UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 February 25, 2010 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

REACTOR AND SENIOR REACTOR OPERATOR INITIAL EXAMINATION NORTH ANNA POWER STATION - 05000338/2010-301 AND 05000339/

2010-301

Dear Mr. Heacock:

In a telephone conversation February 24, 2010, between Mr. Walt Shura, Supervisor Nuclear Training and Mr. Edwin Lea, Senior Operations Engineer, arrangements were made for the administration of licensing examinations at North Anna Nuclear Station. The operating test is scheduled to be administered during the weeks of June 6 and June 21, 2010. The written examination is scheduled to be administered the week of June 14. The on-site preparatory week is scheduled for the week of May 17, 2010.

As agreed during the telephone conversation, your staff will prepare both the operating test and written examinations based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory Commission (NRC) regional office will discuss with your staff any changes that might be necessary before the examinations are administered. Your staff has also agreed to make copies of all examination materials that are necessary for administering the examination.

To meet the above schedule, it will be necessary for your staff to furnish the operating test outline by March 25, 2010. Mr. Lea provided the written examination outline to your staff in November 2009. The operating test, written examination, and the supporting reference materials identified in Attachment 3 to ES-201 will be due by April 21, 2010. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized representative of the facility licensee shall approve the outline, examination, and test before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use.

We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.

In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302,

VEPCO 2 your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final.

Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications, medical certifications, and waiver requests (if any) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary.

Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget. The public reporting burden for this collection of information is estimated to average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, writing the examinations, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room).

Thank you for your cooperation in this matter. Mr. Walt Shura, has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Edwin Lea at (404) 562-4567, (Internet E-mail: edwin.lea@nrc.gov), or me at (404) 562-4550, (Internet E-mail: malcolm

.widmann@nrc.gov).

Sincerely,

/RA/

Malcolm T. Widmann, Chief Operations Branch Division of Reactor Safety Docket Nos.:

License Nos.:

cc: (See Page 3)

_________________________ X SUNSI REVIEW COMPLETE MTW OFFICE RII:DRS RII:DRS SIGNATURE EXL /RA/ MTW /RA/

NAME ELea MWidmann DATE 02/25/2010 02/25/2010 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO VEPCO 3 cc w/encl: Christopher A. McClain Daniel G. Stoddard Manager Nuclear Training Site Vice President Virginia Electric and Power Company Virginia Electric and Power Company North Anna Power Station Electronic Mail Distribution P. O. Box 402 Mineral, VA 23117 Eric Hendrixson Director, Nuclear Safety and Licensing Virginia Electric and Power Company Electronic Mail Distribution Chris L. Funderburk Director, Nuclear Licensing & Operations Support Virginia Electric and Power Company Electronic Mail Distribution Lillian M. Cuoco, Esq.

Senior Counsel Dominion Resources Services, Inc.

Electronic Mail Distribution Executive Vice President Old Dominion Electric Cooperative Electronic Mail Distribution Ginger L. Alligood Virginia Electric and Power Company Electronic Mail Distribution Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219 Michael M. Cline Director Virginia Department of Emergency Services Management Electronic Mail Distribution County Administrator Louisa County P.O. Box 160 Louisa, VA 23093

VEPCO 4 Letter to David A. Heacock from Malcolm T. Widmann dated February 25, 2010

SUBJECT:

REACTOR AND SENIOR REACTOR OPERATOR INITIAL EXAMINATION NORTH ANNA POWER STATION - 05000338/2010-301 AND 05000339/

2010-301 Distribution w/encl:

C. Evans, RII L. Slack, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMNorthAnna Resource