Ltr. 08/11/09 Duane Arnold Request for Information Re NRC License Renewal Inspection
ML092240602
Person / Time
Site: Duane Arnold  NextEra Energy icon.png
Issue date: 08/11/2009
From: Ann Marie Stone
NRC/RGN-III/DRS/EB2
To: Costanzo C
Duane Arnold
References
Download: ML092240602 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 August 11, 2009 Mr. Christopher R. Costanzo Vice President Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324-9785

SUBJECT:

DUANE ARNOLD ENERGY CENTER, INFORMATION REQUEST FOR AN NRC LICENSE RENEWAL INSPECTION

Dear Mr. Costanzo,

On November 2, 2009, the NRC will begin a license renewal inspection at the Duane Arnold Energy Center. This inspection will be performed in accordance with the NRC Inspection Procedure IP 71002. The on-site portion of the inspection will take place on November 2-6, 2009, and November 16-20, 2009.

The lead inspector for this inspection is Benny Jose. We understand that our regulatory contact for this inspection is Mr. Kenneth Putnam of your organization, who can be reached at (319) 851-7238.

If there are any questions about the inspection or this request, please contact the lead inspector at (630) 829-9756 or via e-mail at Benny.Jose@nrc.gov.

Experience has shown that these inspections are extremely resource intensive, both for the NRC inspectors and the applicant staff. In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we would like to request the documents needed for the inspection. In order to ensure the inspection team is adequately prepared for the inspection, please provide a copy of the original license renewal application and include any amendments to the application submitted after October 1, 2008. The lead inspector will coordinate with your staff to determine what additional information the team will review, or need access to, during or before the on-site inspection. It is important that all documents provided are up to date and complete. This information should be made available via compact disc to the Region III Office no later than October 16, 2009.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the

C. Costanzo Publicly Available Records System (PARS) component of NRCs Agency wide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-331;72-032 License No. DPR-49 cc w/encl:

M. Nazar, Senior Vice President and Nuclear Chief Operating Officer M. Ross, Vice President and Associate General Counsel A. Khanpour, Vice President, Engineering Support D. Curtland, General Plant Manager S. Catron, Manager, Licensing M. Mashhadi, Senior Attorney Chairman, Linn County, Board of Supervisors M. Rasmusson, State Liaison Officer R. Anderson, Vice President, Nuclear Plant Support R. Kundalkar, Vice President, Fleet Organizational Support M. Cornell, Director, Licensing & Performance Improvement

C. Costanzo Publicly Available Records System (PARS) component of NRCs Agency wide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-331;72-032 License No. DPR-49 cc w/encl:

M. Nazar, Senior Vice President and Nuclear Chief Operating Officer M. Ross, Vice President and Associate General Counsel A. Khanpour, Vice President, Engineering Support D. Curtland, General Plant Manager S. Catron, Manager, Licensing M. Mashhadi, Senior Attorney Chairman, Linn County, Board of Supervisors M. Rasmusson, State Liaison Officer R. Anderson, Vice President, Nuclear Plant Support R. Kundalkar, Vice President, Fleet Organizational Support M. Cornell, Director, Licensing & Performance Improvement DISTRIBUTION:

Susan Bagley RidsNrrDorlLpl3-1 Resource RidsNrrPMDuaneArnold Resource RidsNrrDirsIrib Resource Cynthia Pederson Kenneth OBrien Jared Heck Allan Barker Jeannie Choe Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource DOCUMENT NAME: Ltr 08__09 Duane Arnold Request For Information AMS.doc Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME BJose:ls AMStone DATE 08/07/09 08/11/09 OFFICIAL RECORD COPY