UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 8, 2010 Mr. J. V. Parrish Chief Executive Officer Energy Northwest P.O. Box 968 (Mail Drop 1023)
Richland, WA 99352-0968
SUBJECT:
COLUMBIA GENERATING STATION - CLOSEOUT OF BULLETIN 2007-01 "SECURITY OFFICER ATTENTIVENESS" (TAC NO. MD7585)
Dear Mr. Parrish:
On December 12, 2007, the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2007 01, "Security Officer Attentiveness" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML073400150).
Energy Northwest (the licensee) provided a response, dated February 6,2008, (ADAMS Accession No. ML080510583) to Bulletin 2007-01. The NRC staff reviewed the licensee's response for Columbia Generating Station (CGS), and identified a need for additional information. The NRC staff issued a Request for Additional Information (RAJ) to the licensee on July 7,2008 (ADAMS Accession No. ML081820008). The licensee provided a response to the RAI on August 7,2008 (ADAMS Accession No. ML082320814), which included detailed descriptions of the administrative and managerial controls to deter and address inattentiveness and complicity among licensee security personnel at CGS. Due to the sensitivity of the subject matter, some responses may contain Security-Related Information and may not be publicly available.
The NRC staff has reviewed the submitted information and has concluded that your response to Bulletin 2007-01 and the subsequent RAI is adequate for CGS. The bases for the NRC's conclusion have been documented in a memorandum, "Security Bulletin 2007-01, Security Officer Attentiveness: Summary Report" (ADAMS Accession No. ML093440311). Based on this review,Bulletin 2007-01 is considered closed and no further action is required.
If you have any questions regarding this letter, please feel free to contact me at (301) 415-2296.
Y, J,eI 4!L fO~
I V
arl F. Lyon, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-397 cc: Distribution via Listserv
April 8,2010 Mr. J. V. Parrish Chief Executive Officer Energy Northwest P.O. Box 968 (Mail Drop 1023)
Richland, WA 99352-0968
SUBJECT:
COLUMBIA GENERATING STATION - CLOSEOUT OF BULLETIN 2007-01 "SECURITY OFFICER ATIENTIVENESS" (TAC NO. MD7585)
Dear Mr. Parrish:
On December 12,2007, the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2007 01, "Security Officer Attentiveness" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML073400150).
Energy Northwest (the licensee) provided a response, dated February 6,2008, (ADAMS Accession No. ML080510583), to Bulletin 2007-01. Once the licensee response was reviewed for Columbia Generating Station (CGS), the NRC staff identified a need for additional information. To gather that information, the NRC staff issued a Request for Additional Information (RAI) to the licensee on July 7,2008 (ADAMS Accession No. ML081820008). The licensee provided a response to the RAI on August 7,2008 (ADAMS Accession No. ML082320814), which included detailed descriptions of the administrative and managerial controls to deter and address inattentiveness and complicity among licensee security personnel at CGS. Due to the sensitivity of the subject matter, some responses may contain Security Related Information and may not be publicly available.
The NRC staff has reviewed the submitted information and has concluded that your response to Bulletin 2007-01 and the subsequent RAI is adequate for CGS. The bases for the NRC's conclusion have been documented in a memorandum, "Security Bulletin 2007-01, Security Officer Attentiveness: Summary Report" (ADAMS Accession No. ML093440311). Based on this review, your response to the Bulletin 2007-01 is considered closed and no further action is requested of you at this time.
If you have any questions regarding this letter, please feel free to contact me at (301) 415-2296.
Sincerely,
/raj (LWilkins for)
Carl F. Lyon, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-397 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPLIV Reading RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLpl4 Resource RidsOgcRp Resource RidsRgn4MailCenter Resource RidsNrrPMColumbia Resource RidsNrrLAJBurkhardt SStuchell, DPR/PGCB Accession No.: ML100621283 OFFICE LPL4/PM LPL1-2/LA LPL4/BC LPL4/PM NAME FLyon (LWilkins for)
ABaxter MMarkley FLyon (LWilkins for)