UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 30, 2009 LICENSEE: Entergy Operations, Inc. (ENO)

FACILITIES: Palisades Nuclear Plant (PNP)

SUB~IECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 14, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (I\lFPA) STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The licensee reported that there has been significant increase in the work scope. As a result, the milestone date for completion of some of the tasks is shown to be later than the final license amendment request date of March 31, 2010. The licensee obtained additional resources for the project but has not completed development of a schedule. Enclosure 2 provides the list of all attendees.

Background

On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.

~j /)

L1'~~ &t 1114--

Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255 Enclosures.

1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Distribution via ListServ

10/14/2009 Palisades NFPA 805 Project Milestones NEI Task Milestone Start Title Status' ,

No. Date' Date Transition of Nuclear Safety Performance See Task 1:

Criteria (NEI 04-02 Table B-2) 11/25/09 -

Comments Fundamental Fire Protection Program & Desig See Task 2: 12/22/09 -

Elements (NEI 04-02 Table B-1) Comments Radioactive Release Transition (NEI 04-02 See Task 3: 12/22/09 -

Table G-1) Comments Nuclear Safety Analysis Transition (NEI 04-02 See Task 4:

Table B-3) 03/29/10 Comments See ST4.1.1 Off-Site Power Cable Selection and Analysis 11/05/09 -

Comments ST 4.1.2 Other Power Cable Selection and Analysis - Complete -

Subsequent Cablellnstrument Identification & See ST4.1.3 11/13/09 -

Analysis Comments Non-Power Operational Modes Transition See Task 5: 11/19/09 -

NEI 04-02 Table F-1) Comments See Task 6: Internal Events PRA 06/03/10 -

Comments ST 6.2.1 Prepare LERF Model - Complete -

See ST 6.2.2 Update Flooding Analysis 11/03/09 -

Comments See ST 6.3 Thermal Hydraulic Analysis for MSOIHRA 12108/09 Comments ST 6.4 Internal Events PRA Peer Review 10/30109 Not Started 10/26/09 See Task 7: Fire PRA 02/01/10 -

Comments ST 7.6.4 R3 Internal Events Model - Complete -

See ST 7.7 Quantification Risk Screening 01/21/10 -

Comments ST 7.8 Scoping for Fire Modeling - Complete -

See ST 7.9/10 Circuit Failure Mode Likelihood Analysis 11120109 -

Comments See ST 7.12 Post Fire HRA 12/07/09 -

Comments ST 7.13 Seismic Fire Interaction Assessment - Complete -

See ST 7.14 Fire Risk Quantification 02/24/10 02/24/10 Comments See ST 7.15 Uncertainty and Sensitivity Analysis 02/25/10 -

Comments ST 7.17 Fire PRA Peer Review 01/22/10 Not Started 01/18/10 See Task 8: NFPA 805 Change Evaluations 04/22/10 -

Comments See ST 8.1 Change Evaluations 03/30/10 Comments See ST 8.2 Non-Compliance Risk Evaluations 04/22/10 02/10/10 Comments Palisades Mapping of Post Transition See Task 9: 01/26/10 11/16/09 Procedures & Document Revisions Comments See Task 10: Transition Report 05/12/10 09/07/09 Comments Task 11: License Amendment Request (LAR) 03/31/10 - -

Notes:

1 The original milestone dates per schedule PLP B05 S1~3 WIFe Schedule 12NOVOB and are subject to change. The current schedule (B05 S8 OJ 050CT09) dates were ...alidated to be on or before these dates unless otherwise noted.

2 "On Track" means that the task current percentage completed i2: the expected completion percent and the expected completion date for the task is projected to be mel.

3 Start dates provided are estimates and may \lary contingent upon predecessor completion and available resources at that time. Even if this start date is adjusted, the completion date is still expected to be met unless indicated otherwise Comments:

All uncompleted task dates have slipped except the IE PRA Peer Review 1ST 6.4J. Fire PRA Peer Review [ST 7.17]. and the LERF model 1ST 6.2.1] which was completed.

The Task 11. LAR submittal date is prior to the IE PRA completion [T 6J, Change Evaluations [T 8). and the Transition report completion [T 10] due to the self-imposed contraint for the LAR submittal of the end of the 1st quarter 2010.

E:\Palisades\PLP\Enforcement Extension\Milestone Itrs\NRC Milestones 10-14-09.xls Enclosure 1

TELEPHONE CONFERENCE CALL ON NFPA 805 TRANSITION PROGRESS BETWEEN U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC.

LIST OF PARTICIPANTS OCTOBER 14, 2009 PARTICIPANTS TITLE/POSITION AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC)

Mahesh Chawla Proiect Manaaer HEADQUARTERS Alex Klein Branch Chief Harrv Barrett Senior Fire Protection Enaineer John Ellegood Senior Resident Inspector REGION ENTERGY Bob VanWagner Program Engineering Manager PALISADES NUCLEAR PLANT Ron Penna Program Engineering Supervisor Tom Swiecicki Fire Protection Lead Brian Brogan Probabilistic Safety Assessment (PSA)

Engineer Frank Yanik Probabilistic Safety Assessment Engineer Roger Stobert Contract Project Manager NFPA 805 Jim Kuemin Licensing Engineer Enclosure 2

ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.

IRA!

Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosures:

1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Listserv Distribution:

PUBLIC LPL3-1 r/f RidsRgn3MailCenter Resource AKlein, NRR JGeissner, Rill RidsNrrDorLpl3-1 Resource RidsNrrPMANO Resource MVaaler, NRR TTaylor, Rill RidsNrrPMPalisades Resource RidsNrrLABTully Paul Lain, NRR HBarrett RidsAcrsAcnw_MailCtr Resource RidsOgcRp Resource JEliegood, Rill SBagley, EDO R-III CTucci, NRR ADAMS Accession No' ML093030151 OFFICE LPL3-1/PM LPL3-1/LA DRNAFPB/BC LPL3-1/BC NAME MChawla THarris AKlein RPascarelli DATE 10/30/09 10/30/09 10/30/09 10/30/09