MONTHYEARML24290A1572024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds (L-2024-LLR-0047) ML24290A1552024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley, Hatch, and Vogtle 1 and 2 - Proposed Alternative Request for Code Case N-572 ML24289A2002024-10-15015 October 2024 NRR E-mail Capture - for Your Action - RAI - Proposed License Amendment Request (LAR) for Vogtle Electric Generating Plant, Units 3 and 4 TS 3.7.6 Action E and SR 3.7.6.5 (L-2024-LLA-0083) ML24282A6722024-10-0808 October 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24261B8062024-09-17017 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24261B9282024-09-17017 September 2024 NRR E-mail Capture - for Your Action Discussion Points - Steam Generator Tube Inspection Call with SNC Regarding Vogtle, Unit 3 ML24257A0212024-09-11011 September 2024 Document Request for Oconee Nuclear Station - Radiation Protection Inspection - Inspection Report 2024-04 ML24250A0242024-09-0606 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24250A0852024-09-0606 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24248A0822024-09-0303 September 2024 NRR E-mail Capture - Acceptance Review for Turkey Point Alternative Request VR-02 for Certain Motor-Operated Isolation Valves (L-2024-LLR-0059) ML24247A0092024-09-0303 September 2024 NRR E-mail Capture - Fyi - Revised Estimated Completion Date - Vogtle 3 and 4 - UFSAR Scheduler Exemption Request ML24250A1132024-09-0303 September 2024 Inspection Report 2024004 Radiation Safety Baseline Inspection Information Request ML24250A1922024-08-29029 August 2024 Amendment Nos. 223/206 (1) - Email ML24234A0842024-08-21021 August 2024 Notification of Inspection and Request for Information ML24234A2972024-08-21021 August 2024 August 21, 2024 - Oconee Nuclear Station, Units 1, 2, and 3 - Acceptance of Requested Licensing Action License Amendment Request to Revise Technical Specification 3.7.7 ML24234A0142024-08-20020 August 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Spent Fuel Storage License Amendment Request (LAR) (L-2023-LLA-0142) ML24232A1812024-08-19019 August 2024 Summer_2024-04_RP Information Request ML24232A0052024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - LAR and Exemption Request to Remove Tier 1 and Tier 2 Requirements for Vogtle 3 and 4 ML24253A0722024-08-15015 August 2024 Perspectives on Proposed Removal of Tier 1 and Tier 2 Requirements ML24225A0062024-08-0909 August 2024 NRR E-mail Capture - Acceptance Review - Vogtle 3 and 4 - LAR Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves), Action a and SR 3.7.6.6 (L-2024-LLA-0101) ML24211A0872024-07-27027 July 2024 EN 57079 Paragon Energy Solutions Final - No Active Links ML24206A0252024-07-20020 July 2024 NRR E-mail Capture - for Your Comments - State of Georgia - Vogtle Unit 1 - Emergency License Amendment Request for Technical Specification 3.7.9 ML24199A1592024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information - Vogtle 3 and 4 - Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Report ML24198A1672024-07-16016 July 2024 NRR E-mail Capture - Acceptance Review Vogtle 3 and 4 - License Amendment Request Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Surveillance Requirement L-2024-LLA-0083 ML24197A2292024-07-15015 July 2024 Email from Mark Yoo (NRC) to Steve Snider (Duke) - Oconee SLRA - RAI - 2024 Annual Update ML24197A1572024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Farley and Vogtle 1 and 2, LAR - TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24197A0172024-07-12012 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24190A0462024-07-0505 July 2024 Notification of Inspection and Request for Information ML24190A0412024-07-0505 July 2024 Notification of Inspection and Request for Information ML24191A4232024-07-0303 July 2024 RAI2 NRC Response to Fws ESA Crystal River Unit 3 LTP ML24180A0012024-06-26026 June 2024 NRR E-mail Capture - Acceptance Review Farley 1 and 2 and Vogtle 1 and 2 - Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) (L-2024-LLR-0041) ML24179A1292024-06-24024 June 2024 Acceptance Review for LAR to Revise TS to Adopt TSTF-234-A, Revision 1 ML24190A1382024-06-18018 June 2024 Supplement to NRC Request for Concurrence with ESA Determinations for Crystal River Unit 3 LTP ML24170A9352024-06-18018 June 2024 NRR E-mail Capture - Supplement to Audit Plan - Turkey Point - 18 to 24 Month Fuel Cycle LAR (L-2023-LLA-0161) ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24170A3892024-06-18018 June 2024 NRR E-mail Capture - Acceptance Review for VC Summer Containment Tendon Relief Request (L-2024-LLR-0035) ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24165A1912024-06-13013 June 2024 003 Radiation Safety Baseline Inspection Information Request ML24156A0022024-06-0303 June 2024 VC Summer SLRA - Requests for Additional Information - Set 2 - Email from Marieliz Johnson to Eric Carr ML24149A3532024-05-24024 May 2024 Change in Estimated Review Schedule for Nextera Common Emergency Plan Amendment ML24143A1322024-05-22022 May 2024 May 22, 2024, Verbal Authorization for Duke Energy Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI (RA-24-0152) (EPID L- 2024-LLR-0034) ML24143A0132024-05-20020 May 2024 Achp Response for Crystal River Unit 3 (Achp Project No. 020794) ML24143A0242024-05-20020 May 2024 Draft EA for Crystal River Unit 3 Opportunity for Flhealth Review and Comment ML24143A0212024-05-20020 May 2024 SHPO Response to Initiate Section 106 Consultation for Crystal River Unit 3 ML24178A3422024-05-16016 May 2024 NRR E-mail Capture - Request for Call - Proposed Vogtle 3 & 4 Tier 1 and Tier 2 Exemptions and LAR ML24129A0722024-05-0808 May 2024 VC Summer SLRA - Requests for Confirmation of Information - Set 1 - Email from Marieliz Johnson to Eric Carr ML24130A0112024-05-0808 May 2024 NRR E-mail Capture - Acceptance Review - Turkey Point 3 and 4 - Sixth 10-Year Inservice Testing Interval Proposed Alternative PR-02 (L-2024-LLR-0029) ML24127A0892024-05-0202 May 2024 57079-EN57079-1 - Redline Strikethrough e-mail Re Part 21 Interim Notification of Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker ML24122C6922024-05-0101 May 2024 NextEra Fleet EP Amendment - Demonstration Drill 2024-09-06
[Table view] |
Text
Franke, Mark From: Chou, Rich Sent: Tuesday, November 24, 2009 11:42 AM To: Franke, Mark
Subject:
RE: Curing Time for the Containment Wall Opening with Tendons Mark:
Yes, I will be here next week. Just let me know the time.
From: Franke, Mark Sent: Tuesday, November 24, 2009 9:40 AM To: Chou, Rich
Subject:
RE: Curing Time for the Containment Wall Opening with Tendons Thanks Rich.
We can stop by and brief Kriss when he returns to office.
Are you here next week?
From: Chou, Rich Sent: Tuesday, November 24, 2009 9:38 AM To: Franke, Mark Cc: Chou, Rich
Subject:
Curing Time for the Containment Wall Opening with Tendons Mark:
I received responses for Kriss question of concrete curing time from the Senior Resident Inspectors for the concrete curing time between the new concrete pour and the application of retension of tendons during the Steam Generator and Reactor Head Replacement Projects. I surveyed the sites with tendons installed in the containment walls and domes in Region II.
- 1. Five sites in Region II to have tendons installed in the Containments.
A. Oconee 1, 2, and 3 B. Turkey Points 3 and 4 C. Crystal River 3 D. Summer 1 E. Vogtle 1 and 2
- 2. Concrete curing time between the concrete pour and retention of tendons A. Oconee 1, 2, and 3 3 days during the Steam Generator Replacement B. Turkey Point 3 and 4 7 days minimum during the Reactor Head Replacement C. Crystal River 3 Unknown yet, the original schedule of 7 days during this Steam Generator Replacement prior to the repair of the delaminated Containment wall 112
- 3. Summer 1 Steam Generators were replaced around 1994 and no Containment Wall was cut.
- 4. Vogtle 1 and 2 Steam Generators are in good condition now.