ML093521655

From kanterella
Jump to navigation Jump to search
IR 05000321-09-009, 05000366-09-009, on 11/16-18/2009; Edwin I. Hatch Nuclear Plant, Units 1 and 2; Supplemental Inspection IP 95001 in Response to a White Inspection Finding for Failure to Promptly Identify and Correct a Condition Adverse
ML093521655
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 12/18/2009
From: Wert L
Division Reactor Projects II
To: Madison D
Southern Nuclear Operating Co
References
IR-09-009
Download: ML093521655 (14)


See also: IR 05000321/2009009

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

SAM NUNN ATLANTA FEDERAL CENTER

61 FORSYTH STREET, SW, SUITE 23T85

ATLANTA, GEORGIA 30303-8931

December 18, 2009

Mr. Dennis R. Madison

Vice President

Southern Nuclear Operating Company, Inc.

Edwin I. Hatch Nuclear Plant

11028 Hatch Parkway North

Baxley, GA 31513

SUBJECT: EDWIN I. HATCH NUCLEAR PLANT - NRC SUPPLEMENTAL INSPECTION

REPORT 05000321/2009009, 05000366/2009009

Dear Mr. Madison:

On November 18, 2009, the U.S. Nuclear Regulatory Commission (NRC) staff completed a

supplemental inspection pursuant to Inspection Procedure 95001, (Inspection for One or Two

White Inputs in a Strategic Performance Area), at your Edwin I. Hatch Nuclear Plant, Units 1

and 2. The purpose of the inspection was to examine the causes and actions taken related to a

White inspection finding issued in the first quarter of 2009 for failure to promptly identify and

correct a condition adverse to quality. This finding resulted in a Violation (VIO) 05000321,

366/2008009-01, 1B EDG Coupling Failure. The enclosed inspection report documents the

inspection results, which were discussed at the exit meeting on November 18, 2009, with you

and other members of your staff.

The objectives of this supplemental inspection were to provide assurance that: (1) the root

causes and the contributing causes for the risk-significant issues were understood; (2) the

extent of condition and extent of cause of the issues were identified; and (3) corrective actions

were or will be sufficient to address and preclude repetition of the root and contributing causes.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed the root cause determination report, selected procedures and records,

and interviewed personnel.

Based on the results of this supplemental inspection, no findings of significance were identified.

The inspector determined that, in general, the problem identification, root cause, and corrective

actions taken by your staff were adequate. However, the inspector noted several areas in the

root cause determination report that could have been improved. In addition, weaknesses were

identified in the recently revised maintenance procedure used to inspect the engine/generator

coupling.

SNC 2

In accordance with the Code of Federal Regulations 10 CFR 2.390 of the NRCs Rules of

Practice, a copy of this letter, its enclosure, and your response (if any) will be available

electronically for public inspection in the NRC Public Document Room or from the Publicly

Available Records (PARS) component of the NRCs document system (ADAMS). ADAMS is

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/Joel Munday RA for/

Leonard D. Wert, Jr., Director

Division of Reactor Projects

Docket Nos.: 50-321, 50-366

License Nos.: DPR-57, NPF-5

Enclosure: Inspection Report 05000321/2009009, 05000366/2009009

w/Attachment: Supplemental Information

cc w/encl: (See page 3)

_________________________ X SUNSI REVIEW COMPLETE

OFFICE RII:DRP RII:DRP RII:DRP

SIGNATURE TXL /RA for/ SMS /RA/ Via email

NAME SRose SShaeffer TChandler

DATE 12/16/2009 12/15/2009 12/15/2009

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

SNC 3

cc w/encl: Arthur H. Domby, Esq.

Angela Thornhill Troutman Sanders

Managing Attorney and Compliance Officer Electronic Mail Distribution

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Dr. Carol Couch

Director

Jeffrey T. Gasser Environmental Protection

Executive Vice President Department of Natural Resources

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution

Electronic Mail Distribution

Cynthia Sanders

Raymond D. Baker Program Manager

Licensing Manager Radioactive Materials Program

Licensing - Hatch Department of Natural Resources

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution

Electronic Mail Distribution

Jim Sommerville

L. Mike Stinson (Acting) Chief

Vice President Environmental Protection Division

Fleet Operations Support Department of Natural Resources

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution

Electronic Mail Distribution

Mr. Steven M. Jackson

Paula Marino Senior Engineer - Power Supply

Vice President Municipal Electric Authority of Georgia

Engineering Electronic Mail Distribution

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Mr. Reece McAlister

Executive Secretary

Moanica Caston Georgia Public Service Commission

Vice President and General Counsel Electronic Mail Distribution

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Chairman

Appling County Commissioners

Steven B. Tipps County Courthouse

Hatch Principal Engineer - Licensing 69 Tippins Street, Suite 201

Edwin I. Hatch Nuclear Plant Baxley, GA 31513

Electronic Mail Distribution

Mr. Ken Rosanski

Resident Manager

Edwin I. Hatch

Oglethorpe Power Corporation

Electronic Mail Distribution

Lee Foley

Manager of Contracts Generation

Oglethorpe Power Corporation

Electronic Mail Distribution

SNC 4

Letter to Dennis R. Madison from Leonard D. Wert dated December 18, 2009

SUBJECT: EDWIN I. HATCH NUCLEAR PLANT - NRC SUPPLEMENTAL INSPECTION

REPORT 05000321/2009009, 05000366/2009009

Distribution w/encl:

C. Evans, RII

L. Slack, RII

OE Mail

RIDSNRRDIRS

PUBLIC

RidsNrrPMHatch Resource

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket No.: 50-321, 50-366

License No.: DPR-57 and NPF-5

Report No.: 05000321/2009009, 05000366/2009009

Licensee: Southern Nuclear Operating Company Inc.

Facility : Edwin I. Hatch Nuclear Plant

Location: Baxley, Georgia 31513

Dates: November 16, 2009 - November 18, 2009

Inspector: T. Chandler, Resident Inspector, Region II

Approved by: Scott M. Shaeffer, Chief

Reactor Projects Branch 2

Division of Reactor Projects

Enclosure

SUMMARY OF FINDINGS

IR 05000321/2009009, 05000366/2009009; 11/16/2009 - 11/18/2009; Edwin I. Hatch Nuclear

Plant, Units 1 and 2; Supplemental Inspection IP 95001 in response to a White inspection

finding for failure to promptly identify and correct a condition adverse to quality.

This inspection was conducted by a resident inspector. No findings of significance were

identified. The NRCs program for overseeing the safe operation of commercial nuclear power

reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated

December 2006.

Cornerstone: Mitigating Systems

The NRC staff performed this supplemental inspection in accordance with Inspection Procedure 95001, Inspection for One or Two White Inputs in a Strategic Performance Area, to assess the

licensees evaluation associated with the inoperability of the 1B emergency diesel generator in

June 2008. The NRC staff previously characterized this issue as having low to moderate safety

significance (White) as documented in NRC IR 05000321/2008009, 05000366/2008009. During

this supplemental inspection, the inspector determined that the licensee performed a

comprehensive evaluation of the self-revealing EDG failure, which occurred during a routine

technical specification surveillance requirement test. The licensee identified the primary root

causes of the issue to be (1) less-than-adequate EDG coupling inspection procedures and (2)

less-than-adequate risk perception for degrading components. These two primary root causes,

along with six other root causes and three contributing causes, led the maintenance and

engineering personnel to believe that cracking and separation in the engine-generator coupling

gland was acceptable. The NRC inspector also determined that the licensees extent of

condition and extent of cause evaluations were adequate, and that the corrective actions were

comprehensive and properly prioritized, and sufficient to prevent recurrence of the event.

The inspector did note several areas in the root cause determination report that could have

been more timely. Specifically, because the readiness assessment was not conducted until just

a few weeks before the 95001 inspection was scheduled to begin; time available to incorporate

needed improvements into the final root cause determination reviewed by the inspector was

limited. Also, the MORT analysis was not fully utilized to evaluate the role of supervision in the

event. In addition, weaknesses were identified in the revised maintenance procedure used to

inspect the engine/generator coupling. For example, no specific criteria was provided on how to

determine when inspection of the engine side of the coupling would be needed.

Given the licensees acceptable performance in addressing the inoperable EDG, the White

finding associated with this issue will only be considered in assessing plant performance for a

total of four quarters in accordance with the guidance in IMC 0305, Operating Reactor

Assessment Program. The implementation and effectiveness of the licensees corrective

actions will be reviewed during future inspections.

A. NRC-Identified and Self-Revealing Findings

No findings of significance were identified.

B. Licensee-Identified Violations

No findings of significance were identified.

Enclosure

REPORT DETAILS

4. OTHER ACTIVITIES

4OA4 Supplemental Inspection (95001)

.01 Inspection Scope

The NRC staff performed this supplemental inspection in accordance with IP 95001 to

assess the licensees evaluation of a White finding, which affected the mitigating

systems cornerstone in the reactor safety strategic performance area. The inspection

objectives were to:

  • Verify that the licensee understands the root causes and contributing causes of the 1B

EDG failure.

  • Verify that the licensee has determined the extent of condition and extent of cause of

the identified root and contributing causes.

  • Verify that the corrective actions for these issues are sufficient to address the root and

contributing causes and to prevent recurrence.

  • Verify that the procedures have been revised to perform visual inspections of both

sides of the coupling (generator/motor).

The licensee entered the Regulatory Response Column of the NRCs Action Matrix in

the first quarter of 2008 as a result of one inspection finding of low to moderate safety

(White) significance. The finding was associated with the inoperability of the 1B EDG in

July 2008. On July 12, 2008, the 1B EDG was manually shutdown due to excessive

vibration and declared inoperable. The finding was characterized as having White safety

significance based on the results of a Phase 3 risk analysis performed by a region-based

senior reactor analyst (SRA), as discussed in NRC IR 05000321/2008009,

05000366/2008009. The excessive vibration was attributed to age-related cracks in the

rubber gland on both the diesel engine side and generator side of the generator/motor

coupling. On July 16, 2008, the generator/motor coupling was replaced and the 1B EDG

was returned to service.

The licensee had performed its initial root cause determination (CR 2008107432 RCCA

version 1.0, dated 09/04/08) to identify weaknesses that existed in various organizations,

which allowed for a risk-significant finding and to determine the organizational attributes

that resulted in the White finding. As part of the root cause determination, the licensee

also completed a safety culture assessment. The licensee staff informed the NRC staff

on September 23, 2009, that they were ready for the supplemental inspection. In

October 2009, in preparation for the 95001 inspection, the licensee conducted an in-

depth readiness assessment of the original root cause determination report. As a result

of that self-critical readiness assessment, the licensee made numerous significant

improvements to the original report. As a result, the revised root cause determination

Enclosure

4

report (CR 2008107432 RCCA version 2.0, dated 11/12/09) was issued just prior to the

inspection.

The inspector reviewed the licensees root cause determination report, along with

several evaluations that were conducted in support of the root cause determination. The

inspector reviewed the licensees extent of condition and extent of cause evaluations to

ensure they were sufficient in breadth. The inspector reviewed the corrective actions

that were taken or planned to address the identified causes. The inspector also held

discussions with licensee personnel to ensure that the root and contributing causes, as

well as the contribution of safety culture components, were understood and that

corrective actions taken or planned were appropriate to address the causes and

preclude repetition.

.02 Evaluation of the Inspection Requirements

02.01 Problem Identification

a. IP 95001 requires that the inspection staff determine that the licensees evaluation of the

issue documents who identified the issue (i.e., licensee-identified, self-revealing, or

NRC-identified) and the conditions under which the issue was identified.

The self-revealing issue occurred during a Technical Specification surveillance

requirement. The initial indications of the issue were high engine vibrations

approximately four hours into the 24-hour test run of the 1B EDG.

b. IP 95001 requires that the inspection staff determine that the licensees evaluation of the

issue documents how long the issue existed and prior opportunities for identification.

The licensees RCCA documented that the cracks in the coupling gland were first

identified back in 1988. However, it was determined at that time that the cracks did not

impact EDG operability due to the coupling gland passing a vendor recommended air

test and the EDGs ability to pass the Technical Specification surveillance requirement.

c. IP 95001 requires that the inspection staff determine that the licensees evaluation of the

issue documents the plant-specific risk consequence, as applicable, and compliance

concerns associated with the issue.

The NRC determined this issue was a White finding, as documented in NRC IR 05000321/2009008 and 05000366/2009008. The inspector determined that the licensee

conducted a plant specific risk consequence analysis and provided its results in the final

root cause determination report. Using the Hatch PRA model with a 93 day exposure

time yields a probable core damage frequency (CDF) of 9.16 E-7. The large early

release frequency (LERF) is 3.89 E-9 and is considered negligible. Due to the small

amount of risk increase (less than 1.0 E-6) the licensee determined this to be a Green

finding. It is also noted that Plant Hatch requires only one EDG per unit for performance

of LOSP functions.

Enclosure

5

d. Findings

No findings of significance were identified.

02.02 Root Cause and Extent-of-Condition Evaluation

a. IP 95001 requires that the inspection staff determine that the licensee evaluated the

issue using a systematic methodology to identify the root and contributing causes.

The licensee used the following systematic methods to complete their RCCA:

  • Fault tree analysis
  • Barrier analysis
  • Event and causal factors chart
  • Event timeline

The inspector determined that the licensee evaluated the issue using a systematic

methodology to identify the root and contributing causes.

b. IP 95001 requires that the inspection staff determine that the licensees RCCA was

conducted to a level of detail commensurate with the significance of the problem.

The licensees RCCA included an extensive timeline of events, as well as an event and

causal factors chart as discussed in the previous section. Using a multidisciplinary

team, the licensee identified eight root causes and three contributing causes. Based on

the extensive work performed for this root cause evaluation, the inspector concluded that

the root cause evaluation was conducted to a level of detail commensurate with the

significance of the problem.

c. IP 95001 requires that the inspection staff determine that the licensees RCCA include a

consideration of prior occurrences of the problem and knowledge of prior operating

experience.

The licensees RCCA included a review of both internal and external OE. A search of

the Plant Hatch condition report data base for previous reports of the same or similar

problems found no reports of previous problems with the EDG couplings. However, the

event and causal factors chart reviewed the history of the event and looked for previous

opportunities to correct the problem. As a result of this review, the licensee identified

that their use of vendor information was poor, and as a result, several of the root causes

are tied to inadequate dissemination of vendor information. Based on the licensees

detailed evaluation and conclusions, the inspector determined that the licensees RCCA

considered prior occurrences and operating experience.

d. IP 95001 requires that the inspection staff determine that the licensees RCCA

addresses the extent of condition and the extent of cause of the issue.

Enclosure

6

To address the extent of condition issue, the licensees RCCA contained a review of

several components that contain similar elastomer-coupled elements and the preventive

maintenance items associated with them. As a result of this review, the couplings were

replaced on the other four EDGs at Plant Hatch, and the inspection and replacement

requirements on several other major components that contain similar elastomer-coupled

elements were greatly improved. Also, a review of the actions taken in relationship to

the causes was documented in the RCCA to provide assurance that the actions were

sufficiently broad to address the extent of causes. The inspector determined that the

licensees RCCA addressed the extent of condition and the extent of cause of the issue.

e. IP 95001 requires that the inspection staff determine that the licensees root cause

evaluation, extent of condition, and extent of cause appropriately considered the safety

culture components as described in IMC 0305.

As part of the RCCA, the licensee performed a Safety Culture Assessment. This

assessment identified three areas needing improvement: Decision Making, Corrective

Action Program, and Operating Experience. In addition, a MORT analysis was

performed to provide additional focus on why condition reports were not initiated. Based

upon the corrective actions listed in the Safety Culture Assessment, the inspector

determined that the licensees root cause evaluation, extent of condition, and extent of

cause appropriately considered the safety culture components as described in IMC 0305.

f. Findings

No findings of significance were identified. However, the inspector did note several

areas in the root cause determination report that could have been more timely.

Specifically, because the readiness assessment was not conducted until just a few

weeks before the 95001 inspection was scheduled to begin; time available to incorporate

needed improvements into the final root cause determination reviewed by the inspector

was limited. Also, the MORT analysis was not fully utilized to evaluate the role of

supervision in the event.

02.03 Corrective Actions

a. IP 95001 requires that the inspection staff determine that: (1) the licensee specified

appropriate corrective action(s) for each root and/or contributing cause; or (2) an

evaluation that states no actions are necessary is adequate.

The licensee took immediate corrective actions to restore operability of the 1B EDG by

replacing the cracked coupling. All root and contributing causes listed in the RCCA were

linked to an appropriate corrective action. The inspector determined that the proposed

corrective actions are appropriate and addressed each root and contributing cause.

b. IP 95001 requires that the inspection staff determine that the licensee prioritized

corrective actions with consideration of risk significance and regulatory compliance.

Enclosure

7

The licensees immediate corrective actions restored the 1B EDG to operable status

within 86 hours9.953704e-4 days <br />0.0239 hours <br />1.421958e-4 weeks <br />3.2723e-5 months <br />. While the 1B EDG was inoperable, the licensee performed monthly TS

surveillance procedures to verify operability of the 1A, 1C, 2A, and 2B EDGs. Over the

next few weeks, the licensee conservatively replaced the couplings in the 1A, 1C, 2A,

and 2B EDGs, greatly reducing the risk of an additional coupling failure. Based upon

these corrective actions, as well as the other corrective actions identified in the RCCA,

the inspector determined that the licensee prioritized corrective actions with

consideration of risk significance and regulatory compliance.

c. IP 95001 requires that the inspection staff determine that the licensee established a

schedule for implementing and completing the corrective actions.

The inspector determined that all of the corrective actions listed in the RCCA have been

either scheduled or completed.

d. IP 95001 requires that the inspection staff determine that the licensee developed

quantitative and qualitative measures of success for determining the effectiveness of the

corrective actions to preclude repetition.

The inspector determined that an interim effectiveness review for the corrective actions

listed in the RCCA is scheduled for December 2009 (ref. AI 2009203209) Because the

RCCA was revised on November 12, 2009, the final effectiveness review will be delayed

until June 2010 to allow additional time to completed newly added corrective actions.

The inspector determined that the licensee has developed quantitative and qualitative

measures of success for determining the effectiveness of the corrective actions to

preclude repetition of this event.

e. IP 95001 requires that the inspection staff determine that the licensees planned or taken

corrective actions adequately address a Notice of Violation (NOV) that was the basis for

the supplemental inspection, if applicable.

The NRC issued an NOV to the licensee on June 4, 2009. The licensee provided the

NRC a written response to the NOV on July 2, 2009. The licensees response

described: (1) corrective steps which have been taken and the results achieved; (2)

corrective steps which will be taken; (3) the date when full compliance will be achieved;

and (4) the reasons for the violation. During this inspection, the inspector confirmed that

the licensees RCCA and planned and taken corrective actions addressed the NOV.

The licensee restored the 1B EDG to full compliance on July 16, 2008.

f. Findings

No findings of significance were identified. Inspectors did note weaknesses in the

revised maintenance procedure used to inspect the engine/generator coupling. For

example, no specific criteria was provided on how to determine when inspection of the

engine side of the coupling would be needed. Based on observations provided by the

inspector the licensee initiated actions to add criteria to address this issue.

Enclosure

8

4OA6 Exit Meeting

On November 18, 2009, the inspector presented the results of the supplemental

inspection to Mr. Dennis R. Madison and other members of licensee management and

staff, who acknowledged the findings. The inspector confirmed that no proprietary

information was provided or examined during the inspection.

ATTACHMENT: SUPPLEMENTAL INFORMATION

Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

G. Johnson - Engineering Director

D. Madison - Site Vice President

L. Mikulecky - Root Cause Analyst

S. Tipps - Principle Licensing Engineer

NRC personnel:

E. Morris, Senior Resident Inspector - Hatch

P. Niebaum, Resident Inspector - Hatch

S. Shaeffer, Chief, Reactor Projects Branch 2

ITEMS OPENED, CLOSED AND DISCUSSED

None

LIST OF DOCUMENTS REVIEWED

Action Items

2001202296 2008203824 2004202167 2008203692 2008204097 2008204098

2008204099 2009204100 2008204101 2008204102 2008204103 2008204104

2008204105 2008204106 2008204107 2008204108 2008204109 2008204110

2008204111 2008204112 2008204113 2008204114 2008204115 2008203209

2008204651 2008205554

Procedures

52SV-R43-001, Diesel, Alternator, and accessories inspection, various revisions

Maintenance Work Orders

10100390, Replace inboard and outboard alternator bearings on 1B EDG

28603340, 2C EDG bearing seizure

28603681, Inspect 2C EDG inboard bearing

Condition Reports

1996001491 1998002701 2001004250 2000011063 2001000624 2004104711

1996001491 2007108168 2008107432

Miscellaneous

Fermi Event Card 02-14329

Sure-Flex Elastomeric Couplings Manual

Test Report 08-0372-TR-001, Altran Technical Report on Hatch EDG Coupling Assessments

Vendor document SX28733

Vendor document SX13147

Attachment