December 22, 2009 Mr. William L. Berg President and CEO Dairyland Power Cooperative 3200 East Avenue S.
P.O. Box 817 La Crosse, WI 54602-0817
SUBJECT:
LA CROSSE BOILING WATER REACTOR MASTER INSPECTION PLAN -
FISCAL YEAR 2010
Dear Mr. Berg:
In accordance with the U.S. Nuclear Regulatory Commission Inspection Manual Chapter 2561 Decommissioning Power Reactor Inspection Program, the NRC Region III staff and management have developed a Master Inspection Plan (MIP) for the La Crosse Boiling Water Reactor (LACBWR). The plan is based on your current performance and schedule of significant decommissioning activities planned for the site for fiscal year (FY) 2010, which is from October 2009 through September 2010. The plan outlines how we intend to focus our Regional inspection resources to address significant ongoing decommissioning activities.
Because the FY 2010 MIP is based, in part, on your proposed schedule of significant decommissioning activities for FY 2010, the plan and the focus of NRC inspection activities may change to reflect a change in your planned decommissioning activities or your performance. In order to ensure that the FY 2010 MIP remains current, we request that you keep the Materials Control, Independent Spent Fuel Storage Installation (ISFSI), and Decommissioning Branch staff informed of any significant changes in your proposed schedule of decommissioning activities. You will be informed of any significant changes to the LACBWR FY 2010 MIP.
We currently project the Region will conduct an inspection at LACBWR during FY 2010 to evaluate spent fuel pool safety and related routine decommissioning activities. Additional inspections will be scheduled as necessary regarding the construction of a large tank in the reactor cavity that will hold the dry fuel storage casks for off-loading the fuel. The Region will also conduct approximately three onsite inspections to evaluate the design and construction of the ISFSI pad, in addition to in-office review. Following is a list of the inspection procedures we expect to use during our inspections. The specific procedures used during each inspection will depend on the specific decommissioning activities being conducted. Additional inspection procedures may be used or inspections conducted if decommissioning activities warrant.
Security-related inspection activities will be addressed in a separate MIP.
W. Berg Inspection Procedure Title IP 36801 Organization, Management and Cost Controls IP 37801 Safety Reviews, Design Changes, and Modifications IP 40801 Self-Assessment, Auditing, and Corrective Action IP 60801 Spent Fuel Pool Safety IP 62801 Maintenance and Surveillance IP 60856 Review of 72.212(b) Evaluations IP 60853 Onsite Fabrication of Components and Construction of an Independent Spent Fuel Storage Installation IP 71801 Decommissioning Performance and Status Review IP 83750 Occupational Radiation Exposure IP 84750 Radioactive Waste Treatment, and Effluent and Environmental Monitoring IP 86750 Solid Radioactive Waste Management and Transportation of Radioactive Materials In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.
We will gladly discuss any questions you may have regarding these inspection plans. If you have questions, please contact William Snell of my staff at (630) 829-9871.
Sincerely,
/RA/
Christine A. Lipa, Chief Materials Control, ISFSI, and Decommissioning Branch Docket No. 50-409 License No. DPR-45 cc :
Michael A. Brasel, Plant Manager B. D. Burks, P.E., Director, Bureau of Field Operations Spark Burmaster, Coulee Region Energy Coalition State Liaison Officer Chief, Radiation Protection Section, WI Department of Health Social Services, Division of Health
W. Berg Inspection Procedure Title IP 36801 Organization, Management and Cost Controls IP 37801 Safety Reviews, Design Changes, and Modifications IP 40801 Self-Assessment, Auditing, and Corrective Action IP 60801 Spent Fuel Pool Safety IP 62801 Maintenance and Surveillance IP 60856 Review of 72.212(b) Evaluations IP 60853 Onsite Fabrication of Components and Construction of an Independent Spent Fuel Storage Installation IP 71801 Decommissioning Performance and Status Review IP 83750 Occupational Radiation Exposure IP 84750 Radioactive Waste Treatment, and Effluent and Environmental Monitoring IP 86750 Solid Radioactive Waste Management and Transportation of Radioactive Materials In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.
We will gladly discuss any questions you may have regarding these inspection plans. If you have questions, please contact William Snell of my staff at (630) 829-9871.
Sincerely,
/RA/
Christine A. Lipa, Chief Materials Control, ISFSI, and Decommissioning Branch Docket No. 50-409 License No. DPR-45 cc :
Michael A. Brasel, Plant Manager B. D. Burks, P.E., Director, Bureau of Field Operations Spark Burmaster, Coulee Region Energy Coalition State Liaison Officer Chief, Radiation Protection Section, WI Department of Health Social Services, Division of Health DISTRIBUTION:
See next page
- See previous concurrence DOCUMENT NAME: MIP LaCrosse Boiling Water Reactor (LACBWR) FY2010.doc X Publicly Available Non-Publicly Available Sensitive X Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII E
RIII E
RIII E
RIII E
NAME WGSnell:jc*
PJLee*
JETapp; CL for CALipa DATE 12/17/09 12/17/09 12/22/09 12/22/09 OFFICIAL RECORD COPY
Letter to W. L. Berg from Christine Lipa dated December 22, 2009
SUBJECT:
LA CROSSE BOILING WATER REACTOR (LACBWR) MASTER INSPECTION PLAN - FISCAL YEAR (FY) 2010 DISTRIBUTION:
D. Persinko, FSME K. Banovac, FSME N. Orlando, FSME C. Pederson, RIII S. Reynolds, RIII P. Louden, RIII A. Barker, RIII V. Mitlyng, RIII P. Chandrathil, RIII