MONTHYEARML24011A2332024-01-11011 January 2024 Request for Additional Information - License Amendment Request (ML23058A064) (EPID L-2023-LLA-0026 - Three Mile Island, U2: Amendment Historic and Cultural Resources) ML23187A0202023-06-29029 June 2023 TMI Unit 2 RAI Related to the Amended Post-Shutdown Decommissioning Activities Report ML23135A3992023-05-12012 May 2023 (External_Sender) Section 106 Consultation - NRC NHPA for Three Mile Island Unit 2 ML23159A1642023-05-11011 May 2023 Email TMI-2 Pol Am. 67 SE Minor Discrepancies ML23107A2232023-04-14014 April 2023 Response Re State Consultation-TMI-2 Solutions - Draft EA Fonsi Criticality Exemption Request ML23094A1482023-03-30030 March 2023 TMI-2 TS 6.0 Draft Wording Agreement ML23090A2142023-03-30030 March 2023 Asnyder, NRC Email from Tdevik, Energysolutions, Three Mile Island, Unit 2 -Response Regarding MC&A TS Change, Modification ML23094A0602023-03-30030 March 2023 TMI-2 Response on Draft TS Wording ML23068A4682023-03-0909 March 2023 Response Re State Consultation - License Amendment Request TMI-2 Solutions - Update Technical Specifications and Remove Certain License Conditions Applicable to Pdms ML23057A0062023-02-24024 February 2023 State Consultation - License Amendment Request TMI-2 Solutions - Update Technical Specifications and Remove Certain License Conditions Applicable to Pdms ML23051A0412023-02-15015 February 2023 Email from TMI-2 Solutions Regarding Commitment Date, Dated 02/15/2023 ML22364A1942022-12-30030 December 2022 Email Mitigation for Hydrogen Concerns Commitment, Dated December 30, 2022 ML22357A0142022-12-22022 December 2022 NRC Request for Additional Information Related to the TMI-2 Pdms Transition License Amendment Request ML22321A0072022-11-16016 November 2022 Material Control and Accounting RAI Response Clarification Call Docket No 50-320 ML23069A1582022-09-22022 September 2022 NRC Response TMI-2 Solutions Exemption Question ML22214A0482022-08-0101 August 2022 TMI-2 Response: License Amendment Request TMI-2 Solutions Physical Materials Security Plan - Revised Modified License Condition 2.C(2) ML22208A0492022-07-21021 July 2022 State Consultation Response: License Amendment Request TMI-2 Solutions Physical Materials Security Plan ML22199A2762022-07-18018 July 2022 E-mail from A. Snyder, NRC, to B. Werner, PDEP, Regarding State Consultation Proposed Conforming Amendment Related to Proposed Exemption Request from Certain Record Retention Requirements ML22199A2772022-07-15015 July 2022 E-mail Attachment: Federal Register Notice - Volume 87 ML22189A2032022-07-0808 July 2022 E-mail from A. Snyder, NRC, to B. Werner, PA Department of Environment Protection - Three Mile Island, Unit 2 - State Consultation - License Amendment Request TMI-2 Solutions Physical Materials Security Plan ML22189A2042022-06-28028 June 2022 NRC-2022-0131-0001_Content - Federal Register Vol. 87, No. 123 ML22143A8902022-05-23023 May 2022 Request for Additional information- TMI-1 ISFSI Only Physical Security License Amendment Request ML22131A1382022-05-10010 May 2022 E-mail from T. Devik, Energysolutions TMI-2, to A. Snyder, NRC, Physical Security Plan May 9 Submittal Typo Correction ML22125A0162022-05-0303 May 2022 Email from T Devik to a Snyder: Three Mile Island 2 - Security Plan Proposed Revision License Condition 2.C.(2) (EPID: L-2021-LLA-0103) Proposed License Condition - May 3, 2022 Response Courtesy Copy ML22125A0102022-05-0303 May 2022 Proposed Action- Proposed Fonsi for TMI-1 Exemption Request from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) Notification of Commonwealth of Pennsylvania Response ML22125A0092022-05-0303 May 2022 Proposed Action- Proposed Fonsi for TMI-1 Exemption Request from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) Notification of Commonwealth of Pennsylvania ML22125A0132022-04-28028 April 2022 Security Plan Proposed Revision License Condition 2.C.(2) (EPID: L-2021-LLA-0103) Proposed License Condition - Partial Response ML22125A0122022-04-28028 April 2022 Clarification RAI Partial Response Email from C Smith to a Snyder ML22110A0212022-04-19019 April 2022 Security Plan Proposed Revision License Condition 2.C.(2) (EPID: L-2021-LLA-0103) Proposed License Condition ML22110A0202022-04-19019 April 2022 Unit 1 Request for Additional Information ML22108A1762022-04-14014 April 2022 E-mail: Proposed Order Conditions for In-Direct Transfer of Licenses Held by Energysolutions, LLC (Zion, TMI Unit-2, La Crosse Boiling Water Reactor, Kewaunee, Energysolutions Radioactive Materials License, and Energysolutions Export Licens ML22102A3062022-03-31031 March 2022 Email from T. Divik, Energy Solutions, to A. Snyder Clarification of Security License Condition Amendment Request ML22094A1812022-03-22022 March 2022 Licensee High Confidence Dates for Submittals ML22108A1022022-03-18018 March 2022 Email from A. Snyder, NRC to G. Van Noordennen, Energy Solutions, Clarification Request - September 21, 2021 Supplement- TMI-2 Physical Security Plan LAR ML22090A0142022-03-17017 March 2022 TMI, Unit 1 - Commonwealth of PA Response to Request for Consultation on the Proposed Revision to the License and the Permanently Defueled Technical Specifications to Align to the Requirements for Permanent Removal of Spent Fuel from the Sp ML22070A1202022-03-10010 March 2022 E-mail from S. Acker, PADEP, to A. Snyder, NRC - Three Mile Island Unit 1, State Consultation - License Amendment Request TMI-1 in Support of the ISFSI Only Security Plan License Amendment Request ML22068A1792022-03-0909 March 2022 Email from a Snyder to Acker State Consultation- License Amendment Request TMI-1 in Support of the ISFSI Only Emergency Plan and Emergency Action Level Scheme ML22068A1672022-03-0909 March 2022 Email from a Snyder to Acker State Consultation - License Amendment Request TMI-1 in Support of the ISFSI Only Security Plan License ML22068A1462022-03-0909 March 2022 Email from a Snyder to Acker Three Mile Island Unit 1, State Consultation- License Amendment Request TMI-1 in Support of the ISFSI Only Tech Spec License Amendment Request ML22090A0232022-03-0909 March 2022 Email from A. Snyder, NRC to Craig Smith, Constellation Energy Generation, License Amendment Request - Proposed ISFSI-Only Technical Specifications, Dated March 9, 2022 ML22047A2392022-02-16016 February 2022 E-mail from D. Kenney to A. Snyder Dated 2/16/2022 TMI Unit 1 Typo Correction to February 8, 2022 Submittal ML22038A9352022-02-0707 February 2022 TMI-2 Pdms LAR Email Dated 2/7/2022 from T. Smith, NRC to G. Van Noordennen ML22034A6702022-02-0303 February 2022 LTR-22-0020 Eric Epstein, E-mail Follow-up on Decommissioning and Tax Question from December 8, 2021 on TMI Cleanup Funding, Docket Id NRC-2021-0230 - Region I Response ML22343A1612021-11-0909 November 2021 Shpo Email 11-9-2021 Alowery to Gvannoordennen and Hpell ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21230A3812021-08-18018 August 2021 TMI-1 ISFSI-Only Security Plan License Amendment Request ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application 2024-01-11
[Table view] |
Text
Barber, Scott From: Barkley, Richard Sent: Monday, November 23, 2009 10:50 AM To: Cullingford, Michael Cc: Glitter, Joseph; Bellamy, Ronald; Barber, Scott
Subject:
RE: 11721/2009 TMI Contamination Control Event Mike - Thanks forthe heads up. I have been on the periphery of this issue. Ron or Scott can give you more details if needed.
I'll also forward a ,recent staff communication in this matter.
RichardS. Brkley. PE Technical Communications Assistant, Region I - ...........
__1610) 3375065 -- --
(b)( 6 )
Pleaseconsider the environment before printing this e-maiL. Thank you.
From: Cullingford, Michael Sent: Monday, November 23, 2009 10:17 AM To: Ba'rkley, Richard Cc:. Gitter, Joseph
Subject:
-FW: 11/21/2009 TMI Contamination Control Event Richard: fyi .................... mike From: Cullingford, Michael Sent: Monday, November 23, 2009 10:13 AM To: Schwartzman, Jennifer
Subject:
FW: 11/21/2009 TMI Contamination Control Event A summary of the subject TMI event as we know it today. Based on what we know, ,it is likely that this event would not even be rated on the INES scale. No operating limit was exceeded and no contamination outside the containment building has been detected.
Approximately at 4 PM Saturday 11/21 TMI had an event involving loss of contamination control inside containment. At the time the reactor was defueled With a hole cut in the containment wall to support the ongoing SG replacement outage. The licensee is, not sure at this time what activity inside containment led to the problem. Their investigation is focusing on two activities (1) "A"piping loop decontamination activities or (2) some work on a drain line on the B"SG.
At the time of the event 175 workers were inside containment. Of these workers 151 people were: selected for detailed monitoring, based on nasal smears and portal monitor readings. Ofithe 151, preliminarily,-about 19 people have potentially received doses greater than 10 mR. The highest dose to a worker was approximately 38 mR, far below the yearly NRC limit of 5000,mrem. No site worker left the site with external contamination.
_ontamination levels inside containment have been restored to pre'event levels and cleanup of ecoomnw vt VW F/Gedom of InmwnUoon AcL P ..........
-O
containment surfaces is in progress. The tarp that was covering the containment opening was contaminated on its inside surface and is in the process of being replaced.
With the open equipment hatch and the SG opening there was the potential for a release outside of containment. At the time of the event a slight positive pressure existed in containment. This has now been corrected to what it should be, ie a slightly negative pressure. Based on readings from radiation monitors present at the SG opening and the duration of the positive pressure, the estimates of release levels are still less than one percent of the quarterly limit in the licensee's offsite dose calculation manual.
2