ML101230096
| ML101230096 | |
| Person / Time | |
|---|---|
| Site: | Calvert Cliffs |
| Issue date: | 04/29/2010 |
| From: | Bartnik D Constellation Energy Group, EDF Group |
| To: | Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation |
| References | |
| Download: ML101230096 (2) | |
Text
SAFEGUARDS INFORMATION Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, Maryland 20657 CENG a joint venture of Constellation 60-W Energy e DF CALVERT CLIFFS NUCLEAR POWER PLANT
,April 29, 2010 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:
SUBJECT:
Document Control Desk Calvert Cliffs Nuclear Power Plant; Unit Nos. 1 & 2; Docket Nos. 50-317 & 50-318 Independent Spent Fuel Storage Installation; Docket No. 72-8 Calvert Cliffs Nuclear Power Plant Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 6 As required by 10 CFR 50.54(p)(2) and 10 CFR 72.186, changes to the Calvert Cliffs Nuclear Power Plant Security Plan, Training and Qualification Plan, Safeguards Contingency Plan and Independent Spent Fuel Storage Installation Security Program, Revision 6 (Attachment 1) are being provided.
Attachment (2) provides a Table of Deviations which details where Calvert Cliffs Nuclear Power Plant deviates from the industry template and why.
This revision does not decrease the effectiveness of the Plan and is being submitted under the provisions of 10 CFR 50.54(p).
This cover letter is not subject to protective requirements, the Attachment is subject to Safeguards Information protection according to 10 CFR 73.21 upon separation from the attachment, and this cover letter is to be considered Decontrolled.
SDDý f t A
SAFEGUARDS INFORMATION
Document Control Desk April 29, 2010 Page 2 Should you have questions regarding this matter, please contact Mr. Douglas E. Lauver at 410-495-5219.
Very truly yours, Donald J. Bartnik Director - Security DJB/RDW/bjd Attachments:
(1)
Calvert Cliffs Nuclear Power Plant Security Plan, Training and Qualification Plan, Safeguards Contingency Plan andIndependent Spent Fuel Storage Installation Security Program, Revision 6 (Safeguards Information)
(2)
Table of Deviations cc:
S. J. Collins, NRC V. Ordaz, NMSS (Without Attachments)
D. V. Pickett, NRC Resident Inspector, NRC S. Gray, DNR