DCPP License Renewal Aging Management Program Audit Plan
ML101120117
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 04/07/2010
From:
License Renewal Projects Branch 2
To:
Ferrer, N B, NRR/DLR, 415-1045
References
Download: ML101120117 (2)


Text

License Renewal Aging Management Program Audit Plan Diablo Canyon Nuclear Power Plant

1.

Background

By letter dated November 23, 2009, Pacific Gas & Electric Company (PG&E), submitted an application pursuant to Title 10 of the Code of Federal Regulations, Part 54 (10 CFR Part 54) for renewal of Operating License Nos. DPR-80 and DPR-82 for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (DCPP), respectively. PG&E requested renewal of the operating licenses for an additional 20 years beyond the current 40-year license terms, which expire on November 2, 2024 (Unit 1) and August 26, 2025 (Unit 2). The staff from the Division of License Renewal will lead an on-site regulatory audit to gain a better understanding of the documentation and bases for those aging management programs (AMPs) for which PG&E claims consistency with NUREG-1801, Generic Aging Lessons Learned (GALL) Report.

2.

Regulatory Audit Bases License renewal requirements are specified in 10 CFR Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, and the guidance for the NRC staff review is provided in NUREG-1800, Rev. 1, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants (SRP-LR), and NUREG-1801.

3.

Regulatory Audit Scope The scope of this regulatory audit includes those plant AMPs for which PG&E claims consistency with NUREG-1801. It is incumbent on the applicant to ensure that the plant AMP is consistent with the elements of the referenced GALL program or to provide a suitable alternative. The regulatory audit may also include a verification of the aging management review results.

4.

Information and Other Material Necessary for the Regulatory Audit While on site, the project team will review the license renewal application, the AMP basis documents, and other applicant supporting documents as appropriate.

2

5.

Team Assignments Area of Review Assigned Auditor Project Manager Kimberly Green Nathaniel Ferrer Branch Chief Girija Shukla Raj Auluck David Pelton Electrical Cliff Doutt Duc Nguyen Rui Li Mechanical and Materials Omesh Chopra, Argonne National Laboratory (ANL)

Dwight Diercks (ANL)

Yogendra Guard (ANL)

Keith Axler, Center for Nuclear Waste Regulatory Analyses (CNWRA)

Todd Mintz (CNWRA)

Roman Kazban (CNWRA)

James Mancillas (CNWRA)

Structural Abdul Sheikh Barry Oland, Oak Ridge National Laboratory (ORNL)

Dan Naus (ORNL)

Operating Experience Don Brittner Merrilee Banic Specialist Allen Hiser

6.

Logistics The audit will be conducted at Diablo Canyon from April 12 until April 16, 2010, and April 26 until April 30, 2010. Entrance and exit briefings will be held at the beginning and end of this audit, respectively.

7.

Special Requests The staff requests the applicant to make available its condition report database for independent searches by the regulatory audit team.

8.

Deliverables An audit report should be issued within 90 days from the end of the audit.