The Ginna Project Update for the
j p
Independent Spent Fuel Storage Installation (ISFSI)
Project September 15, 2009
Ginna Project Summary 3/4 Ginna requires ISFSI in service prior to the Spring 2011 Refueling Outage.
3/4 Ginna will utilize the TransNuclear NUHOMS system 3/4 Ginna will utilize a General License.
3/4 ISFSI Project includes ISFSI, 125 ton Single Failure Proof Crane, Canister Preparation Building (CPB), and Upgraded Haul Path.
3/4 Ginna ISFSI is designed for 30 Horizontal Storage Modules (HSMs) with 10 initially installed.
2
Ginna ISFSI Pad Site Layout 3
Ginna ISFSI Project Milestones
- NRC Inspection of ISFSI Pad installation completed October 2008
- Initial 10 HSMs installation and Security Upgrades completed August 2009 4
completed August 2009
- NRC Inspection of 125 Ton Single Failure Proof Crane (ASME NOG-1) Factory Test completed August 2009
- Crane Installation and Testing scheduled to complete in November 2009
- Internal Dry Runs scheduled to take place in May 2010
Ginna ISFSI Upcoming Activities
- Crane Installation September/October 2009
- 20 Trucks to Deliver
- 4 Super Loads
- Critical Activity is Positioning of Stationary Runways
- CPB Construction October 2009 to March 2010 CPB Construction October 2009 to March 2010
- Coordination with crane installation
- Weather concerns result in long schedule
- Transporter delivery February 2010 (Shared all sites)
- Factory Acceptance Test (FAT) with Cask mock-up
- Critical Path for dry run schedule 5
Crane Foundation Ready for Crane 6
125 Ton Crane Assembly, rolling girder 7
125 Ton Single Failure Proof Crane, FAT 8
Ballast Connection 125% load test at Ginna 9
125% load test, girder extended 10
FAT, TC/DSC mockup plug installation 11
Crane loading for shipping 8-25-09 12
Ginna Level 1 Schedule 13
Questions Questions 14 Questions