January 20, 2010 Mr. David A. Heacock President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
MILLSTONE POWER STATION, UNIT NO. 1 - TWENTY FIVE DAY RESPONSE TO NRC ORDER IMPOSING INCREASED CONTROLS (EA 204) AND TO NRC ORDER IMPOSING FINGERPRINTING AND CRIMINAL HISTORY RECORDS CHECK REQUIREMENTS FOR UNESCORTED ACCESS TO CERTAIN RADIOACTIVE MATERIAL (EA-09-205)
Dear Mr. Heacock:
By letter dated December 17, 2009, you requested an extension of time to fully respond to EA-09-204 until February 15, 2010, and an extension of time to implement measures to comply with that Order. We have reviewed your request for an extension of time to fully respond to the Order and determined that your justification is reasonable. We are hereby granting your request for an extension of time to fully respond to that Order until February 15, 2010. Regarding your request for an extension of time to implement measures to comply with the Order, we believe that it is premature to extend the implementation period until you have determined how you will comply with the Order, therefore we are deferring a decision on that request until you have provided your full response and provided a specific date for compliance. We also note that by separate letter dated December 17, 2009, you replied to EA-09-205. Our review of that response will be addressed by separate correspondence.
Sincerely,
/RA/
Larry W. Camper, Director Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs Docket No. 50-245 cc: Millstone 1 Service List
Mr. David A. Heacock President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
MILLSTONE POWER STATION, UNIT NO. 1 - TWENTY FIVE DAY RESPONSE TO NRC ORDER IMPOSING INCREASED CONTROLS (EA 204) AND TO NRC ORDER IMPOSING FINGERPRINTING AND CRIMINAL HISTORY RECORDS CHECK REQUIREMENTS FOR UNESCORTED ACCESS TO CERTAIN RADIOACTIVE MATERIAL (EA-09-205)
Dear Mr. Heacock:
By letter dated December 17, 2009, you requested an extension of time to fully respond to EA-09-204 until February 15, 2010, and an extension of time to implement measures to comply with that Order. We have reviewed your request for an extension of time to fully respond to the Order and determined that your justification is reasonable. We are hereby granting your request for an extension of time to fully respond to that Order until February 15, 2010. Regarding your request for an extension of time to implement measures to comply with the Order, we believe that it is premature to extend the implementation period until you have determined how you will comply with the Order, therefore we are deferring a decision on that request until you have provided your full response and provided a specific date for compliance. We also note that by separate letter dated December 17, 2009, you replied to EA-09-205. Our review of that response will be addressed by separate correspondence.
Sincerely, Larry W. Camper, Director Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs Docket No. 50-245 cc: Millstone 1 Service List ML100070559 Office DWMEP:PM DWMEP:LA DWMEP:BC DWMEP:DD DWMEP Name JHickman CHolston APersinko KMcConnell LCamper Date 01 /10 01/ 7 /10 01/14/10 01/14/10 01/20/10 Official Record Copy
Millstone Power Station Unit 1 - John Hickman, Project Manager cc:
Mr. A. J. Jordan Site Vice President - Millstone Dominion Nuclear Connecticut, Inc.
Rope Ferry Road Waterford, CT 06385 Mr. P. J. Parulis Manager - Nuclear Oversight Dominion Nuclear Connecticut, Inc.
Rope Ferry Road Waterford, CT 06385 Mr. S. E. Scace Assistant to the Site Vice President Dominion Nuclear Connecticut, Inc.
Rope Ferry Road Waterford, CT 06385 Mr. Robert T. Griffin, Director Nuclear Safety and Licensing Dominion Nuclear Connecticut, Inc.
Rope Ferry Road Waterford, CT 06385 Mr. S. P. Sarver, Director Nuclear Station Operations & Maintenance Dominion Nuclear Connecticut, Inc.
Rope Ferry Road Waterford, CT 06385 Mr. Chris L. Funderburk Director, Nuclear Licensing and Operations Support Dominion Resources Services, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. William D. Bartron Licensing Supervisor Dominion Nuclear Connecticut, Inc.
Rope Ferry Road Waterford, Connecticut 06385 Lillian M. Cuoco, Esquire Senior Counsel Dominion Resources Services, Inc.
Rope Ferry Road Waterford, CT 06385 Edward L. Wilds, Jr., Ph.D.
Director, Division of Radiation Department of Environmental Protection 79 Elm Street Hartford, CT 06106-5127 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 First Selectmen Town of Waterford 15 Rope Ferry Road Waterford, CT 06385 Mr. Evan W. Woollacott, Co-Chair Nuclear Energy Advisory Council 128 Terry's Plain Road Simsbury, CT 06070 Nancy Burton, Esquire 147 Cross Highway Redding Ridge, CT 06876 Senior Resident Inspector Millstone Power Station c/o Nuclear Regulatory Commission P.O. Box 513 Niantic, CT 06357 Mr. David A. Christian President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 13060-6711