MONTHYEARML24016A0052024-01-23023 January 2024 Summary of Meeting with Holtec Decommissioning International, LLC, Regarding Power Operations Technical Specifications ML23303A2132023-11-0101 November 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit a License Transfer Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23263A0012023-09-27027 September 2023 Summary of August 29, 2023, Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit an Exemption Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclea ML23171B1222023-06-22022 June 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23107A1212023-04-20020 April 2023 Summary of Meeting with Holtec Decommissioning International, Llc Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML22292A2612022-10-31031 October 2022 PSDAR Meeting Summary ML22132A0892022-05-12012 May 2022 Summary of the April 26, 2022, Public Outreach to Discuss the NRC 2021 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML21200A2262021-07-19019 July 2021 Summary of the July 1, 2021, Public Outreach to Discuss the NRC 2020 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML21145A0482021-06-0202 June 2021 Summary of May 12, 2021, Teleconference with Entergy Nuclear Operations, Inc. to Discuss Potential License Amendment Request Related to Permanently Defueled Technical Specifications for Palisades Nuclear Plant ML21012A0382021-01-14014 January 2021 December 8, 2020, Summary of Public Teleconference with Entergy Nuclear Operations Inc. Regarding Pre-submittal of a License Transfer Application to Holtec International for Palisades Nuclear Plant ML20309A2372020-11-0606 November 2020 Summary of Public Teleconference with Entergy Nuclear Operations, Inc. to Discuss Future Request for One-Time Exemption from Certain Requirements of 10 CFR 50, Appendix E, Section Iv.F. at Palisades Nuclear Plant (EPID L-2020-LRM-0091 ML20304A1442020-11-0202 November 2020 Summary of September 21, 2020, Public Teleconference with Entergy Nuclear Operations Inc. Regarding a Proposed Alternative for Repair of Reactor Vessel Head Penetrations for Palisades Nuclear Plant ML20280A6972020-10-13013 October 2020 20200910 NRC Mid Outage Q and a for Phone Call for Palisades 1R27-Entergy Responses ML20280A6962020-10-13013 October 2020 20200912 NRC Mid Outage Q and a for Phone Call for Palisades 1R27 (Revised) ML20280A6952020-10-13013 October 2020 Letter - Palisades Nuclear Plant- Summary of September 11, 2020, Conference Call with Entergy Nuclear Operations Inc. Regarding the Fall 2020 Steam Generator Tube Inspections at Palisades Nuclear Plant EPID L-2020-LRO-0051 ML20231A2202020-08-17017 August 2020 Summary of Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Palisades Nuclear Plant ML19296D0632019-11-0101 November 2019 August 2019 Palisades NEIMA 108 Public Meeting Summary ML19136A2552019-05-16016 May 2019 Summary of the Public Outreach/Open House to Discuss the NRC 2018 End-of-Cycle Plant Performance Assessment of the Palisades Nuclear Plant ML18351A2382018-12-18018 December 2018 Summary of Public Teleconference Call with Entergy Nuclear Operations. Inc., Regarding Emergent Alternative Request for Repair of Central Rod Drive Nozzles at Palisades Nuclear Plant ML18340A0072018-12-0606 December 2018 Summary of Call with Entergy Nuclear Operations, Inc. - Verbal Authorization of Request for Alternative for the Repair of Reactor Vessel Closure Head Penetrations ML18268A2802018-09-26026 September 2018 Summary of Public Teleconference Call with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Relocate Surveillance Frequencies to Licensee Control ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18113A6592018-04-23023 April 2018 Summary of Open House to Discuss the 2017 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML18008A2302018-01-10010 January 2018 Summary of Public Teleconference Meeting with Entergy Nuclear Operations, Inc., Regarding Request to Extend Enforcement Discretion for Tornado-Generated Missile Non-Conformances at Palisades Nuclear Plant ML17338B0502017-12-0505 December 2017 Summary of November 28, 2017, Public Meeting with Entergy Nuclear Operations, Inc. Regarding a Potential Request Associated with an Alternative to the Reexamination Frequency for a Relevant Condition ML17335A0262017-12-0505 December 2017 Summary of November 27, 2017 Public Meeting with Entergy Nuclear Operations, Inc. Regarding Request to Extend Enforcement Discretion for Tornado Missle Non-Confomances ML17227A2742017-08-14014 August 2017 Summary of the July 26, 2017, Public Meeting Regarding Palisades Nuclear Plant ML17173A7672017-07-28028 July 2017 Summary of 6/20/2017 Meeting with Entergy to Discuss Plan for Decommissioning Licensing Actions of Palisades, Pilgrim, Indian Point, Units 2 and 3, and Vermont Yankee ML17164A3112017-06-27027 June 2017 Summary of 06/12/2017, Pre-Submittal Meeting with Entergy Nuclear Operations, Inc. to Discuss Palisades Nuclear Plant Post Shutdown Emergency Plan and Administrative Technical Specification License Amendment Request ML17160A1812017-06-14014 June 2017 Summary of Conference Call with Palisades Nuclear Plant Regarding the Spring 2017 Steam Generator Inspections ML17080A1492017-03-23023 March 2017 Summary of March 20, 2017, Public Meeting with Entergy Nuclear Operations, Inc. Regarding the Cyber Security Plan Implementation Schedule ML16344A0862016-12-20020 December 2016 Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding National Fire Protection Association Standard 805 ML16277A6772016-10-11011 October 2016 Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding the Proposed Closure Plant for Generic Safety Issue 191, Assessment of Debris Accumulation on Pressurized Water Reactor (PWR) Sump Performance ML16182A5142016-06-30030 June 2016 Summary of the June 23, 2016, Public Meeting Regarding Palisades Nuclear Plant ML16127A1722016-05-0505 May 2016 6/23/16 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of the Palisades Nuclear Plant Performance for the 2015 Calendar Year ML16035A4252016-03-0101 March 2016 Summary of January 25, 2016, Pre-Application Teleconference Meeting with Entergy Nuclear Operations to Discuss a Forthcoming License Amendment Request Regarding Steam Generator Cold Leg Alternate Repair Criteria at Palisades Nuclear Plant ( ML15294A2972015-10-27027 October 2015 Steam Generator Tube Inspection Discussion During Palisades 2015 (RF24) Outage (Preliminary Information) ML15294A2922015-10-27027 October 2015 Summary of Conference Call with Palisades Nuclear Plant Regarding the Fall 2015 Steam Generator Inspections ML15272A0652015-09-30030 September 2015 Summary of Telephone Conference on September 28, 2015, Verbal Authorization of Relief Request for Palisades Nuclear Plant ML15261A0392015-09-21021 September 2015 September 17, 2015, Summary of Telephone Conference Verbal Authorization of Relief Request for Palisades Nuclear Plant ML15119A0442015-05-0606 May 2015 Summary of April 14, 2015, Meeting with Entergy Nuclear Operations, Inc. on Plans for Volumetric Examinations of Primary Coolant System Alloy 600 Welds ML15118A0352015-04-27027 April 2015 Meeting Summary with Public to Discuss the 2014 Annual Assessment Results for Palisades Nuclear Plant ML15026A5202015-01-29029 January 2015 Summary of Palisades Nuclear Plant, June 24 - 28, 2013, Audit Associated with License Amendment Request to Transition to National Fire Protection Association 805 Standards (Tac No. MF0382) ML14192B3842014-07-11011 July 2014 Summary of Public Meeting Regarding Palisades Nuclear Plant to Discuss 2013 Annual Assessment ML14093A2432014-04-30030 April 2014 Summary of Conference Call with Palisades Nuclear Plant Regarding the Fall 2014 Steam Generator Inspections ML13347B2862013-12-13013 December 2013 Summary of Public Meeting Webinar Regarding Independent Spent Fuel Storage Installation (ISFSI) Basics ML13296A5402013-10-28028 October 2013 Summary of Pre-Application Teleconference Meeting with Entergy Nuclear Operations, Inc., to Discuss a Forthcoming Palisades Equivalent Margin Analysis Submittal ML13221A5962013-08-0909 August 2013 7/16/2013 - Summary of Public Internet Event Briefing Regarding Palisades Safety Injection Refueling Water Tank (SIRWT) Leak ML13165A2422013-06-13013 June 2013 Summary of Public Meeting Webinar to Discuss Nrc'S Perspectives on Palisades Nuclear Power Plant Effluents 2024-01-23
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 30, 2009 LICENSEE: Entergy Operations, Inc. (ENO)
FACILITIES: Palisades Nuclear Plant (PNP)
SUB~IECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 14, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (I\lFPA) STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The licensee reported that there has been significant increase in the work scope. As a result, the milestone date for completion of some of the tasks is shown to be later than the final license amendment request date of March 31, 2010. The licensee obtained additional resources for the project but has not completed development of a schedule. Enclosure 2 provides the list of all attendees.
Background
On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.
~j /)
L1'~~ &t 1114--
Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255 Enclosures.
1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Distribution via ListServ
10/14/2009 Palisades NFPA 805 Project Milestones NEI Task Milestone Start Title Status' ,
No. Date' Date Transition of Nuclear Safety Performance See Task 1:
Criteria (NEI 04-02 Table B-2) 11/25/09 -
Comments Fundamental Fire Protection Program & Desig See Task 2: 12/22/09 -
Elements (NEI 04-02 Table B-1) Comments Radioactive Release Transition (NEI 04-02 See Task 3: 12/22/09 -
Table G-1) Comments Nuclear Safety Analysis Transition (NEI 04-02 See Task 4:
Table B-3) 03/29/10 Comments See ST4.1.1 Off-Site Power Cable Selection and Analysis 11/05/09 -
Comments ST 4.1.2 Other Power Cable Selection and Analysis - Complete -
Subsequent Cablellnstrument Identification & See ST4.1.3 11/13/09 -
Analysis Comments Non-Power Operational Modes Transition See Task 5: 11/19/09 -
NEI 04-02 Table F-1) Comments See Task 6: Internal Events PRA 06/03/10 -
Comments ST 6.2.1 Prepare LERF Model - Complete -
See ST 6.2.2 Update Flooding Analysis 11/03/09 -
Comments See ST 6.3 Thermal Hydraulic Analysis for MSOIHRA 12108/09 Comments ST 6.4 Internal Events PRA Peer Review 10/30109 Not Started 10/26/09 See Task 7: Fire PRA 02/01/10 -
Comments ST 7.6.4 R3 Internal Events Model - Complete -
See ST 7.7 Quantification Risk Screening 01/21/10 -
Comments ST 7.8 Scoping for Fire Modeling - Complete -
See ST 7.9/10 Circuit Failure Mode Likelihood Analysis 11120109 -
Comments See ST 7.12 Post Fire HRA 12/07/09 -
Comments ST 7.13 Seismic Fire Interaction Assessment - Complete -
See ST 7.14 Fire Risk Quantification 02/24/10 02/24/10 Comments See ST 7.15 Uncertainty and Sensitivity Analysis 02/25/10 -
Comments ST 7.17 Fire PRA Peer Review 01/22/10 Not Started 01/18/10 See Task 8: NFPA 805 Change Evaluations 04/22/10 -
Comments See ST 8.1 Change Evaluations 03/30/10 Comments See ST 8.2 Non-Compliance Risk Evaluations 04/22/10 02/10/10 Comments Palisades Mapping of Post Transition See Task 9: 01/26/10 11/16/09 Procedures & Document Revisions Comments See Task 10: Transition Report 05/12/10 09/07/09 Comments Task 11: License Amendment Request (LAR) 03/31/10 - -
Notes:
1 The original milestone dates per schedule PLP B05 S1~3 WIFe Schedule 12NOVOB and are subject to change. The current schedule (B05 S8 OJ 050CT09) dates were ...alidated to be on or before these dates unless otherwise noted.
2 "On Track" means that the task current percentage completed i2: the expected completion percent and the expected completion date for the task is projected to be mel.
3 Start dates provided are estimates and may \lary contingent upon predecessor completion and available resources at that time. Even if this start date is adjusted, the completion date is still expected to be met unless indicated otherwise Comments:
All uncompleted task dates have slipped except the IE PRA Peer Review 1ST 6.4J. Fire PRA Peer Review [ST 7.17]. and the LERF model 1ST 6.2.1] which was completed.
The Task 11. LAR submittal date is prior to the IE PRA completion [T 6J, Change Evaluations [T 8). and the Transition report completion [T 10] due to the self-imposed contraint for the LAR submittal of the end of the 1st quarter 2010.
E:\Palisades\PLP\Enforcement Extension\Milestone Itrs\NRC Milestones 10-14-09.xls Enclosure 1
TELEPHONE CONFERENCE CALL ON NFPA 805 TRANSITION PROGRESS BETWEEN U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC.
LIST OF PARTICIPANTS OCTOBER 14, 2009 PARTICIPANTS TITLE/POSITION AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC)
Mahesh Chawla Proiect Manaaer HEADQUARTERS Alex Klein Branch Chief Harrv Barrett Senior Fire Protection Enaineer John Ellegood Senior Resident Inspector REGION ENTERGY Bob VanWagner Program Engineering Manager PALISADES NUCLEAR PLANT Ron Penna Program Engineering Supervisor Tom Swiecicki Fire Protection Lead Brian Brogan Probabilistic Safety Assessment (PSA)
Engineer Frank Yanik Probabilistic Safety Assessment Engineer Roger Stobert Contract Project Manager NFPA 805 Jim Kuemin Licensing Engineer Enclosure 2
ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.
IRA!
Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosures:
1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Listserv Distribution:
PUBLIC LPL3-1 r/f RidsRgn3MailCenter Resource AKlein, NRR JGeissner, Rill RidsNrrDorLpl3-1 Resource RidsNrrPMANO Resource MVaaler, NRR TTaylor, Rill RidsNrrPMPalisades Resource RidsNrrLABTully Paul Lain, NRR HBarrett RidsAcrsAcnw_MailCtr Resource RidsOgcRp Resource JEliegood, Rill SBagley, EDO R-III CTucci, NRR ADAMS Accession No' ML093030151 OFFICE LPL3-1/PM LPL3-1/LA DRNAFPB/BC LPL3-1/BC NAME MChawla THarris AKlein RPascarelli DATE 10/30/09 10/30/09 10/30/09 10/30/09