Independent Spent Fuel Storage Installation, Radioactive Effluent Release Report 52, January 1, 2009 Through December 31, 2009
ML101250142
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 04/28/2010
From: Stathes G
Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
Download: ML101250142 (1)


Text

Exekrn~.

Exelon Nuclear Peach Bottom Atomic Power Station Telephone 717.456.7014 www.exeloncorp.com Nuclear 1848 Lay Road Delta, PA 17314-9032 April 29, 2010 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001

Subject:

Peach Bottom Atomic Power Station Units 2 and 3 Independent Spent Fuel Storage Installation (ISFSI)

Facility Operating License DPR-44 and DPR-56 NRC Docket 50-277 and 50-278 and ISFSI Docket 72-29 Radioactive Effluent Release Report 52 January 1, 2009 through December 31, 2009 Enclosed is the Radioactive Effluent Release Report 52, January 1, 2009, through December 31, 2009, for Peach Bottom Atomic Power Station Units 2 and 3.

This report is being submitted in compliance with 10CFR50.36a (2) and the Technical Specifications of Operating Licenses DPR-44 and DPR-56, and to fulfill the requirements of ODCM 3.10.2. Additionally, this. report is submitted to satisfy annual effluent reporting requirements for the ISFSI required by the Offsite Dose Calculation Manual (ODCM).

There was a revision made to the ODCM for the 2009 reporting period.

There are no commitments contained in this letter.

If you have any questions or require additional information, please do not hesitate to contact us.

Sincerely, Garey L. Stathes Plant Manager Peach Bottom Atomic Power Station GLS/LJLIAMC/bcb Enclosure (2) ccn 10-39 cc: S. J. Collins, Administrator, Region I, USNRC G. F. Wunder, Project Manager, USNRC

,4oCr F. Bower, USNRC Senior Resident Inspector, PBAPS A4 fA MS-S5