lew, DRP (R1DRPMAIL Resource)

J. Clifford, DRP (R1DRPMAIL Resource)

D. Roberts; DRS (R1 DRSMaii Resource)

P. Wilson, DRS (R1DRSMaii Resource)

A. Burritt, DRP L. Cline, DRP A. Turilin, DRP C. Douglas, DRP W. Raymond, DRP, SRI J. Johnson, DRP, RI E. Jacobs,DRP, OA L. Trocine,RI OEDO D. Bearde, DRS RidsNrrPMSeabrook Resource RidsNrrDorlLpl1-2 Resource S. Hansell, DRS D. Silk, DRS Distribution:

DRS Master Exam File (C. Bixler) (w/concurrences)

DRS File