5000 Dominion Boulevard, Glen Allen, Virginia 23060 Web Address: www.dom.com February 23, 2010 Mr. Larry W. Camper Director, Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Programs U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 SVDominion 10 CFR 2.202 EA-09-204 EA-09-205 Serial No.:
09-755C NL&OS/MAE: RO Docket No.:
50-245 License No.: DPR-21 DOMINION NUCLEAR CONNECTICUT, INC.
MILLSTONE POWER STATION UNIT 1 CLARIFICATION OF ORDERS IMPOSING INCREASED CONTROLS AND FINGERPRINTING AND CRIMINAL HISTORY RECORDS CHECK REQUIREMENTS ON POWER REACTOR LICENSEES UNDERGOING DECOMMISSIONING DATED NOVEMBER 23, 2009 On November 23, 2009, the Nuclear Regulatory Commission (NRC) issued Orders EA-09-204 and EA-09-205 (the Orders) to Dominion Nuclear Connecticut, Inc. (DNC) imposing increased controls for Millstone Power Station Unit 1. The Order imposes requirements on licensees possessing specified radioactive material quantities of concern.
In a December 17, 2009 letter (Serial No. 09-755A), DNC submitted an Answer and response to Order EA-09-205. On February 12, 2010 (Serial No. 09-755B)
DNC submitted an Answer and response to Order EA-09-204.
The purpose of this letter is to document information and clarification provided by emails from you on February 19 and 22, 2010 "that the 90 day implementation deadline in the subject Orders is in abeyance until we (the NRC) have addressed your (DNC's) responses."
If you have any questions, please contact Ms. Margaret A. Earle at (804) 273-2768.
Sincerely, L. N. Hartz Vice President - Nuclear Support Services Commitments made by this letter: None
Serial No. 09-755C MPS U1 EA-09-204 & 205 Page 2 of 2 cc:
Attention: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 U. S. Nuclear Regulatory Commission Region I Regional Administrator 475 Allendale Road King of Prussia, PA 19406-1415 Mr. J. B. Hickman NRC Project Manager U. S. Nuclear Regulatory Commission Two White Flint North Mail Stop T-8 F5 11545 Rockville Pike Rockville, MD 20852-2738 Ms. L. A. Kauffman Region I 475 Allendale Road King of Prussia, PA 19406-1415