ML100830027
| ML100830027 | |
| Person / Time | |
|---|---|
| Site: | Hatch, Vogtle, Farley |
| Issue date: | 03/25/2010 |
| From: | Martin R Plant Licensing Branch II |
| To: | Ajluni M Southern Nuclear Operating Co |
| Baxter Angela, NRR/DORL 301-415-2976 | |
| References | |
| TAC MD7598, TAC MD7599, TAC MD7606, TAC MD7607, TAC MD7665, TAC MD7666 | |
| Download: ML100830027 (3) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 25, 2010 Mr. Mark Ajluni Licensing Manager, SNC Fleet 40 Inverness Center Parkway P.O. Box 1295 Birmingham, AL 35201
SUBJECT:
EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 & 2, JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 & 2, VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 & 2 - CLOSEOUT OF BULLETIN 2007-01 "SECURITY OFFICER ATTENTIVENESS" (TAC NOS. MD7606, MD7607, MD7598, MD7599, MD7665, AND MD7666)
Dear Mr. Ajluni:
On December 12, 2007, the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2007 01, "Security Officer Attentiveness" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML073400150).
Southern Nuclear Operating Company, Inc (the licensee) provided a response, dated February 8,2008 (ADAMS Accession No. ML080420449), to Bulletin 2007-01. Once the licensee response was reviewed for the subject plants, the NRC staff identified a need for additional information. To gather that information, the NRC staff issued a Request for Additional Information (RAI) to the licensee on June 27,2008 (ADAMS Accession No. ML081770481).
The licensee provided a response to the RAI on August 1, 2008 (ADAMS Accession No. ML082180179), which included detailed descriptions of the administrative and managerial controls to deter and address inattentiveness and complicity among licensee security personnel at the subject plants. Due to the sensitivity of the subject matter, some responses may contain Security-Related Information and may not be publicly available.
The NRC staff has reviewed the submitted information and has concluded that your response to Bulletin 2007-01 and the subsequent RAI is adequate for the subject plants. The bases for the NRC's conclusion have been documented in a memorandum, "Security Bulletin 2007-01, Security Officer Attentiveness: Summary Report" (ADAMS Accession No. ML093440311).
Based on this review, your response to the Bulletin 2007-01 is considered closed and no further action is requested of you at this time.
M. Ajluni
- 2 If you have any questions regarding this letter, please feel free to contact me at (301) 415-1493.
Sincerely,
. )
/~.
/
,*:...e~f-// ?C~/~t:*_;"v IRobert. Martin, Senior Project Manaqer Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-321, 50-366, 50-348, 50-364, 50-424, 50-425 cc: Distribution via Listserv
M. Ajluni
- 2 If you have any questions regarding this letter, please feel free to contact me at (301) 415-1493.
Sincerely,
/raj Robert E. Martin, Senior Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-321, 50-366, 50-348, 50-364, 50-424, 50-425 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL2-1Reading RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLpl2-1 Resource RidsOgcRp Resource RidsNrrPMFarley Resource RidsNrrPMVogtle Resource RidsNrrPMHatch Resource RidsNrrLASRohrer Resource RidsRgn2MailCenter Resource AMarkley, DPR/PGCB SStuchell, DPR/PGCB ADAMS Accession No.: ML100830027 OFFICE NRR/LPL2-1 /PM LPL 1-2/LA NRR/LPL2-1/BC NRR/LPL2-1 /PM NAME RMartin ABaxter GKulesa RMartin DATE 3/24/10 3/24/10 3/25/10 3/25/10 OFFICIAL RECORD COpy