MONTHYEARML1002001312009-12-21021 December 2009 Report No. 0900634.401, Revision 2, Updated Leak-Before-Break Evaluation for Several RCS Piping at Prairie Island Nuclear Generating Plant, Units 1 & 2 Project stage: Request L-PI-09-134, License Amendment Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology2009-12-22022 December 2009 License Amendment Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology Project stage: Request ML1005701342010-02-25025 February 2010 Acceptance Review of LAR to Apply Leak-Before-Break Methodology (TAC Nos. ME2976 and ME2977 Project stage: Acceptance Review ML1011708142010-05-0606 May 2010 Request for Withholding Information from Public Disclosure for Prairie Island Nuclear Generation Plant, Units 1 and 2 Project stage: Withholding Request Acceptance ML1011708332010-05-0606 May 2010 Request for Withholding Information from Public Disclosure for Prairie Island Nuclear Generating Plant, Units 1 and 2 Project stage: Withholding Request Acceptance ML1011802112010-05-0606 May 2010 Request for Withholding Information from Public Disclosure for Prairie Island Nuclear Generating Plant, Units 1 and 2 Project stage: Withholding Request Acceptance ML1015506682010-06-10010 June 2010 Request for Additional Information Related to License Amendment Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-before-Break Project stage: RAI L-PI-10-077, Supplement to License Amendment Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology Additional .2010-07-23023 July 2010 Supplement to License Amendment Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology Additional . Project stage: Supplement L-PI-10-085, Clarification of Responses to Requests for Additional Information Regarding a License Amendment Request for Certain Applications of Leak-Before-Break Methodology2010-08-20020 August 2010 Clarification of Responses to Requests for Additional Information Regarding a License Amendment Request for Certain Applications of Leak-Before-Break Methodology Project stage: Response to RAI L-PI-10-094, Supplement to License Amendment Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology - Response to RAI2010-10-0808 October 2010 Supplement to License Amendment Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology - Response to RAI Project stage: Supplement ML1032803982010-12-14014 December 2010 RAI, Related to Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of LBB Methodology Project stage: RAI L-PI-11-006, Supplement to License Amendment Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology - Response to RAI2011-01-14014 January 2011 Supplement to License Amendment Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology - Response to RAI Project stage: Supplement L-PI-11-019, Supplement to License Amendment Request to Exclude Dynamic Effects Associated with Certain Postulated Pipe Ruptures from Licensing Basis Based Upon Application of Leak-Before-Break Methodology - Response to Requests for Clarification2011-02-23023 February 2011 Supplement to License Amendment Request to Exclude Dynamic Effects Associated with Certain Postulated Pipe Ruptures from Licensing Basis Based Upon Application of Leak-Before-Break Methodology - Response to Requests for Clarification Project stage: Supplement L-PI-11-038, Supplement to License Amendment Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology2011-04-0606 April 2011 Supplement to License Amendment Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology Project stage: Supplement ML1120106962011-07-22022 July 2011 RAI, Related to Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology Project stage: RAI L-PI-11-070, Supplement to License Amendment Request to Exclude Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology - Response to RAI2011-08-0909 August 2011 Supplement to License Amendment Request to Exclude Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology - Response to RAI Project stage: Supplement ML1122008562011-10-27027 October 2011 Operating Plant, Units 1 and 2 - Issuance of Amendments Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology Project stage: Approval 2010-07-23
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 6, 2010 Mr. Mark A. Schimmel Site Vice President Prairie Island Nuclear Generating Plant Northern States Power Company - Minnesota 1717 Wakonade Drive East Welch, MN 55089-9642
SUBJECT:
REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 (TAC NOS. ME2976 AND ME2977)
Dear Mr. Schimmel:
By letter dated December 22, 2009 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML100200129), you submitted an affidavit dated December 21, 2009, executed by J. A. Gresham of Westinghouse Electric Company, requesting that the information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390:
WCAP-15379, "Technical Justification for Eliminating Pressurizer Surge Line Rupture as the Structural Design Basis for Prairie Island Unit 2 Nuclear Plant," dated March 2000.
A nonproprietary version of the document has been placed in the Nuclear Regulatory Commission's (NRC's) Public Document Room and added to the ADAMS Public Electronic Reading Room (ADAMS Accession No. ML100200133).
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
(a)
The information reveals the distinguishing aspects of a process (or component, structure, tool, method, etc.) where prevention of its use by any of Westinghouse's competitors without license from Westinghouse constitutes a competitive advantage over other companies.
(c)
Its use by a competitor would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product.
(e)
It reveals aspects of past, present, or future Westinghouse or customer funded development plans and programs of potential commercial value to Westinghouse.
Additionally, the affidavit stated that the information was transmitted to the NRC in confidence, has been held in confidence, is of a type customarily held in confidence, and is not available in public sources.
M. Schimmel
- 2 We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the applicable portions of the document marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-4037.
Sincerely, Thomas J. Wengert, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306 cc:
J. A. Gresham, Manager Regulatory Compliance and Plant Licensing Westinghouse Electric Company, LLC P.O. Box 355 Pittsburgh, PA 15230-0355 Additional Distribution via ListServ
ML101170814 RidsNrrLABTully Resource RidsNrrPMPrairielsland Resource OFFICE NRR/DORLlLPL3-1/PM NRRIDORLlLPL3-1/LA NRR/DCI/CPNB/BC NRRIDORLlLPL3-1/BC NAME TWengert BTuily TLupold /JTsao for RPascarelli DATE 05/05/10 04/29/10 05/06/10 05/06/10