Attachment 6 OBDI 202 - IOLE Process DRAFT OUTLINE COMMENTS Rev 0 Facility:
FC First Exam Date:
03/27/2009 Written Exam Outline (1/22/2009)
Comment Resolution 1 Put revision number on all forms.
Will do.
2 Sampling methodology - were 000007 Reactor Trip and CE/E02 Reactor Trip Recovery sampled as separate E/APEs?
Yes.
3 Sampling methodology - were 000040 Steam Line Rupture and CE/E05 Excessive Steam Demand sampled as separate E/APEs?
Yes.
4 Provide ES-401-2/3s for Audit exam.
Will do.
Administrative JPM Outline (1/22/2009)
Comment Resolution 1 Use A designators (A1-A4 for RO, A5-A9 for SRO)
Will do.
2 Put revision number on all forms.
Will do.
3 Draft exam submittal for Modified JPMs must include a copy of the parent JPM.
Will do.
4 Provide ES-301-1 for Audit exam.
Will do.
5 SRO - G2.2.37 is also on written exam.
Ensure no content overlap.
Will do.
6 SRO - Is the Authorize Monitor Tank Release the same as the Radiation Control Admin JPM in the 2005 exam?
No.
OBDI 202 - IOLE Process Control Room / In-Plant System JPM Outline (1/22/2009)
Comment Resolution 1 Use S designators (S1-S8) and P designators (P1-P3)
Will do.
2 Put revision number on all forms.
Will do.
3 Draft exam submittal for Modified JPMs must include a copy of the parent JPM.
Will do.
4 Provide ES-301-2 for Audit exam.
Will do.
Simulator Scenario Outline Comments (1/22/2009)
Comment Resolution 1 Provide ES-D-1s for Audit exam.
Will do.
2 For each scenario, complete Target Quantitative Attributes from ES-301-4 and include on D-1s.
Will do.
3 Last two NRC exams have included SGTR - replace this Major Event Will do.
4 Scenario 3, Event 2 - minor discriminatory value Will replace the event.
5 Scenario 3, Event 7 - include description of PT-910 Will do.
6 ES-305-1: blocks should identify event numbers, not totals (like the ES-301-6)
Will correct.
7 ES-305-1: final will depend on which scenarios are selected for exam (after validation)
Okay.
8 When preparing Draft Op Test, identify all Tech Specs and action statement(s) in the D-2 for each TS call.
N/A 9
When preparing Draft Op Test, Critical Tasks must be carefully defined, including time limits where applicable.
N/A 10 When preparing Draft Op Test, identify all procedure transitions in the D-2s.