MONTHYEARML24164A0182024-06-12012 June 2024 May 29, 2024, Summary of the Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2 ML24152A1852024-06-0404 June 2024 Summary of March 28, 2024, Closed Hybrid Pre-Submittal Meeting Between Constellation Energy Generation, LLC and the U.S. Nuclear Regulatory Commission Regarding a Future Amendment Request for Fuel Transition ML24128A2512024-05-14014 May 2024 Summary of April 11, 2024, Public Meeting with Constellation Energy Generation, LLC Regarding Proposed Alternative to Implement American Society of Mechanical Engineers Operation and Maintenance Code Case OMN-32 ML24113A2872024-04-25025 April 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Regarding Hooded Masks ML24079A2382024-03-19019 March 2024 Summary of March 7, 2024 Regulatory Conference with Constellation Nuclear Regarding Braidwood Station, Unit 2 ML24009A0552024-01-24024 January 2024 Summary of January 8, 2024, Presubmittal Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Removal of the Power Distribution Monitoring System from Technical Specifications ML23363A0942024-01-0303 January 2024 Summary of October 4, 2023, Pre Submittal Meeting Between the U.S. NRC and Constellation Energy Generation, LLC, Regarding Revising Technical Specification 3.7.9. Ultimate Heat Sink (UHS) ML23352A3822023-12-19019 December 2023 Summary of December 11, 2023, Presubmittal Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Deletion of Technical Specification 5.6.5.b.5 ML23320A2472023-11-17017 November 2023 Constellation - Summary of November 14, 2023, Public Pre-Application Meeting with Constellation Energy Generation, LLC on Adoption of TSTF-591 ML23263B1062023-09-22022 September 2023 R. E. Ginna Nuclear Power Plant - Constellation - Pre-Application Amse 9/18/2023 Meeting Summary ML23164A2112023-06-14014 June 2023 Summary of the June 1, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2; and Byron Station, Units 1 and 2 ML23129A0202023-05-30030 May 2023 Summary of March 22, 2023, Closed Meeting with Constellation Energy Generation, LLC, to Discuss a Future License Amendment Request That Allows Byron Station and Braidwood Station to Utilize a New Citicality Analysis for the Spent Fuel Pools ML23055A0352023-03-24024 March 2023 Summary of February 23, 2023, with Constellation Energy Generation, LLC on Proposed Changes to Emergency Plans to Revise Emergency Action Levels ML23033A6662023-02-0909 February 2023 Summary of Public Meeting with Constellation Energy Generation, LLC (Constellation) to Discuss Its Request for Alternatives for Certain Steam Generator Weld Inspections for Calvert Cliffs 1 & 2, Byron 1 & 2, Braidwood 1 & 2, and Ginna ML22264A1992022-11-14014 November 2022 Summary of August 22, 2022, Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Performance Monitoring of Steam Generator Welds (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and ML22305A5992022-11-10010 November 2022 Summary of Closed Presubmittal Meeting Between the U. S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Transition to Framatome Fuel ML22159A2232022-06-0909 June 2022 Summary of the June 2, 2022, Public Outreach to Discuss the NRC 2021 End of Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2 ML22111A2852022-05-0909 May 2022 Summary of April 4, 2022, Meeting Between the U.S. NRC and Constellation Energy Generation, LLC, Regarding Performance Monitoring of Pressurizer Welds (EPIDs L-2022-LLR-0035/36) ML22111A3362022-05-0909 May 2022 Summary of April 7, 2022, Meeting Between the NRC and Constellation Energy Generation, LLC, Regarding Performance Monitoring of Pressurizer Welds (Epids L-2022-LRR-0035 and 0036) ML21330A0722021-12-0303 December 2021 Summary of November 17, 2021, Meeting with Exelon Generation Company, LLC, Related to a Future License Amendment to Remove License Condition 2.C.(12)(d) for Braidwood Station, Unit 2 ML21333A1532021-11-30030 November 2021 Summary of November 16, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Extend the Inservice Inspection Interval ML21237A0412021-08-30030 August 2021 Summary of the July 27, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use Case OMN-28, ML21176A0822021-07-0606 July 2021 June 15, 2021, Summary of Meeting with Exelon Generation Company, LLC Vessel Nozzle Repair Related to a Planned Request for an Alternative Related to Reactor Pressure ML21139A1852021-06-22022 June 2021 Summary of Meeting with Exelon Generation Company, LLC Regarding Its Requested Alternative to Eliminate Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting ML21167A2152021-06-16016 June 2021 June 8, 2021, Summary of the Public Outreach to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2; and Byron Station, Units 1 and 2 ML21147A4262021-06-0303 June 2021 Summary of May 12, 2021, Meeting with Exelon Generation Company, Llc, Related to a Planned License Amendment to Modify the Ultimate Heat Sink Technical Specifications ML21011A2822021-01-21021 January 2021 Summary of January 6, 2021, Presubmittal Meeting Between the NRC and Exelon Generation Company, LLC Regarding Licensing Activities to Support the Planned Early Closures of Byron, Unit Nos. 1 and 2 and Dresden, Units 2 and 3 ML20351A2832020-12-18018 December 2020 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Exemption to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20342A3522020-12-10010 December 2020 Summary of November 13, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alterantive to Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting (EPID-L-2020-LRM-0102) ML20323A0332020-12-0101 December 2020 Summary of November 4, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20218A5302020-08-0505 August 2020 July 14, 2020, Summary of the Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2; and Byron Station, Units 1 and 2 ML20181A0002020-06-29029 June 2020 Summary of 6/24/20 Meeting with Exelon Generation Company, LLC Regarding Planned Request for Alternative to Supplemental Valve Position Indication Testing Requirements for Braidwood, Calvert Cliffs, Clinton, Limerick, Nine Mile, Peach Botto ML19326C3582019-12-0303 December 2019 Summary of November 20, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Revise the Quality Assurance Program ML19326A3152019-12-0303 December 2019 Summary of November 18, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Supplemental Valve Position Indication Testing Requirements ML19162A0272019-06-21021 June 2019 Summary of June 4, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Extend the Test Interval for Safety Relief Valves ML20108F0902019-04-20020 April 2019 April 15, 2020, Meeting Summary with Exelon Generation Company, LLC Regarding Planned Request to Defer Submittal of Owner'S Activity Report (Braidwood 2,Byron 2,Calvert Cliffs 1, LaSalle 1, Limerick 1, Nine Mile Point 2, Quad 2, R. E. Ginna ML19036A8832019-02-0707 February 2019 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use ASME Code Case N-879 ML18354B1712019-01-0202 January 2019 Summary of December 19, 2018, Meeting with Exelon Generation Company, LLC Regarding the Use of Boiling Water Reactor Vessel and Internals Project Guidelines ML18325A1712018-11-28028 November 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned Fleet License Amendment Request to Revise Technical Specifications for High Radiation Areas ML18297A1722018-10-26026 October 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned License Amendment Request to Adopt TSTF-427 ML18225A3042018-08-16016 August 2018 Summary of August 8, 2018, Meeting with Exelon Generation Company, LLC, on a Future Relief Request to Extend the Post Peening Follow-Up Inspections for Certain Reactor Pressure Vessel Head Penetrations ML18135A0222018-05-14014 May 2018 Summary of the May 10th, 2018, Public Open House Regarding Braidwood Nuclear Power Station ML18120A1772018-05-0101 May 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Draft Guidance for Emergency Response Organization Staffing ML18065A8362018-03-0707 March 2018 Summary of February 27, 2018, Meeting with Exelon Generation Company, LLC Planned Fleet License Amendment Request to Relocate Staff Qualification Requirements from TSs to the Quality Assurance Topical Report ML18058A5232018-03-0101 March 2018 Summary of February 26, 2018, Meeting with Exelon Generation Company, LLC Regarding Proposed Alternative to the Main Steam Isolation Valve Testing Requirements ML18018B4432018-01-25025 January 2018 Summary of December 17, 2017, Closed Meeting with Exelon Generation Company, LLC, Regarding Tvel Lead Test Assemblies to Be Placed in the Braidwood Reactor (EPID 000976/05000456/L-2017-LRM and 000976/05000457/L-2017-LRM-0047 ML17347B1022017-12-14014 December 2017 Summary of Meeting with Exelon Generation Company, LLC on Its Planned Fleet License Amendment Request to Revise the Minimum Staffing Requirements for Emergency Response ML17184A0092017-07-10010 July 2017 Summary of June 29, 2017, Meeting with Exelon Generation Company, LLC, on Proposed Changes to Emergency Plans to Revise Emergency Action Levels (CAC Nos. MF9779-MF9801) ML17164A0512017-06-15015 June 2017 Summary of May 25, 2017, Meeting with Exelon Generation Company, LLC, on a Future License Amendment Request to Add Mitigating Actions to Technical Specifications with Two Control Room Ventilation Temperature Control System Trains Inoperable ML17132A3422017-05-12012 May 2017 Summary of the April 28, 2017, Open House to Discuss the 2016 End-of-Cycle Plant Performance Assessment of Braidwood Station 2024-06-04
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 27, 2009 LICENSEE: Exelon Generation Company, LLC FACILITY: Braidwood Station, Units 1 and 2
SUBJECT:
SUMMARY
OF THE MAY 21, 2009, PUBLIC MEETING TO DISCUSS THE BRAIDWOOD STATION, UNITS 1 AND 2, END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On May 21, 2009, the Nuclear Regulatory Commission (NRC) held a public meeting at Fossil Ridge Library in Braidwood, IL. The meeting was between NRC Region III management and Exelon Generation Company management to discuss the NRC=s assessment of the safety performance of Braidwood Station, Units 1 and 2, for the period from January 1 through December 31, 2008. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML090980411 and ML091460796, respectively. A list of principal NRC and licensee meeting participants can be found in the Enclosure.
The NRC began the meeting with an overview of the NRC=s Reactor Oversight Program (ROP), national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRC=s assessment of the performance of Braidwood Station, Units 1 and 2, in calendar year 2008, which was documented in the March 4, 2009, End-Of-Cycle assessment letter, as ML090630284. As part of this regulatory performance meeting, Exelon briefly responded to the NRC=s assessment. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.
Sincerely,
/RA/
Richard A. Skokowski, Chief Branch 3 Division of Reactor Projects Docket Nos. 50-456; 50-457 License Nos. NPF-72; NPF-77
Enclosure:
As Stated DISTRIBUTION See next page
LICENSEE: Exelon Generation Company, LLC FACILITY: Braidwood Station, Units 1 and 2
SUBJECT:
SUMMARY
OF THE MAY 21, 2009, PUBLIC MEETING TO DISCUSS THE BRAIDWOOD STATION, UNITS 1 AND 2, END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On May 21, 2009, the Nuclear Regulatory Commission (NRC) held a public meeting at Fossil Ridge Library in Braidwood, IL. The meeting was between NRC Region III management and Exelon Generation Company management to discuss the NRC=s assessment of the safety performance of Braidwood Station, Units 1 and 2, for the period from January 1 through December 31, 2008. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML090980411 and ML091460796, respectively. A list of principal NRC and licensee meeting participants can be found in the Enclosure.
The NRC began the meeting with an overview of the NRC=s Reactor Oversight Program (ROP), national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRC=s assessment of the performance of Braidwood Station, Units 1 and 2, in calendar year 2008, which was documented in the March 4, 2009, End-Of-Cycle assessment letter, as ML090630284. As part of this regulatory performance meeting, Exelon briefly responded to the NRC=s assessment. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.
Sincerely,
/RA/
Richard A. Skokowski, Chief Branch 3 Division of Reactor Projects Docket Nos. 50-456; 50-457 License Nos. NPF-72; NPF-77
Enclosure:
As Stated DISTRIBUTION See next page DOCUMENT NAME: G:\Branch TSS\ALL EOC\EOC CY 2008\EOC Letters\EOC Meeting Summaries\Braidwood 2008 EOC Mtg Summary.doc G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME JDalzell:dtp RSkokowski DATE 05/27/09 05/27/09 OFFICIAL RECORD COPY
Letter to Exelon Generation Company, LLC from R. Skokowski dated May 27, 2009
SUBJECT:
SUMMARY
OF THE MAY 21, 2009, PUBLIC MEETING TO DISCUSS THE BRAIDWOOD STATION, UNITS 1 AND 2, END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT cc w/encl: C. Pardee, Senior Vice President President and Chief Nuclear Officer (CNO), Exelon Nuclear Site Vice President - Braidwood Station Plant Manager - Braidwood Station Manager Regulatory Assurance - Braidwood Station Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Braidwood, Byron and LaSalle Associate General Counsel Document Control Desk - Licensing Assistant Attorney General J. Klinger, State Liaison Officer, Illinois Emergency Management Agency Chairman, Illinois Commerce Commission Will County Executive Will County Sheriff Director, Will County Emergency Management Agency Mayor of Joliet City Manager of Joliet Kendall County Board Chairman Kendall County Sheriff Grundy County Board Chairman Grundy County Sheriff Grundy County Emergency Management Agency Mayor of Morris Minooka Village President Mayor of Coal City Mayor of Carbon Hill Mayor of Diamond Mayor of Braidwood Mayor of Wilmington Channahon Village President Channahon Village Administrator Mayor of Shorewood Shorewood Village Administrator Mayor of Elwood Mayor of Braceville Mayor of Kankakee G. Mortensen, INPO
Letter to Exelon Generation Company, LLC from R. Skokowski dated May 27, 2009.
SUBJECT:
SUMMARY
OF THE MAY 21, 2009, PUBLIC MEETING TO DISCUSS THE BRAIDWOOD STATION, UNITS 1 AND 2, END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT DISTRIBUTION:
RidsNrrDorlLpl3-2 Tamara Bloomer RidsNrrPMBraidwood Resource RidsNrrDirsIpab Resource Patrick Hiland Kenneth OBrien Jared Heck Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource
PUBLIC MEETING PRINCIPAL ATTENDEES NRC R. Skokowski, Chief, Branch 3, Division of Reactor Projects, Region III B. Dickson, Senior Resident Inspector, Braidwood A. Garmoe, Resident Inspector, Braidwood S. Orth, Health Physics Team Lead, Division of Reactor Safety, Region III V. Mitlyng, Public Affairs Officer, Region III H. Logaras, Regional Government Liaison, Region III S. Bakhsh, Reactor Inspector, Materials Control, ISFSI, & Decommissioning, Region III M. Learn, Reactor Engineer, Materials Control, ISFSI, & Decommissioning, Region III Exelon Generation Company Braidwood Station B. Hanson, Site Vice President L. Coyle, Plant Manager D. Gullott, Regulatory Assurance Manager S. Tribuzzi, Government Affairs Manager P. Dempsey, Communications N. Miller, Outreach Manager P. Simpson, Licensing Manager L. Schofield, Licensing Engineer R. Hall, Environmental Lead Illinois Emergency Management Agency C. Settles, Section Head M. Perry, Resident Inspector Enclosure