Category:Letter
MONTHYEARIR 05000440/20230042024-01-30030 January 2024 Integrated Inspection Report 05000440/2023004 L-24-017, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2024-01-24024 January 2024 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative L-23-207, License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2024-01-24024 January 2024 License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs IR 05000440/20234022024-01-10010 January 2024 Cyber Security Inspection Report 05000440/2023402 ML24003A8032024-01-0303 January 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML23321A0472023-12-20020 December 2023 Letter to Rod L. Penfield - Perry Nuclear Power Plant, Unit 1 - License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application L-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023 CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000440/20230112023-11-28028 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000440/2023011 IR 05000440/20234032023-11-27027 November 2023 Security Baseline Inspection Report 05000440/2023403 ML23292A2972023-11-17017 November 2023 Table of Contents LAR (L-2023-LLA-0111) L-23-238, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 202023-11-10010 November 2023 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 20 L-23-052, Submittal of the Updated Safety Analysis Report, Revision 232023-10-27027 October 2023 Submittal of the Updated Safety Analysis Report, Revision 23 ML23292A2472023-10-19019 October 2023 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected ML23292A2482023-10-19019 October 2023 Fws to NRC, Federal Agency Coordination Under ESA Section 7 for Perry Nuclear Plant, Unit 1, License Renewal, and Concurrence with Not Likely to Adversely Affect Determination for Northern Long-eared Bat IR 05000440/20230032023-10-11011 October 2023 Integrated Inspection Report 05000440/2023003 ML23249A1032023-10-0303 October 2023 Letter to Rod L. Penfield, Site Vice President-Perry Nuclear Power Plant, Unit 1-Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure ML23261B0192023-09-25025 September 2023 Aging Management Audit Plan Regarding the License Renewal Application Review ML23261C3642023-09-25025 September 2023 License Renewal Application Online Reference Portal ML23256A3592023-09-22022 September 2023 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Energy Harbor Nuclear Corp. Application for License Renewal L-23-206, Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD2023-09-12012 September 2023 Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000440/20234012023-08-28028 August 2023 Public - Perry Nuclear Power Plant Security Baseline Inspection Report 05000440/2023401 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) ML23172A2852023-08-23023 August 2023 Safety Evaluation Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimate ML23227A2202023-08-15015 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Perry Nuclear Power Plant L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-001, License Amendment Request to Remove the Table of Contents from the Technical Specifications2023-08-0707 August 2023 License Amendment Request to Remove the Table of Contents from the Technical Specifications IR 05000440/20230022023-08-0202 August 2023 Integrated Inspection Report 05000440/2023002 L-23-174, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2023-07-19019 July 2023 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative ML23198A2842023-07-17017 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant IR 05000440/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection Report 05000440/2023010 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-23-050, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-22022 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-051, Plan, Nineteenth Inservice Inspection Summary Report2023-06-22022 June 2023 Plan, Nineteenth Inservice Inspection Summary Report L-22-249, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener2023-06-0505 June 2023 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener ML23144A3562023-05-25025 May 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End of Cycle Plant Performance Assessment of Perry Nuclear Power Plant, Unit 1 L-23-134, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-23023 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) IR 05000440/20230012023-05-0404 May 2023 Integrated Inspection Report (05000440/2023001) L-23-121, Annual Radiological Effluent Release Report2023-04-26026 April 2023 Annual Radiological Effluent Release Report L-23-122, Annual Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Radiological Environmental Operating Report 2024-01-30
[Table view] |
Text
May 13, 2009 Mr. Mark Bezilla Site Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P. O. Box 97, 10 Center Road, A-PY-A290 Perry, OH 44081-0097
SUBJECT:
UPCOMING INSPECTIONS OF PERRY NUCLEAR PLANT INDEPENDENT SPENT FUEL STORAGE INSTALLATION
Dear Mr. Bezilla:
The purpose of this letter is to encourage and highlight the importance of good coordination between our staffs during your Independent Spent Fuel Storage Installation (ISFSI) activities.
Experience from our inspections at other sites has highlighted communication and coordination challenges that have, on occasion, become an impact on both the licensee and the NRC. Our goal is to minimize, to the extent possible, the NRCs impact on your ISFSI critical path schedule, while ensuring that the NRC inspections are conducted in a timely and efficient manner.
Our March 4, 2009, Annual Assessment Letter from Ms. Cynthia Pederson to you provided our ISFSI inspection plans in the coming months. The inspections, particularly during dry-run demonstrations, involve in-depth reviews of your staffs approved and accepted documentation and direct inspection of key activities during ISFSI operations. Furthermore, the NRC inspections involve coordinated efforts with staff from the NRC headquarters, other regional divisions, and the Division of Nuclear Materials Safety primary ISFSI inspectors.
Given the sometimes dynamic nature of ISFSI activity schedules and the need for the NRC to effectively schedule ISFSI inspection work-load at many sites in Region III, we would like to emphasize the importance of open, frequent communications between our respective staffs.
We understand that schedule changes can and do occur due to unforeseen circumstances.
The inspectors do accommodate scheduling changes, where possible. However, the sooner that we are made aware of scheduling delays and changes the more effectively we can perform our work and minimize impact to your schedule.
M. Bezilla I look forward to an effective working relationship between our staffs. If you have any questions or concerns regarding this matter please feel free to contact me at (630) 829-9800.
Sincerely,
/RA/
Steven A. Reynolds, Director Division of Nuclear Materials Safety Docket Nos.72-069; 50-440 License No. DPR-58 cc: J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and Chief Operating Officer - FENOC D. Pace, Senior Vice President, Fleet Engineering - FENOC K. Fili, Vice President, Fleet Oversight - FENOC P. Harden, Vice President, Nuclear Support Director, Fleet Regulatory Affairs - FENOC Manager, Fleet Licensing - FENOC Manager, Site Regulatory Compliance - FENOC D. Jenkins, Attorney, FirstEnergy Corp.
Public Utilities Commission of Ohio C. OClaire, State Liaison Officer, Ohio Emergency Management Agency R. Owen, Ohio Department of Health
M. Bezilla I look forward to an effective working relationship between our staffs. If you have any questions or concerns regarding this matter please feel free to contact me at (630) 829-9800.
Sincerely,
/RA/
Steven A. Reynolds, Director Division of Nuclear Materials Safety Docket Nos. 72-069: 50-440 License No. DPR-58 cc: J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and Chief Operating Officer - FENOC D. Pace, Senior Vice President, Fleet Engineering - FENOC K. Fili, Vice President, Fleet Oversight - FENOC P. Harden, Vice President, Nuclear Support Director, Fleet Regulatory Affairs - FENOC Manager, Fleet Licensing - FENOC Manager, Site Regulatory Compliance - FENOC D. Jenkins, Attorney, FirstEnergy Corp.
Public Utilities Commission of Ohio C. OClaire, State Liaison Officer, Ohio Emergency Management Agency R. Owen, Ohio Department of Health DISTRIBUTION:
See next page
- See previous concurrence DOCUMENT NAME: G:\SEC\Work in progress\Perry.doc Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII-DNMS C RIII-DNMS RIII-DRP C RIII-DNMS NAME SBakhsh:ps* CALipa
- JLCameron SAReynolds DATE 05/04/09 05/06/09 05/05/09 05/13/09 OFFICIAL RECORD COPY
Letter to Mark Bezilla from Steven A. Reynolds dated May 13, 2009.
SUBJECT:
UPCOMING INSPECTIONS OF PERRY NUCLEAR PLANT INDEPENDENT SPENT FUEL STORAGE INSTALLATION DISTRIBUTION:
RidsNrrPMPerry RidsNrrDorlLpI3-2 RidsNrrDirsIrib Resource Mark Satorius Patrick Hiland Kenneth OBrien Jared Heck Allen Barker Cynthia Pederson Steven West Gary Shear Patrick Louden Jamnes Cameron David Hills Julio Lara SRI, Perry