Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402-2801 October 23, 2009 10 CFR 50.90 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, UnittI Facility Operating License No. IDPR-33 NRC Docket No. 50-259

Subject:

Technical Specifications Change TS-446 - Safety Limit Minimum Critical Power Ratio (SLMCPR),- Cycle 8 Operation (NRC TAC No.

MD92 *,*;*ithdrawa4*of Request

References:

1. Letter from TVA to NRC, "Bro wns Ferry Nuclear Plant (BFN) - Unit 1 -

Technical Specifications (TS), Change TS-446 - Safety Limit Minimum Critical Power Ratio (SLMCPR) - Cycle 8 Operation," dated July 18, 2008

2. Letter from to TVA to NRC, "Technical Specification Change TS-467 -

Utilization of AREVA Fuel and Associated Analysis Methodologies,"

dated October 23, 2009 By letter dated July 18, 2009 (Ref. 1), the Tennessee Valley Authority (TVA) submitted a Technical Specifications (TS) change request t&revise the Browns Ferry Nuclear Plant, Unit 1, Safety Limit Minimum Critical Power Rati (SLMCPR) values to incorporate the results of the SLMCPR analysis performed based on Extended Power Uprate (EPU) conditions for Unit 1 Cycle 8. By letter dated October 23, 2009 (Ref. 2), the TVA submitted TS change request TS-467 to allow utilization of AREVA NP fuel and associated analysis methodologies. TS-467 also includes proposed changes to the Unit 1 SLMCPR values that incorporate the results of the Unit 1 Cycle 9 SLMCPR analysis performed based on EPU conditions. Due to delays in the EPU review for the Browns Ferry Nuclear Plant, approval and impl`mentation of EPU for Unit 1 is not expected to occur during Unit 1 Cycle 8. The proposed changes in TS-467, associated with SLMCPR values, supersede the SLMCPIRchanges proposed in TS-446.

Accordingly, the TVA is withdrawing TS change, request TS-446.

Aoo Printed on recycled paper

U. S. Nuclear Regulatory Commission Page 2 October 23, 2009 If you have any questions or need additional information, please contact Dan Green at (423) 751-8423.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on the 23rd day of October 2009.

Respectfully, R. M. Krich Vice President Nuclear Licensing cc:

NRC Regional Administrator-Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant State Health Officer - Alabama Department of Public Health