Preparation and Scheduling of Operator Licensing Examinations - NRC Regulatory Issue Summary 2009-11
ML100480642
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 02/16/2010
From: Church C
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RIS-09-011
Download: ML100480642 (3)


Text

Tennessee Valley Authority, Post Office Box 2000, Soddy Daisy, Tennessee 37384-2000 February 16, 2010 U.S. Nuclear Regulatory Commission ATTN:

Document Control Desk Washington, D.C. 20555 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328

Subject:

Preparation and Scheduling of Operator Licensing Examinations -

NRC Regulatory Issue Summary 2009-11 This letter requests changes to the dates for scheduled examinations to those in the enclosed NRC Form 536, Operator Licensing Examination Data.

The exam date changes are requested because a corporate initiative has been implemented that revises our Initial License Training (ILT) program to improve station throughput performance.

The additional program requirements extend the ILT classes and impact the previously scheduled exam dates.

The requested date changes will allow us to implement these changes and improve our applicants' performance on license exams.

The revised dates were coordinated with Phillip Capehart of your staff.

Please direct any questions concerning this matter to Beth A. Wetzel at (423) 843-7170.

Respectfully, Christopher R. Church Site Vice President Sequoyah Nuclear Plant

Enclosure:

NRC Form 536 Operator Licensing Examination Data for Sequoyah Nuclear Plant cc (Enclosure):

Regional Administrator - Region

ENCLOSURE SEQUOYAH NUCLEAR PLANT NRC FORM 536 OPERATOR LICENSING EXAMINATION DATA

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION (10-2008)

OPERATOR LICENSING EXAMINATION DATA APPROVED BY OMB:

NO. 3150-0131 EXPIRES:

10/31/2011 Estimated burden per response to comply with this voluntary information collection request:

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This information collection is used to plan budgets and resources for operator examinations.

Send comments regarding burden estimate to the Records and FOIA/Privacy Services Branch (T-5 F53), U.S.

Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503.

If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY Sequoyah Nuclear Plant NRC REGION Region II A.

PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS CY 2010 1

0 CY 2012 1

0 CY 2012 1

0 CY 2013 1

0 B.

INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER NUMBER OF REACTOR OPERATORS NUMBER OF SENIOR REACTOR OPERATORS - INSTANT NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE ALTERNATE DATE CY 2010 3

14 0

0 09/07/2010 09/13/2010 CY2012 6

12 0

0 01/17/2012 01/23/2012 CY2012 10 8

0 0

11/26/2012 12/03/2012 CY2013 10 8

0 0

12/02/2013 12/09/2013 C.

PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE PROPOSED NUMBER ESTIMATED NUMBER OF CANDIDATES CY 2010 MARCH 0

JUNE 18 SEPTEMBER 0

DECEMBER 0

CY 2011 MARCH 0

JUNE 18 SEPTEMBER 0

DECEMBER 0

NRC FORM 536 (10-2008)