ML092650677

From kanterella
Jump to navigation Jump to search
Slides from the Public Meeting with Constellation Energy - Ginna ISFSI Presentation
ML092650677
Person / Time
Site: Ginna Constellation icon.png
Issue date: 09/15/2009
From:
Constellation Energy Group
To:
Decommissioning Branch I
References
Download: ML092650677 (15)


Text

The Ginna Project j Update p for the Independent Spent Fuel Storage Installation (ISFSI)

Project September 15, 2009

Ginna Project Summary 3/4 Ginna requires ISFSI in service prior to the Spring 2011 Refueling Outage.

3/4 Ginna will utilize the TransNuclear NUHOMS system 3/4 Ginna will utilize a General License.

3/4 ISFSI Project includes ISFSI, 125 ton Single Failure Proof Crane, Canister Preparation Building (CPB), and Upgraded Haul Path.

3/4 Ginna ISFSI is designed for 30 Horizontal Storage Modules (HSMs) with 10 initially installed.

2

Ginna ISFSI Pad Site Layout 3

Ginna ISFSI Project Milestones

  • NRC Inspection of ISFSI Pad installation completed October 2008
  • Initial 10 HSMs installation and Security Upgrades completed August 2009
  • NRC Inspection of 125 Ton Single Failure Proof Crane (ASME NOG-1) Factory Test completed August 2009
  • Crane Installation and Testing scheduled to complete in November 2009
  • Internal Dry Runs scheduled to take place in May 2010 4

Ginna ISFSI Upcoming Activities

  • Crane Installation September/October 2009

- 20 Trucks to Deliver

- 4 Super Loads

- Critical Activity is Positioning of Stationary Runways

  • CPB Construction October 2009 to March 2010

- Coordination with crane installation

- Weather concerns result in long schedule

  • Transporter delivery February 2010 (Shared all sites)

- Factory Acceptance Test (FAT) with Cask mock-up

- Critical Path for dry run schedule 5

Crane Foundation Ready for Crane 6

125 Ton Crane Assembly, rolling girder 7

125 Ton Single Failure Proof Crane, FAT 8

Ballast Connection 125% load test at Ginna 9

125% load test, girder extended 10

FAT, TC/DSC mockup plug installation 11

Crane loading for shipping 8-25-09 12

Ginna Level 1 Schedule 13

Questions Questions 14

The Ginna Project Update for the Independent Spent Fuel Storage Installation (ISFSI)

Project