MONTHYEARML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 IR 05000266/20220062023-03-0101 March 2023 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022006 and 05000301/2022006) ML23003A8022023-01-0303 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22256A3182022-09-13013 September 2022 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection Report 05000266/2023010 05000301/2023010 IR 05000266/20220052022-08-26026 August 2022 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022005 and 05000301/2022005) ML22175A2002022-06-27027 June 2022 Request for Information for an NRC Triennial Heat Exchanger/Sink Performance Inspection and Request for Information: Inspection Report 05000266/2022004: 05000301/2022004 ML22172A2132022-06-22022 June 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML22173A0172022-06-22022 June 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Point Beach Nuclear Plant IR 05000266/20210062022-03-0202 March 2022 Annual Assessment Letter for Point Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021006 and 05000301/2021006) ML22041B0752022-02-10010 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000266/2022002 ML21253A1672021-09-10010 September 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000266/2022010 05000301/2022010 IR 05000266/20210052021-09-0101 September 2021 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021005 and 05000301/2021005) ML21214A2812021-08-0202 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21180A2302021-06-29029 June 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2021004 and 05000301/2021004 ML21074A3962021-03-15015 March 2021 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000266/2021010; 05000301/2021010 IR 05000266/20200062021-03-0404 March 2021 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020006 and 05000301/2020006) IR 05000266/20200052020-09-0101 September 2020 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020005 and 05000301/2020005) ML20218A4322020-08-0505 August 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2020004 ML20168A8912020-06-15015 June 2020 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20190062020-03-0303 March 2020 Annual Assessment Letter for Point Beach Nuclear Plants, Units 1 and 2 (Report 05000266/2019006 and 05000301/2019006) IR 05000266/20190052019-08-28028 August 2019 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2019005 and 05000301/2019005) ML19190A1532019-07-0909 July 2019 Ltr. 07/09/19 Point Beach Nuclear Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000266/2019012; 05000301/2019012 (DRS-G.Hausman) ML19136A1402019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19094B1182019-04-0404 April 2019 Ltr. 04/04/19 Point Beach Nuclear Plant, Units 1 and 2 - Request for Information for an NRC Design Bases Assurance Inspection (Program): Implementation of the EQ Program; Inspection Report 05000266/2019013 and 05000301/2019013 (DRS-B.Jose) IR 05000266/20180062019-03-0404 March 2019 Annual Assessment Letter for Point Beach Nuclear Plant (Report 05000266/2018006 and 05000301/2018006) ML19037A3102019-02-0505 February 2019 Ltr. 02/05/19 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for the Cyber-Security Full Implementation Inspection, Notification to Perform Inspection; Inspection Report 05000266/2019412; 05000301/2019412 (DRS-G.Hausman) ML19024A2772019-01-24024 January 2019 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2019001 (DRS-M.Domke) IR 05000266/20180052018-08-28028 August 2018 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2018005 and 05000301/2018005) IR 05000266/20170062018-03-0202 March 2018 Annual Assessment Letter for Point Beach Plant, Units 1 and 2 (Report 05000266/2017006 and 05000301/2017006) IR 05000266/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000266/2017005 and 05000301/2017005) ML17088A7242017-03-29029 March 2017 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000266/2017007; 05000301/2017007 IR 05000266/20160062017-03-0101 March 2017 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2016006 and 05000301/2016006) ML17039B0182017-02-0808 February 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Point Beach Nuclear Plant, Units 1 and 2 - Inspection Report 05000266/2017008; 05000301/2017008 IR 05000266/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant Units 1 and 2 (Report 05000266/2016005; 05000301/2016005) IR 05000266/20150062016-03-0202 March 2016 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Inspection Report 05000266/2015006 and 05000301/2015006) IR 05000266/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2015005; 05000301/2015005) ML15131A3132015-05-0808 May 2015 Ltr. 05/08/15 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for an NRC Triennial Permanent Modifications and 10 CFR 50.59 (Mod/50.59) Baseline Inspection 05000266/2015010; 05000301/2015010 (Jjc) ML15124A9012015-05-0101 May 2015 Ltr. 05/01/15 Point Beach Nuclear Plant, Unit 2 - Notification of NRC Inspection and Request for Information (Msh) IR 05000266/20140012015-03-0404 March 2015 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2014001; 05000301/2014001) ML15050A2702015-02-19019 February 2015 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 ML14245A1662014-09-0202 September 2014 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20130012014-03-0404 March 2014 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2013001; 05000301/2013001) ML14038A3472014-02-0606 February 2014 ISI Request for Information ML13246A2212013-09-0303 September 2013 2013 Point Beach MOC Letter Combined ML13172A4072013-06-20020 June 2013 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000266-13-010; 05000301-13-010 ML13129A1952013-05-0909 May 2013 Ltr 5/9/13 Point Beach Ti 2515-182 Phase 2 Request for Information IR 05000266/20120012013-03-0404 March 2013 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (05000266/2012001; 05000301/2012001) 2024-02-05
[Table view] Category:Letter
MONTHYEARML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-2024-001, Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-01-26026 January 2024 Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24005A3242024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0040 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23352A2752024-01-23023 January 2024 Issuance of Amendment Nos. 274 and 276 Regarding Revision to Technical Specification 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-174, Subsequent License Renewal Application - Third Annual Update2023-12-13013 December 2023 Subsequent License Renewal Application - Third Annual Update L-2023-176, Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-159, Part 3 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 3 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks and Security Event Notifications Final Rule IR 05000266/20234022023-11-14014 November 2023 Security Baseline Inspection Report 05000266/2023402 and 05000301/2023402 ML23279A0672023-11-0909 November 2023 Issuance of Relief Request I6 RR 02 - Examination of the Unit 2 Steam Generator Feedwater Nozzle Extension to Nozzle Weld Sixth 10 Year Inservice Inspection Program Interval IR 05000266/20230032023-10-16016 October 2023 Integrated Inspection Report 05000266/2023003 and 05000301/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published L-2023-128, License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program2023-09-19019 September 2023 License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program ML23243A9102023-09-0606 September 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors IR 05000266/20235012023-08-29029 August 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000266/2023501 and 05000301/2023501 ML23208A2262023-08-28028 August 2023 Exemption from the Requirements of 10 CFR 50,46, Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Reactors (EPID L-2022-LLE-0026) - Letter ML23208A0952023-08-28028 August 2023 Issuance of Amendment Nos. 273 and 275 Regarding Revising Licensing Basis to Address Generic Safety Issue-191 and Respond to Generic Letter 2004-02 Using a Risk Informed Approach IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) ML23160A0642023-08-21021 August 2023 Issuance of Amendment Nos. 272 and 274 Regarding Revision to Use Beacon Power Distribution Monitoring System L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update ML23221A0522023-08-0909 August 2023 Confirmation of Initial License Examination, March 2024 L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment L-2023-089, Refueling Outage Owner'S Activity Report (OAR-1) Unit 2 for Inservice Inspections2023-07-24024 July 2023 Refueling Outage Owner'S Activity Report (OAR-1) Unit 2 for Inservice Inspections IR 05000266/20230022023-07-18018 July 2023 Integrated Inspection Report 05000266/2023002 and 05000301/2023002 IR 05000266/20234012023-07-13013 July 2023 Public-Point Beach Nuclear Plant-Security Baseline Inspection Report 05000266/2023401; 05000301/2023401; Independent Spent Fuel Storage Security Inspection Report 07200005/2023401 L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-2023-088, 10 CFR 50.55a Requests, Relief Requests I6-RR-1, I6-RR-2, and I6-RR-3 Sixth Ten-Year Inservice Inspection Program Interval2023-06-27027 June 2023 10 CFR 50.55a Requests, Relief Requests I6-RR-1, I6-RR-2, and I6-RR-3 Sixth Ten-Year Inservice Inspection Program Interval ML23171B1062023-06-21021 June 2023 Info Meeting with a Question and Answer Session to Discuss NRC 2022 EOC Plant Performance Assessment of Ptbh, Units 1 and 2 ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 L-2023-075, Response to Request for Additional Information (RAI) Regarding Exemption Request, License Amendment Request and Revised Response in Support of a Risk-Informed Resolution of Generic Letter 2004-022023-06-0909 June 2023 Response to Request for Additional Information (RAI) Regarding Exemption Request, License Amendment Request and Revised Response in Support of a Risk-Informed Resolution of Generic Letter 2004-02 L-2023-073, Subsequent License Renewal Application, Second Annual Update Request for Additional Information Set 1 Response2023-06-0101 June 2023 Subsequent License Renewal Application, Second Annual Update Request for Additional Information Set 1 Response ML23103A1332023-06-0101 June 2023 Issuance of Amendment Nos. 271 and 273 Regarding Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal ML23118A1762023-05-0404 May 2023 Audit Summary for License Amendment Request Regarding Risk-Informed Approach for Closure of Generic Safety Issue 191 IR 05000266/20230012023-05-0101 May 2023 Integrated Inspection Report 05000266/2023001 and 05000301/2023001 ML23114A1222023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-2023-058, 2022 Annual Monitoring Report2023-04-10010 April 2023 2022 Annual Monitoring Report L-2023-021, Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-03-28028 March 2023 Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2023-028, and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2023-03-27027 March 2023 and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications 2024-02-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 18, 2010 Mr. Larry Meyer Senior Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNIT 1 INFORMATION REQUEST FOR AN NRC POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL
Dear Mr. Meyer:
On August 9, 2010, the NRC will begin a Post-Approval Site Inspection for License Renewal at Point Beach Nuclear Plant Unit 1. A team of five inspectors will perform this 3-week inspection in accordance with NRC Inspection Procedure (IP) 71003. The inspection will include two weeks on-site, the week of August 9, 2010, and the week of August 23, 2010.
This inspection will focus on verifying that license conditions added as part of the renewed license, license renewal commitments, and selected aging management programs are implemented in accordance with Title 10 of the Code of Federal Regulations (CFR) Part 54, Requirements for the Renewal of Operating Licenses for Nuclear Power Plants.
In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for information needed for the inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection. Insofar as possible, this information should be provided electronically to the lead inspector. The information request has been divided into two groups:
- The first group lists information necessary for our initial inspection scoping and in-office preparation activities. During the in-office preparation activities, the team will identify as much as possible the information and activities to be reviewed during the inspection. This information should be provided to the lead inspector by July 23, 2010.
- The second group includes the additional information required for the team to review the selected activities. This information should be available to the team onsite August 9, 2010.
It is also requested that corrective action documents and/or questions developed during the inspection be provided to the lead inspector as the documents are generated.
The lead inspector for this inspection is Dr. Stuart Sheldon. We understand that our licensing contact for this inspection is Ms. Fritzie Flentje of your organization. If there are any questions about the inspection or the material requested in the enclosure, please contact the lead inspector at (630) 829-9727 or via e-mail at Stuart.Sheldon@nrc.gov.
L. Meyer This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-266 License No. DPR-24
Enclosure:
Request for Information Post-Approval Site Inspection for License Renewal cc w/encl: Distribution via ListServ
INFORMATION REQUEST POST APPROVAL SITE INSPECTION FOR LICENSE RENEWAL Inspection Report: 05000266/2010011 (DRS)
Inspection Dates: August 9, 2010 - August 27, 2010 Inspection Procedure: IP 71003 Post-Approval Site Inspection for License Renewal Lead Inspector: Stuart Sheldon, Lead Inspector (630) 829-9727 Stuart.Sheldon@nrc.gov I. Information Requested Prior to the On-site Inspection Week The following information is requested by July 23, 2010, or sooner, to facilitate inspection preparation. If you have any questions regarding this information, please call the team leader as soon as possible. (Please provide the information electronically in pdf files, Excel, or other searchable formats, preferably on some portable electronic media (e.g. CDROM, DVD, etc.). The portable electronic media should contain descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information in lists should contain enough information to be easily understood by someone who has knowledge of light water reactor technology).
- 1. Provide a list of your license renewal commitments with the completion status of each. If a commitment is not complete, please provide an anticipated completion date.
- 2. For each complete commitment, please provide documentation demonstrating that the commitment has been completed.
- 3. For any commitment that has been changed, please provide documentation of the commitment change process, and any associated justification.
- 4. Provide a list of your Aging Management Programs (AMPs), copies of the program basis documents for each, and a listing of the action tracking items for each.
- 5. For AMPS that are one-time inspection programs, provide a list of completed work order numbers for inspections that have been completed. This may be incorporated with the previous item.
1 Enclosure
INFORMATION REQUEST POST APPROVAL SITE INSPECTION FOR LICENSE RENEWAL
- 6. Provide a list of any newly identified structures, systems and components (SSCs) pursuant to 10 CFR 54.37(b) and RIS-2007-16.
- 7. Provide a copy of your updated final safety analysis report (UFSAR), or UFSAR update which includes descriptions of your AMPs.
- 8. Provide a copy of any self-assessment that you have completed related to license renewal.
- 9. Provide current management and license renewal organizational charts.
II. Information requested to be available when the inspectors arrive on-site on August 9, 2010 and during the inspection.
- 1. Documentation demonstrating completion of license renewal commitments that are complete as of the inspection date. For example, this may be in the form of a binder for each commitment which includes the implementing documentation and references.
- 2. Copies of any corrective action documents generated as a result of the teams questions or queries during this inspection.
- 3. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member).
If you have questions regarding the information requested, please contact the lead inspector. It may also help to review the IP 71003 frequently asked questions which are available at:
http://www.nrc.gov/reactors/operating/licensing/renewal/introduction/inspections/faq-ip71003.html 2 Enclosure
L. Meyer This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-266 License No. DPR-24
Enclosure:
Request for Information Post-Approval Site Inspection for License Renewal cc w/encl: Distribution via ListServe DISTRIBUTION:
Susan Bagley RidsNrrDorlLpl3-1 Resource RidsNrrPMPointBeach RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak DOCUMENT NAME: G:\DRS\WIP\Ltr. 051810 Point Beach License Renewal RFI SNS.doc 9 Publicly Available 9 Non-Publicly Available 9 Sensitive 9 Non-Sensitive To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy OFFICE RIII RIII NAME SSheldon:ls AMStone DATE 05/12/10 05/18/10 OFFICIAL RECORD COPY