Forthcoming Prelicensing Meeting with Omaha Public Power District, to Discuss Plans for Extended Power Uprate License Amendment Request for Fort Calhoun Station, Unit 1
ML092940080
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 10/22/2009
From: Lynnea Wilkins
Plant Licensing Branch IV
To: Markley M
Plant Licensing Branch IV
Wilkins, L E, NRR/DORL/LPL4, 415-1377
References
Download: ML092940080 (1)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 22, 2009 MEMORANDUM TO: Michael T. Markley, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation .

FROM: lynnea Wilkins, Project Manager Plant Licensing Branch IV ~~ v v

/, JAiL*

Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

SUBJECT:

FORTHCOMING MEETING WITH OMAHA PUBLIC POWER DISTRICT, FORT CALHOUN STATION, UNIT 1 DATE & TIME: Thursday, November 5, 2009 2:00 p.m. - 4:00 p.m.

LOCATION: U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room 0-4-B6 Rockville, Maryland PURPOSE: The purpose of this pre-application meeting is to discuss with representatives of Omaha Public Power District (OPPD) updates to plans to submit an extended power uprate request for the Fort Calhoun Station, Unit 1.

CATEGORY 1*: This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

PARTICIPANTS: Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC OPPD T. Alexion W. Lyon L. Wilkins B. Dulee B. Van Sant G. Cranston M. Markley D. Woodyatt J. McManis H. Garg B. Parks C.Ovici W. Kemper A. Russell R. Short MEETING CONTACTS: Lynnea Wilkins, NRR Alan Wang, NRR 301-415-1377 301-415-1445 Lynnea.Wilkins@nrc.gov Alan.Wang@nrc.gov

  • Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings" (67 FR 36920), May 28, 2002.

M. Markley -2 The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in a meeting, or need a meeting notice or a transcript or other information from a meeting in another format (e.g., Braille, large print), please notify the NRC's meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.

To receive a summary of this meeting and begin receiving other plant-specific e-mail distributions, you must subscribe to the Operating Reactor Correspondence electronic distribution for this plant via http://www.nrc.gov/public-involve/listserver/plants-by-region.html.

Once subscribed, if you wish to discontinue receiving electronic distribution, you may unsubscribe at any time by visiting the same web address above.

Docket No. 50-285

Enclosure:

Agenda cc w/encl: Distribution via Listserv

MEETING AGENDA OMAHA PUBLIC POWER DISTRICT FORT CALHOUN STATION PRE-LICENSING MEETING Thursday, November 5, 2009 2:00 p.m. to 4:00 p.m.

1. Introductions and meeting objectives
2. Brief status on the progress and schedule of the extended power uprate (EPU) project
3. Potential methodology changes that may require early and separate NRC approval
4. Changes to analyses in the current license basis that do not require prior NRC approval
5. Changes to be included as part of EPU
6. NRC feedback on EPU lessons learned
7. Summary and follow-up actions
8. Public participation and adjournment Enclosure

ML092940080 OFFICE DORULPL4/PM DORLlLPL4/PM DORULPL4/LA DORLlLPL4/BC DORLlLPL4/PM MMarkley CFLyon NAME LWilkins AWang JBurkhardt for LWilkins DATE 10/21/09 10/21/09 10/21/09 10/22/09 10/22/09