UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 JRnllary 25, 2010 LICENSEE:
Entergy Operations, Inc. (ENO)
FACILITIES: Palisades Nuclear Plant (PNP)
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON DECEMBER 17, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The licensee reported that significant schedule delays have occurred due to increase in the work scope and the availability of the resources. The NRC staff expressed concerns with the progress on this project and requested the licensee to conduct these conference calls on a monthly basis. The licensee has also changed the final completion date for the project from March 31, 2010, to August 20, 2010. provides the list of all attendees.
Background
On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.
Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosures:
1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Distribution via ListServ
12/16/2009 Palisades NFPA 805 Project Milestones NEI Task No.
Title Milestone Date' Status' Start Date' Task 1:
Transition of Nuclear Safety Performance Criteria lNEI 04-02 Table B*2) 02/03/10 See Comments Task 2:
Fundamental Fire Protection Program & Desig Elements lNEI 04-02 Table B*1) 03/03/10 See Comments Task 3:
Radioactive Release Transition (NEI 04-02 Table G-1) 01/25/10 See Comments Task 4:
Nuclear Safety Analysis Transition (NEI 04-02 Table B-3) 06/08/10 See Comments ST 4.1.1 Off-Site Power Cable Selection and Analysis 02/04/10 See Comments ST 4.1.2 Other Power Cable Selection and Analysis Complete ST 4.1.3 Subsequent Cablellnstrument Identification &
Analysis 03/05/10 See Comments Task 5:
Non-Power Operational Modes Transition NEI 04-02 Table F-ll 02/03/10 See Comments Task 6:
Internal Events PRA 05/17110 See Comments ST 6.2.1 Prepare LERF Model Complete ST 6.2.2 Update Flooding Analysis Complete ST6.3 Thermal Hydraulic Analysis for MSOIHRA 01125/10 See Comments ST6.4 Internal Events PRA Peer Review Complete Task 7:
Fire PRA 05/11/10 See Comments ST 7.6.4 R3 Internal Events Model Complete ST 7.7 Quantification Risk Screening Complete ST7.8 Scoping for Fire Modeling Complete ST 7.9/10 Circuit Failure Mode Likelihood Analysis Complete ST 7.12 Post Fire HRA 01/28/10 See Comments ST 7.13 Seismic Fire Interaction Assessment Complete ST 7.14 Fire Risk Quantification 03/22/10 See Comments 11/02/09 ST7.15 Uncertainty and Sensitivity Analysis 03/05/10 See Comments ST 7.17 Fire PRA Peer Review 01/22/10 Not Started 01/18/10 Task 8:
NFPA 805 Fire Risk 1Change Evaluations 04/28/10 See Comments ST 8.1 Fire Risk 1Change Evaluations 03/12/10 See Comments ST 8.2 Non-Compliance Risk Evaluations 04/28/10 See Comments 02/10/10 Task 9:
Palisades Mapping of Post Transition Procedures & Document Revisions 04/02/10 See Comments 01/11/1 0 Task 10:
Transition Report 07/14/10 See Comments Task 11:
License Amendment Request (LAR) 08/20/10 See Comments Notes:
1 The original milestone dates per schedule PLP 805 51-3 VV1FC Schedule 12NOVQB and are subject to change. The current schedule (805 59 1 U 07DEC09) dates were validated to be on or before these dates unless otherwise noted.
2 "On Track" means that the task current percentage completed is: the expected completion percent and the expected completion date for the task is projected to be met.
3 Start dates provided are estimates and may vary contingent upon predecessor completion and available resources at that time. Even if this start date is adjusted, the completion date is still expected to be met unless indicated otherwise.
Comments:
All uncompleted task dates have been extended as a result of the change to the 2nd pilot plant SER date. These dates may change es schedule validation and adjustment. and resource optimization. continue due to the schedule changes resulting from the 2nd pilot plant SER date change.
E:IPalisadeslPLPIEnforcement ExtensionlMilestone ItrslNRC Milestones 12-17-09.xls
TELEPHONE CONFERENCE CALL ON NFPA 805 TRANSITION PROGRESS BETWEEN U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC.
LIST OF PARTICIPANTS DECEMBER 17, 2009 PARTICIPANTS TITLE/POSITION AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC)
Mahesh Chawla Proiect Manaaer HEADQUARTERS Alex Klein Branch Chief Harrv Barrett Senior Fire Protection Enaineer Thomas Taylor Resident Inspector REGION ENTERGY Bob VanWagner Program Engineering Manager PALISADES NUCLEAR PLANT Tom Swiecicki Fire Protection Lead Roger Stobert Contract Project Manager NFPA 805 Chad Main Project Manager Jim Kuemin Licensing Engineer
ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.
IRA!
Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosures:
1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Distribution via Listserv Distribution:
PUBLIC LPL3-1 r/f RidsRgn3MailCenter Resource AKlein, NRR JGeissner, Rill RidsNrrDorLpl3-1 Resource RidsNrrPMANO Resource MVaaler, NRR TTaylor, Rill RidsNrrPMPalisades Resource RidsNrrLABTulIy Paul Lain, NRR HBarrett RidsAcrsAcnw_MailCtr Resource RidsOgcRp Resource JEliegood, Rill SBagley, EDO R-1I1 CTucci, NRR ADAMS Accession No' ML100110191 OFFICE LPL3-1/PM LPL3-1/LA DRAlAFPB/BC LPL3-1/BC NAME MChawla THarris AKlein RPascarelli DATE 01/14/10 01/14/10 01/1910 01/25/10