Mid-Cycle Performance Review and Inspection Plan - Surry Power Station
ML092440499
Person / Time
Site: Surry, 07200002, 07200055  Dominion icon.png
Issue date: 09/01/2009
From: Gerald Mccoy
NRC/RGN-II/DRP/RPB5
To: Heacock D
Virginia Electric & Power Co (VEPCO)
References
Download: ML092440499 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 September 1, 2009 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

SURRY POWER STATION

Dear Mr. Heacock:

On August 13, 2009, the NRC staff completed its performance review of Surry Power Station Units 1 and 2. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from July 1, 2008 through June 30, 2009. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only-Security-Related Information" will include the Security cornerstone performance review and resultant inspection plan.

Plant performance for the most recent quarter at Surry Power Station Units 1 and 2 was within the Licensee Response column of the NRC=s Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.

The enclosed inspection plan details the inspections, less those related to security, scheduled through December 31, 2010. In addition to ROP baseline inspection activities, we also plan on conducting infrequently performed inspections, which include; ISFSI Operational Inspection, and Operator Licensing Examinations. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.

The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

VEPCO 2

As you may know, the NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible.

Please contact me at 404-562-4551 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Gerald J. McCoy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos: 50-280, 50-281, 72-02, 72-55 License Nos: DPR-32, DPR-37

Enclosure:

Surry Inspection/Activity Plan cc w/encl: (See Page 3)

VEPCO 2

As you may know, the NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible.

Please contact me at 404-562-4551 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Gerald J. McCoy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos: 50-280, 50-281, 72-02, 72-55 License Nos: DPR-32, DPR-37

Enclosure:

Surry Inspection/Activity Plan cc w/encl: (See Page 3)

X PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE X NON-SENSITIVE ADAMS: G Yes ACCESSION NUMBER:_________________________

X SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP SIGNATURE DA GM NAME DArnett GMcCoy DATE 8/21/09 9/1/09 E-MAIL COPY?

YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME:

S:\\DRP\\PERIODIC ASSESSMENTS REPORTS\\EOC MID-CYCLE\\2009\\MID-CYCLE\\RPB5\\SURRYMIDCYCLELETTER2009.DOC

VEPCO 3

cc w/encl:

Gerald T. Bischof Site Vice President Surry Power Station Virginia Electric and Power Company Electronic Mail Distribution B. L. (Sonny) Stanley Director, Nuclear Safety and Licensing Virginia Electric and Power Company Electronic Mail Distribution Lillian M. Cuoco, Esq.

Senior Counsel Dominion Resources Services, Inc.

Electronic Mail Distribution Chris L. Funderburk Director, Nuclear Licensing & Operations Support Virginia Electric and Power Company Electronic Mail Distribution Ginger L. Alligood Virginia Electric and Power Company Electronic Mail Distribution Virginia State Corporation Commission Division of Energy Regulation P.O. Box 1197 Richmond, VA 23209 Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219 Senior Resident Inspector Surry Power Station U.S. Nuclear Regulatory Commission 5850 Hog Island Rd Surry, VA 23883 Michael M. Cline Director Virginia Department of Emergency Services Management Electronic Mail Distribution

VEPCO 4

Letter to David A. Heacock from Gerald J. McCoy dated September 1, 2009

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - SURRY POWER STATION Distribution w/encl: