Summary of Public Meeting with Firstenergy Nuclear Operating Company (FENOC) to Discuss the Results of Repairs Made to the Reactor Vessel Head and the Basis for Davis-Besse's Decision to Start UpML101610792 |
Person / Time |
---|
Site: |
Davis Besse ![Cleveland Electric icon.png](/w/images/7/78/Cleveland_Electric_icon.png) |
---|
Issue date: |
06/10/2010 |
---|
From: |
Jamnes Cameron NRC/RGN-III/DRP/B6 |
---|
To: |
|
---|
References |
---|
Download: ML101610792 (5) |
|
|
---|
Category:Meeting Summary
MONTHYEARML23152A2552023-06-0505 June 2023 Summary of the May 17, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Davis-Besse Nuclear Power Station ML22178A2312022-06-28028 June 2022 Summary of the June 22, 2022, Public Outreach to Discuss the NRC 2021 End-Of-Cycle Plant Performance Assessment of Davis Besse Nuclear Power Station ML22088A1972022-03-30030 March 2022 Summary of March 11, 2022, Call Regarding the Spring 2022 Steam Generator Tube Inspections ML22084A1022022-03-27027 March 2022 Reissue Summary of the February 1, 2022, Regulatory Conference Between Energy Harbor, Davis-Besse Nuclear Power Station and the Nuclear Regulatory Commission ML22077A8062022-03-23023 March 2022 Summary of the February 1, 2022, Regulatory Conference Between Energy Harbor, Davis-Besse Nuclear Power Station and the Nuclear Regulatory Commission ML21314A5362021-11-18018 November 2021 Summary of November 8, 2021, Meeting with Energy Harbor Nuclear Corp. Regarding Its Proposed Alternate for Examination of Steam Generator Welds at ML21180A4632021-06-29029 June 2021 Summary of the June 22, 2021, Public Outreach to Discuss the NRC 2020 End-of-Cycle Plant Performance Assessment of Davis-Besse Nuclear Power Station, and Perry Nuclear Power Plant ML20240A2942020-08-27027 August 2020 July 23, 2020 Summary of Public Webinar to Discuss the Nrc 2019 End-Of-Cycle Plant Performance Assessment of the Davis-Besse Nuclear Power Station and the Perry Nuclear Power Plant ML19249C7112019-09-0404 September 2019 Summary of the July 18, 2019 Public Outreach/Open House to Discuss the NRC 2018 End-Of-Cycle Plant Performance Assessment of the Davis-Besse Nuclear Power Station ML18313A1982018-11-14014 November 2018 Summary of Meeting with Firstenergy Nuclear Operating Company Regarding Planned Submittal of Post-Shutdown Emergency Plan for Davis-Besse Nuclear Power Station ML18192A6522018-07-10010 July 2018 Summary of Public Meeting to Discuss the 2017 End-of-Cycle Plant Performance Assessment of Davis-Besse Nuclear Power Station ML17258A1462017-09-20020 September 2017 Summary of September 12, 2017, Meeting with Firstenergy Nuclear Operating Company Regarding Its Licensing Amendment Request to Adopt National Fire Protection Association Standard 805 at Davis-Besse Nuclear Power Station, Unit No. 1 ML17229B1362017-08-16016 August 2017 Summary of July 19, 2017, Open House to Discuss the 2016 End-of-Cycle Plant Performance Assessment of Davis-Besse Nuclear Power Station ML17087A1882017-03-28028 March 2017 Summary of Closed Meeting with Firstenergy Nuclear Operating Company Regarding Changes to the Davis-Besse Nuclear Power Station, Unit No. 1, Security Plan ML16197A0522016-07-14014 July 2016 Summary of June 21, 2016, Public Meeting with Firstenergy Nuclear Operating Company to Discuss the 2015 End-of-Cycle Plant Performance Assessment of Davis-Besse Nuclear Station ML16130A7502016-05-12012 May 2016 Summary of April 12, 2016, Teleconference Regarding Steam Generator Tube Inservice Inspection ML14177A5782016-02-22022 February 2016 November 13, 2013, Summary of Meeting with Firstenergy Nuclear Operating Company to Discuss Delay in Submittal of Fire Risk Reduction Amendment Request ML16006A3512016-01-20020 January 2016 December 17,2015 Summary of Meeting with Firstenergy Nuclear Operating Company on Its License Amendment Request to Revise the Emergency Diesel Generator Surveillance Requirements at Davis-Besse Nuclear Power Station, Unit 1 ML16007A3962016-01-12012 January 2016 Summary of January 5, 2016, Meeting with Firstenergy Nuclear Operating Company on Its Planned License Amendment Request to Revise the Emergency Action Level Scheme at Davis-Besse Nuclear Power Station, Unit No. 1 ML15196A5162015-07-24024 July 2015 Summary of Telephone Conference Call Held on May 06, 2015, and May 19, 2015 Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company ML15170A2862015-06-18018 June 2015 Summary of the Public Open House Regarding Davis-Besse Nuclear Power Station ML15089A1642015-04-27027 April 2015 Summary of February 25, 2015, Partially Closed Meeting with Industry Stakeholders Regarding the Babcock and Wilcox Loss of Coolant Accident Evaluation Model Analysis ML15056A4562015-04-20020 April 2015 Summary of Teleconference Call Held February 20, 2015, Between U.S. Nuclear Regulatory Commission and First Energy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis-Besse Nuclear Power Station ML14325A7782014-12-16016 December 2014 October 6, 2014, Summary of Pre-Application Meeting with Firstenergy Nuclear Operating Company to Discuss Proposed Combination of Site Emergency Plans ML14224A6142014-08-12012 August 2014 Summary of Public Meeting to Discuss the 2013 Performance of Davis-Besse Nuclear Power Station ML14160B1032014-07-10010 July 2014 June 6, 2014 Summary of Meeting with FENOC Flooding Hazard Reevaluation Extension Request for Beaver Valley Power Station, Units 1 and 2 and Flooding Hazard Reevaluation Report for Davis-Besse Nuclear Power Station, Unit 1 ML14099A4642014-05-0606 May 2014 Summary of Public Meetings to Discuss Draft Supplement 52 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Davis-Besse Nuclear Generating Station, Unit 1 ML14099A3392014-04-22022 April 2014 March 27, 2014, Summary of Telephone Conference Call Held Between Nuclear Regulatory Commission and First Energy Nuclear Operating Company Concerning Commitment 13 of the Safety Evaluation Report Pertaining to the Davis Besse Unit 1, Licens ML14080A1842014-03-21021 March 2014 Summary of Webinar Meeting to Discuss NRC Inspection Activities Associated with the Davis-Besse Nuclear Power Station Installation of Two New Steam Generators ML13240A0702013-08-29029 August 2013 8 22 2013 DB NRC Telecon Summary License Condition ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13197A2572013-07-17017 July 2013 5 28 2013 DB Hs Bolts Telecon Summary ML13182A4082013-07-17017 July 2013 Summary of Telephone Conference Call Held on October 16, 2012, Between NRC and FENOC, Concerning RAI Pertaining to the Davis-Besse Nuclear Power Station, LRA (TAC No. ME640) ML13149A2862013-07-12012 July 2013 Summary of Telephone Conference Call Held on May 2, 2013, Between the NRC and FENOC, Concerning RAI Pertaining to the Davis-Besse Nuclear Power Station License Renewal Application ML13182A4432013-07-12012 July 2013 Summary of Telephone Conference Call Held on April 11, 2013, Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis-Besse Nuclear Powe ML13149A2882013-07-0909 July 2013 May 9, 2013, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis-Besse Nuclear Power Stat ML13168A2422013-06-14014 June 2013 6/11/2013 - Summary of Open House to Discuss the 2012 Davis-Besse Nuclear Power Station End-Of-Cycle Performance ML13091A3272013-03-29029 March 2013 Summary of Public Meeting to Discuss the Davis-Besse Replacement Activities ML13051A6602013-03-26026 March 2013 Summary of Telephone Conference Call Held on January 23, 2013, Between the NRC and FENOC, Concerning RAI Pertaining to the Davis-Besse Nuclear Power Station, LRA ML13051A0682013-03-26026 March 2013 January 16, 2013 Summary of Telephone Conference Call Held Between U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company ML13025A0272013-02-14014 February 2013 October 23, 2012 Summary of Telephone Conference Call Held Between the Nuclear Regulatory and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis-Besse Nuclear Power Station, License ML12277A4082012-10-0303 October 2012 September 26, 2012, Summary of Public Meeting to Discuss FENOC Fleet Performance ML12243A2832012-08-30030 August 2012 Summary of Public Meeting to Discuss Nrc'S Review of Fenoc'S Root Cause Analysis of Davis-Besse Shield Building Cracks ML12237A0432012-08-24024 August 2012 August 15, 2012 - Summary of Public Meeting to Discuss the Davis-Besse Nuclear Power Station, Unit 1, End-Of-Cycle Plant Performance Assessment ML12195A1132012-07-16016 July 2012 Summary of Public Meeting with FENOC Regarding Licensing Practices and Processes ML12165A3502012-07-16016 July 2012 Summary of Conference Call for Stream Generator Tube Inservice Inspections for Spring 2012 Refueling Outage ML12052A1792012-05-15015 May 2012 July 19, 2011, Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis-Besse Nuclear Power Station ML12059A0782012-04-0202 April 2012 Summary of Telephone Conference Call Held on February 9, 2012, Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company Concerning Requests for Additional Information Pertaining to the Davis-Besse Nuclear Pow ML12061A2582012-04-0202 April 2012 Summary of Telephone Conference Call Held on July 12,2011, Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis-Besse Nuclear Power ML12031A1832012-03-0202 March 2012 Summary of Telephone Conference Call Held on July 13, 2011, Between the U.S. Nuclear Regulatory Commission and Firstentergy Nuclear Operating Company, Concerning Request for Additional Information Pertaining to the DA7 13 2011 DB NRC Teleco 2023-06-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 10, 2010 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station
SUBJECT:
SUMMARY
OF THE JUNE 3, 2010, PUBLIC MEETING TO DISCUSS THE RESULTS OF REPAIRS MADE TO THE REACTOR VESSEL HEAD AND THE BASIS FOR DAVIS-BESSES DECISION TO START UP On June 3, 2010, the Nuclear Regulatory Commission (NRC) held a public meeting at the Camp Perry Lodging & Conference Center in Port Clinton, Ohio. The meeting was between NRC Region III senior management and FirstEnergy Nuclear Operating Company (FENOC) representatives to discuss inspections and repairs of the reactor vessel head and technical questions regarding the basis for their decision to start up the Davis-Besse Nuclear Power Station.
The NRC began the meeting by sharing background information on the initial NRC actions upon the discovery of nozzle cracking at the Davis-Besse nuclear plant. This was followed by a discussion of the NRCs expectations about the information they would receive from FENOC at the meeting.
The licensee then provided a presentation of their site activities during recent months, including discussion of the control rod drive mechanism (CRDM) issue. During their presentation, the licensee discussed refueling outage activities and plant performance through their most recent cycle. In addition, they shared the results of the exams performed on the reactor vessel head, described the methods being used to repair the damaged CRDM nozzles, and addressed the results of their root cause analysis. They also discussed their basis for determining that the reactor vessel head could be safely returned to service, and the remaining activities that needed to be completed before starting up the plant. The NRCs questions and comments were addressed by the licensee throughout the presentation.
Following the licensees presentation, the NRC provided their closing remarks. During these remarks, the NRC discussed the next steps in their process to evaluate the information FENOC has provided to date, including the information gathered at the meeting. The NRC did not make any regulatory decisions regarding the acceptability of inspections and repairs or the suitability of startup during this meeting. However, the results of the NRCs evaluation will be documented and made publically available in ADAMS at a later date.
FirstEnergy Nuclear Operating Company (FENOC)
The NRCs meeting presentation slides as well as the licensees meeting slides can be found in the Agencywide Documents Access and Management System (ADAMS) at ML101540031. A list of principal meeting attendees can be found in the attached enclosure.
At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and engage the licensee.
/RA/ By Frances C. Ramirez Acting For/
Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3
Enclosure:
As stated cc w/encl: Distribution via ListServ
PUBLIC MEETING PRINCIPAL ATTENDEES June 3, 2010 FirstEnergy B. Allen, Site Vice President, Davis-Besse B. Boles, Director, Site Operations C. Price, Director, Site Performance Improvement, Davis-Besse V. Kaminskas, Director, Site Engineering, Davis-Besse S. Plymale, Manager, Plant Engineering K. Byrd, Manager, Design Engineering Nuclear Regulatory Commission C. Pederson, Deputy Regional Administrator, Region III A. Boland, Director, Division of Reactor Safety, Region III M. Evans, Director, Division of Component Integrity, Office of Nuclear Reactor Regulation J. Cameron, Chief, Branch 6, Division of Reactor Projects, Region III D. Hills, Chief, Engineering Branch 1, Division of Reactor Safety, Region III T. Lupold, Chief, Piping and NDE Branch, Division of Component Integrity, Office of Nuclear Reactor Regulation M. Mahoney, Project Manager, Division of Operating Reactor Licensing, Licensing Branch III-2, Office of Nuclear Reactor Regulation J. Rutkowski, Senior Resident Inspector, Davis-Besse Other Attendees M. Stahl, Ottawa County (Ohio) Commissioner, President J. Sass, Ottawa County (Ohio) Commissioner S. Arndt, Ottawa County (Ohio) Commissioner J. Witt, Ottawa County (Ohio) Administrator R. Bratton, Ottawa County (Ohio) Sheriff Enclosure
FirstEnergy Nuclear Operating Company (FENOC)
The NRCs meeting presentation slides as well as the licensees meeting slides can be found in the Agencywide Documents Access and Management System (ADAMS) at ML101540031. A list of principal meeting attendees can be found in the attached enclosure.
At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and engage the licensee.
/RA/ By Frances C. Ramirez Acting For/
Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3
Enclosure:
As stated cc w/encl: Distribution via ListServ DOCUMENT NAME: G:\DAVI\Davis Besse Mtng Summary for June 3 2010 Management Mtng.docx G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME PVoss:dtp FRamirez for JCameron DATE 06/10/10 06/10/10 OFFICIAL RECORD COPY
Letter to FirstEnergy Nuclear Operating Company from J. Cameron dated June 10, 2010
SUBJECT:
SUMMARY
OF THE JUNE 3, 2010, PUBLIC MEETING TO DISCUSS THE RESULTS OF REPAIRS MADE TO THE REACTOR VESSEL HEAD AND THE BASIS FOR DAVIS-BESSES DECISION TO START UP DISTRIBUTION:
RidsNrrDorlLpl3-2 Resource Susan Bagley RidsNrrPMDavisBesse Resource RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource