MONTHYEARML24283A1192024-10-28028 October 2024 Letter to Shawn Hafen, Re Monticello Subsequent License Renewal Schedule Change L-MT-24-038, Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI2024-10-15015 October 2024 Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI ML24277A0202024-10-0303 October 2024 Operator Licensing Examination Approval Monticello Nuclear Generating Plant, October 2024 IR 05000263/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000263/2024011 ML24199A1752024-10-0101 October 2024 Issuance of Amendment No. 212 Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 L-MT-24-025, Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements2024-09-26026 September 2024 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements L-MT-24-029, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI2024-09-13013 September 2024 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI IR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) L-MT-24-028, Response to RCI for RR-017 ISI Impracticality2024-08-28028 August 2024 Response to RCI for RR-017 ISI Impracticality 05000263/LER-2024-002, Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure2024-08-27027 August 2024 Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure ML24222A1822024-08-27027 August 2024 – Proposed Alternative Request VR-09 to the Inservice Testing Requirements of the ASME OM Code for Main Steam Safety Relief Valves IR 05000263/20244202024-08-21021 August 2024 Security Baseline Inspection Report 05000263/2024420 - Cover Letter IR 05000263/20240022024-08-14014 August 2024 Integrated Inspection Report 05000263/2024002 ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24215A2992024-07-23023 July 2024 Minnesota State Historic Preservation Office Comments on Monticello SLR Draft EIS ML24198A2372024-07-18018 July 2024 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Monticello Nuclear Generating Plant L-MT-24-022, – Preparation and Scheduling of Operator Licensing Examinations2024-07-0909 July 2024 – Preparation and Scheduling of Operator Licensing Examinations L-MT-24-019, Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii)2024-06-10010 June 2024 Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii) ML24164A2402024-06-10010 June 2024 Minnesota State Historic Preservation Office- Comments on Draft Monticello SLR Draft EIS L-MT-24-017, Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-01602024-06-0404 June 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-0160 ML24137A2792024-06-0303 June 2024 Audit Summary for License Amendment Request to Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A1782024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-MT-24-015, Response to Request for Additional Information - Alternative Request VR-09 for OMN-172024-05-16016 May 2024 Response to Request for Additional Information - Alternative Request VR-09 for OMN-17 L-MT-24-013, 2023 Annual Radiological Environmental Operating Report2024-05-14014 May 2024 2023 Annual Radiological Environmental Operating Report ML24135A1902024-05-14014 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report IR 05000263/20240102024-05-13013 May 2024 Age-Related Degrading Inspection Report 05000263/2024010 ML24128A0042024-05-0909 May 2024 Letter to Minnesota State Historic Preservation Office- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renewal Application ML24127A1472024-05-0909 May 2024 Letter to Mille Lacs Band- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renew. Application L-MT-24-016, 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2024-05-0808 May 2024 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance IR 05000263/20240012024-04-29029 April 2024 Plan - Integrated Inspection Report 05000263/2024001 ML24115A2872024-04-25025 April 2024 Sec106 Tribal, Dupuis, Kevin-Fond Du Lac Band of Lake Superior Chippewa ML24115A2962024-04-25025 April 2024 Sec106 Tribal, Larsen, Robert-Lower Sioux Indian Community ML24115A3072024-04-25025 April 2024 Sec106 Tribal, Williams, Jr., James-Lac Vieux Desert Band of Lake Superior Chippewa Indians ML24115A3052024-04-25025 April 2024 Sec106 Tribal, Vanzile, Jr., Robert-Sokaogon Chippewa Community ML24115A2892024-04-25025 April 2024 Sec106 Tribal, Fowler, Thomas-St. Croix Chippewa of Wisconsin ML24115A3022024-04-25025 April 2024 Sec106 Tribal, Stiffarm, Jeffrey-Fort Belknap Indian Community ML24115A2972024-04-25025 April 2024 Sec106 Tribal, Miller, Cole-Shakopee Mdewakanton Sioux Community ML24115A2952024-04-25025 April 2024 Sec106 Tribal, Kakkak, Gena-Menominee Indian Tribe of Wisconsin ML24115A2922024-04-25025 April 2024 Sec106 Tribal, Jensvold, Kevin-Upper Sioux Community ML24115A3062024-04-25025 April 2024 Sec106 Tribal, Wassana, Reggie-Cheyenne and Arapaho Tribes ML24115A2912024-04-25025 April 2024 Sec106 Tribal, Jacskon, Sr., Faron-Leech Lake Band of Ojibwe 05000263/LER-2024-001, Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component2024-04-25025 April 2024 Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component ML24115A2982024-04-25025 April 2024 Sec106 Tribal, Reider, Anthony-Flandreau Santee Sioux Tribe ML24115A3032024-04-25025 April 2024 Sec106 Tribal, Taylor, Louis-Lac Courte Oreilles Band of Lake Superior Chippewa Indians ML24115A3012024-04-25025 April 2024 Sec106 Tribal, Seki, Darrell-Red Lake Nation ML24115A2882024-04-25025 April 2024 Sec106 Tribal, Fairbanks, Michael-White Earth Nation.Docx ML24115A2992024-04-25025 April 2024 Sec106 Tribal, Renville, J. Garret-Sisseton Wahpeton Oyate of the Lake Travers Reservation 2024-09-26
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24290A0452024-10-0707 October 2024 Attachment - Monticello SLRA - 3rd Round Request for Additional Information 3rd Round RAI ML24254A4542024-08-26026 August 2024 RAI-holding Ponds ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval ML24198A2372024-07-18018 July 2024 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Monticello Nuclear Generating Plant ML24141A1782024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24131A0802024-05-10010 May 2024 Final RAI for LAR to Revise TS 3.8.6, Battery Parameters, SR 3.8.6.6 ML24107A1462024-04-15015 April 2024 Final Request for Additional Information Re VR-09 ML24040A0482024-02-12012 February 2024 – Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000263/2024010 ML24022A0212024-01-20020 January 2024 NRR E-mail Capture - Monticello - Request for Additional Information ISI RR-002 Alternative to Use IWB-2500(f) ML23268A0252023-09-25025 September 2023 SLRA - Requests for Confirmation of Information - Set 2 ML23248A3462023-09-0505 September 2023 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant - Decommissioning Funding Status Reports ML23237A4832023-08-25025 August 2023 SLRA - Request for Additional Information - Set 3 ML23219A1072023-08-0707 August 2023 SLRA - Requests for Additional Information - Set 2 - Email from Marieliz Johnson to Shawn Hafen ML23219A1082023-08-0707 August 2023 SLRA - Requests for Additional Information - Set 2 ML23201A0352023-07-24024 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23200A3502023-07-19019 July 2023 SLRA - Requests for Additional Information - Set 1 - Email from Marieliz Johnson to Christopher Domingos ML23200A3512023-07-19019 July 2023 SLRA - Request for Additional Information - Set 1 ML23059A3522023-03-0101 March 2023 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000263/2023010 ML23058A1522023-02-27027 February 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2023002 ML23004A1982023-01-0404 January 2023 NRR E-mail Capture - Draft Request for Additional Information Monticello Nuclear Generating Plant Request Pr 08, HPCI Pump Quarterly Testing ML22206A1662022-07-25025 July 2022 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Monticello Nuclear Generating Plant ML22181A1962022-06-24024 June 2022 NRR E-mail Capture - Draft RAI Monticello Alternative VR-08 ML22175A1602022-06-24024 June 2022 NRR E-mail Capture - RAI Monticello Fuel Oil Storage Tank Inspection ML22131A2652022-05-11011 May 2022 NRR E-mail Capture - Request for Additional Information Xcel Energy Amendment Request to Create a Common Eplan and EOF for Monticello and Prairie Island ML22123A2822022-05-0303 May 2022 NRR E-mail Capture - Request for Additional Information Monticello Alternative VR-10, EFCV Testing Frequency ML21322A2362021-11-18018 November 2021 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2022401 ML21085A8582021-03-26026 March 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000263/2021010 ML21068A2772021-03-0909 March 2021 NRR E-mail Capture - Monticello TSTF-505, Request for Additional Information ML20343A1292020-12-0808 December 2020 NRR E-mail Capture - Request for Additional Information ML20302A1972020-10-26026 October 2020 NRR E-mail Capture - Monticello Request for Additional Information TSTF-505 License Amendment Request ML20191A0252020-07-0101 July 2020 NRR E-mail Capture - Draft Request for Additional Information Monticello Alternative Request RR-016 Related to H8, H9, and H 10 Weld Examinations ML20133K0532020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20134H9282020-05-12012 May 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000263/2020013 ML20120A0272020-04-28028 April 2020 NRR E-mail Capture - Request for Additional Information Monticello Long Term Steam Dryer Inspection Plan ML20099F3622020-04-0606 April 2020 Lr Phase 4 Request for Information ML20055F3672020-02-24024 February 2020 Information Request to Support Upcoming Temporary Instruction 2515/193 Inspection at Monticello Nuclear Generating Plant ML20035F1552020-02-0404 February 2020 NRR E-mail Capture - Request for Additional Information Monticello and Prairie Island Alternative Requests to Adopt Code Cases N-786-3 and N-789-3 (Epids: L-2019-LLR-0078 and L-2019-LLR-0079) ML19270E8652019-09-27027 September 2019 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information (Rbaker) ML19080A2182019-03-21021 March 2019 NRR E-mail Capture - Request for Additional Information Monticello License Amendment Request to Remove Note TS LCO 3.5.1 ML19070A1302019-03-0808 March 2019 Ltr. 03/08/19 Monticello Nuclear Generating Plant - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000263/2019003 (DRS-V.Petrella) ML19031A9132019-01-31031 January 2019 NRR E-mail Capture - Request for Additional Information Monticello License Amendment Request to Adopt 10 CFR 50.69 ML18269A3572018-09-26026 September 2018 NRR E-mail Capture - Request for Additional Information Monticello License Amendment Request to Adopt TSTF-425 ML18173A0512018-06-22022 June 2018 NRR E-mail Capture - Request for Additional Information Monticello Request for Exemption from Appendix R Requirements (L-2018-LLE-0001) ML18130A7472018-05-0909 May 2018 NRR E-mail Capture - Request for Information Monticello TSTF-542 License Amendment Request ML18121A2542018-05-0101 May 2018 Enclosurequest for Additional Information (05/01/2018, E-Mail from C. Jacobs/Dsfm to S. Jurek Monticello Exemption: NRC Clarification Questions on RAI#1 Responses) ML18065A5482018-03-0606 March 2018 EnclosuRAI-1 (non-proprietary) (Letter to T. J. O'Connor First Request for Additional Information for Review of Exemption Request for Five Nonconforming Dry Shielded Canisters 11 Through 15) ML17293A0912017-10-18018 October 2017 NRR E-mail Capture - Request for Additional Information Monticello Request for Exemption from Appendix R Requirements (CAC No. MF9586; EPID L-2017-LLE-00012) ML17235B0012017-08-23023 August 2017 NRR E-mail Capture - Request for Additional Information Monticello EAL Scheme Change Amendment Request ML17221A3882017-08-0909 August 2017 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant License Amendment Request Dated March 24, 2017 Emergency Response Organization ML17219A0752017-08-0707 August 2017 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant License Amendment Request Dated March 24, 2017 Emergency Response Organization 2024-08-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 March 10, 2010 Mr. Timothy J. OConnor Site Vice President Monticello Nuclear Generating Plant Northern States Power Company, Minnesota 2807 West County Road 75 Monticello, MN 55362-9637
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT REQUEST FOR INFORMATION FOR AN NRC POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL
Dear Mr. OConnor:
On June 28, 2010, the NRC will begin a Post-Approval Site Inspection For License Renewal.
A team of five inspectors will perform a 3-week Phase 2 inspection in accordance with NRC Inspection Procedure (IP) 71003. This inspection will include two weeks on-site, the week of June 28, 2010 and the week of July 12, 2010.
This inspection will focus on verifying that license conditions added as part of the renewed license, license renewal commitments, and selected aging management programs are implemented in accordance with Title 10 of the Code of Federal Regulations (CFR) Part 54, Requirements for the Renewal of Operating Licenses for Nuclear Power Plants.
In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for information needed for the inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection. Insofar as possible, this information should be provided electronically to the lead inspector. The information request has been divided into two groups:
- The first group lists information necessary for our initial inspection scoping and in-office preparation activities. During the in-office preparation activities, the team will identify as much as possible the information and activities to be reviewed during the inspection. This information should be provided to the lead inspector by June 11, 2010.
- The second group includes the additional information required for the team to review the selected activities. This information should be available to the team onsite June 28, 2010. It is also requested that corrective action documents and/or questions developed during the inspection be provided to the lead inspector as the documents are generated.
The lead inspector for this inspection is Mrs. Caroline Tilton. We understand that our Regulatory Affairs contact for this inspection is Mr. Ron Baumer of your organization. If there are any questions about the inspection or the material requested in the enclosure, please contact Dr. Stuart Sheldon at (630) 829-9727 or via e-mail at Stuart.Sheldon@nrc.gov.
T. OConnor This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011.
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Jamie Benjamin, Acting Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-263 License No. DPR-22
Enclosure:
Request for Information, Post-Approval Site Inspection for License Renewal cc w/encl: Distribution via ListServ
REQUEST FOR INFORMATION POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL Inspection Report: 05000263/2010008 (DRS)
Inspection Dates: June 28, 2010 - July 16, 2010 Inspection Procedure: IP 71003 Post-Approval Site Inspection for License Renewal Lead Inspector: Caroline Tilton, Lead Inspector (630) 829-9718 Caroline.Tilton@nrc.gov I. Information Requested Prior to the On-site Inspection Week The following information is requested by June 11, 2010, or sooner, to facilitate inspection preparation. If you have any questions regarding this information, please call Dr. Sheldon as soon as possible. (Please provide the information electronically in pdf files, Excel, or other searchable formats, preferably on some portable electronic media (e.g. CDROM, DVD, flash drive, etc.). The portable electronic media should contain descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information in lists should contain enough information to be easily understood by someone who has knowledge of light water reactor technology).
- 1. Provide a list of your license renewal commitments with the completion status of each. If a commitment is not complete, please provide an anticipated completion date.
- 2. For each complete commitment, please provide documentation demonstrating that the commitment has been completed.
- 3. For any commitment that has been changed, please provide documentation of the commitment change process, and any associated justification.
- 4. Provide a list of your Aging Management Programs (AMPs), copies of the program basis documents for each, and a listing of the action tracking items for each.
- 5. For AMPS that are one-time inspection programs, provide a list of completed work order numbers for inspections that have been completed. This may be incorporated with the previous item.
- 6. Provide a list of any newly identified structures, systems and components (SSCs) pursuant to 10 CFR 54.37(b) and RIS-2007-16.
1 Enclosure
REQUEST FOR INFORMATION POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL
- 7. Provide a copy of your updated final safety analysis report (UFSAR), or UFSAR update which includes descriptions of your AMPs.
- 8. Provide copies of any internal/external self-assessments and associated corrective action documents generated in preparation for the inspection.
II. Information requested to be available when the inspectors arrive on-site on June 28, 2010 and during the inspection.
- 1. Documentation demonstrating completion of license renewal commitments that are complete as of the inspection date. For example, this may be in the form of a binder for each commitment which includes the implementing documentation and references.
- 2. Copies of any corrective action documents generated as a result of the teams questions or queries during this inspection. (Provide daily during the inspection to the team lead and each team member).
- 3. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member).
If you have questions regarding the information requested, please contact the Dr. Sheldon. It may also help to review the IP 71003 frequently asked questions which are available at:
http://www.nrc.gov/reactors/operating/licensing/renewal/introduction/inspections/faq-ip71003.html 2 Enclosure
T. OConnor This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011.
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Jamie Benjamin, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-263 License No. DPR-22
Enclosure:
Request for Information, Post-Approval Site Inspection For License Renewal cc w/encl: Distribution via ListServ DISTRIBUTION:
Susan Bagley RidsNrrDorlLpl3-1 Resource RidsNrrPMMonticello RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource DOCUMENT NAME: G:\DRS\WIP\Ltr 03___10 Monticello License Renewal 71003b RFI SNS.doc 9 Publicly Available 9 Non-Publicly Available 9 Sensitive 9 Non-Sensitive To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy OFFICE RIII RIII NAME SSheldon:ls JBenjamin DATE 03/10/10 03/10/10 OFFICIAL RECORD COPY