UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 January 5, 2010 Mr. Joseph Jensen Senior Vice President and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106
SUBJECT:
REQUALIFICATION PROGRAM INSPECTION
Dear Mr. Jensen:
In a telephone conversation on November 23, 2009, Mr. R. Ebright, Training Manager, and Mr. D. McNeil, Senior Operations Engineer, made arrangements for the NRC to inspect the licensed operator requalification program at the D. C. Cook Nuclear Power Plant. The inspection is planned for the week of January 25, 2010, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.
In accordance with 10 CFR 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations or annual operating tests as necessary to support the NRC's inspection program needs. In order for the NRC to adequately prepare for this inspection, please furnish the written examinations and operating tests scheduled for the week of the inspection to the NRC by January 18, 2010. Mr. Ebright has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018. The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. D. McNeil at 630-829-9737, or me at 630-829-9707.
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74 cc: Distribution via ListServ
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. D. McNeil at 630-829-9737, or me at 630-829-9707.
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74 cc:
Distribution via ListServ DISTRIBUTION:
Susan Bagley RidsNrrDorlLpl3-1 Resource RidsNrrPMDCCook Resource RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak James McHale DOCUMENT NAME: G:\\DRS\\Work in Progress\\DCC 010510 DRS OL Requal Program Inspection.doc To receive a copy of is document, indicate in the box: " " = Copy without attachment/enclo ure "E" = Copy with attachment/enclosure "N" = No copy th C
s OFFICE RIII RIII NAME DMcNeil:co HPeterson DATE 01/04/10 01/05/10 OFFICIAL RECORD COPY