PRELIMINARY INFORMATION - NOT FOR PUBLIC DISCLOSURE UNTIL VERIFICATION THAT LICENSEE HAS RECEIVED ACTION May 7, 2010 EN 10-022 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION Licensee: Southern Nuclear Operating Company, Inc. EA-10-009 Edwin I. Hatch Nuclear Plant Docket No. 50-366
Subject:
ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION AND NOTICE OF VIOLATION This is to inform the Commission that a Notice of Violation associated with a White Significance Determination Process finding will be issued on or about May 12, 2010, to Southern Nuclear Operating Company, Inc. (Licensee), as a result of inspections at the Edwin I. Hatch Nuclear Plant. This finding, an issue with low to moderate safety significance, which will require additional NRC inspections, was determined to have a cross-cutting aspect in the Operating Experience component of the Problem Identification and Resolution Area (P.2.(b)). Between 1988 and 2009, the Licensee failed to establish and perform preventative maintenance activities on components having a specific lifetime. This led to a surveillance failure which declared the 2A Emergency Diesel Generator (EDG) inoperable.
In lieu of a Regulatory Conference, the Licensee submitted a written response that addressed additional plant specific factors. The response did not dispute the apparent violation or the cross-cutting issue but stated that the Licensee did not agree with the color of the finding. After reviewing the information developed during the inspection and the additional information provided by the licensee, the staff concluded that the inspection finding is appropriately characterized as White.
A Notice of Violation is included based on the licensees failure to meet Technical Specification 5.4.1, which requires, in part, that procedures shall be established, implemented, and maintained covering the applicable procedures recommended in Regulatory Guide 1.33. Regulatory Guide 1.33, states, in part, preventive maintenance schedules should be developed to specify replacement of parts that have a specific lifetime. Contrary to this requirement, the Licensee failed to replace electrolytic capacitors in components which could affect equipment reliability that have been in service for longer than their qualified life of 10 years. This resulted in a capacitor failure in the #2A EDG loss of off-site power timer card which caused the EDG to fail a surveillance test and be declared inoperable.
It should be noted that the licensee has not been specifically informed of the enforcement action.
The schedule of issuance and notification is:
Mailing of Final Significance Determination May 12, 2010 Telephone Notification of Licensee May 12, 2010 The State of Georgia will be notified.
Contacts: Gerry Gulla, OE, (301) 415-2872 Nick Hilton, OE, (301) 415-3055 PRELIMINARY INFORMATION - NOT FOR PUBLIC DISCLOSURE UNTIL VERIFICATION THAT LICENSEE HAS RECEIVED ACTION
PRELIMINARY INFORMATION - NOT FOR PUBLIC DISCLOSURE UNTIL VERIFICATION THAT LICENSEE HAS RECEIVED ACTION Distribution: EN-10-022, May 7, 2010 OWFN OWFN TWFN EBB Regional Offices Chairman Jaczko EDO OCFO NMSS RI RII Comm. Svinicki DEDR OP CENTER RIII RIV Comm. Apostolakis DEDMRS FSME Comm. Magwood OE OIG MAIL Comm. Ostendorff OGC OCIO ADAMS SECY NRR RES OE staff OCA NSIR ACRS PA OI IP Electronic DISTRIBUTION:
R. Zimmerman, OE N. Hilton, OE G. Gulla, OE OE r/f EN binder ADAMS ML101270189 X PUBLIC X NON-SENSITIVE OFFICE OE:ES OE:BC NAME G. Gulla N. Hilton DATE 05/06/10 05/07/10 OFFICIAL RECORD COPY PRELIMINARY INFORMATION - NOT FOR PUBLIC DISCLOSURE UNTIL VERIFICATION THAT LICENSEE HAS RECEIVED ACTION