May 14, 2009 Mr. Charles G. Pardee Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO), Exelon Nuclear 4300 Winfield Road Warrenville IL 60555

SUBJECT:

SUMMARY

OF THE CLINTON MAY 11, 2009, NON-PUBLIC MEETING TO DISCUSS END-OF-CYCLE SECURITY PERFORMANCE FOR CALENDAR YEAR 2008

Dear Mr. Pardee:

On May 11, 2009, the Nuclear Regulatory Commission (NRC) held a Non-Public Meeting at the Clinton Power Station, located at 8401 Tower Road, Clinton, Illinois. The purpose of the meeting was to discuss the NRC End-of-Cycle assessment of Clinton Power Station security performance for the 2008 calendar year.

Mr. Eric Duncan, Chief, Plant Support Branch, Division of Reactor Safety, Region III, opened the meeting with an introduction of NRC officials, the reason for the meeting, and a review of the NRCs Reactor Oversight Process. Mr. Duncan then discussed the Clinton Nuclear Plant Security Performance for the 2008 calendar year and provided the licensee with an opportunity to provide any response and remarks. Mr. Duncan then adjourned the meeting.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and the attendance listing will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRCs Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62

Enclosure:

Meeting Attendees

Mr. Charles G. Pardee Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO), Exelon Nuclear 4300 Winfield Road Warrenville IL 60555

SUBJECT:

SUMMARY

OF THE CLINTON MAY 11, 2009, NON-PUBLIC MEETING TO DISCUSS END-OF-CYCLE SECURITY PERFORMANCE FOR CALENDAR YEAR 2008

Dear Mr. Pardee:

On May 11, 2009, the Nuclear Regulatory Commission (NRC) held a Non-Public Meeting at the Clinton Power Station, located at 8401 Tower Road, Clinton, Illinois. The purpose of the meeting was to discuss the NRC End-of-Cycle assessment of Clinton Power Station security performance for the 2008 calendar year.

Mr. Eric Duncan, Chief, Plant Support Branch, Division of Reactor Safety, Region III, opened the meeting with an introduction of NRC officials, the reason for the meeting, and a review of the NRCs Reactor Oversight Process. Mr. Duncan then discussed the Clinton Nuclear Plant Security Performance for the 2008 calendar year and provided the licensee with an opportunity to provide any response and remarks. Mr. Duncan then adjourned the meeting.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and the attendance listing will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRCs Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62

Enclosure:

Meeting Attendees SEE PREVIOUS CONCURRENCES DOCUMENT NAME: ClintonG:\DRS\Work in Progress\CLI 05__09 DRS Mtg Summary.doc 9 Publicly Available 9 Non-Publicly Available 9 Sensitive 9 Non-Sensitive To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy OFFICE RIII RIII RIII RIII NAME TEck:co DFunk EDuncan MRing JB for DATE 05/14/09 05/14/09 05/14/09 05/14/09 OFFICIAL RECORD COPY

Letter to Charles G. Pardee from Eric Duncan dated May 14, 2009

SUBJECT:

SUMMARY

OF THE CLINTON MAY 11, 2009, NON-PUBLIC MEETING TO DISCUSS END-OF-CYCLE SECURITY PERFORMANCE FOR CALENDAR YEAR 2008 cc w/encl: Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Manager Regulatory Assurance - Clinton Power Station Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General J. Klinger, State Liaison Officer, Illinois Emergency Management Agency Chairman, Illinois Commerce Commission

Letter to Charles G. Pardee from Eric Duncan dated May 14, 2009

SUBJECT:

SUMMARY

OF THE CLINTON MAY 11, 2009, NON-PUBLIC MEETING TO DISCUSS END-OF-CYCLE SECURITY PERFORMANCE FOR CALENDAR YEAR 2008 cc w/encl: Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Manager Regulatory Assurance - Clinton Power Station Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General J. Klinger, State Liaison Officer, Illinois Emergency Management Agency Chairman, Illinois Commerce Commission DISTRIBUTION:

Tamara Bloomer RidsNrrDorlLpl3-2 Resource RidsNrrPMClinton Resource RidsNrrDirsIrib Resource Patrick Hiland Kenneth OBrien Jared Heck Allan Barker Carole Ariano Linda Linn DRSIII DRPIII Patricia Buckley Tammy Tomczak

MEETING PRINCIPAL ATTENDEES May 12, 2008 Exelon Mark Kanavos Plant Manager Charles Williamson Security Manager Steve Gackstetter Regulatory Assurance Manager Nuclear Regulatory Commission Steve West Director, Division of Reactor Safety, Region III Eric Duncan Chief, Plant Support Branch, Region III Mark Ring Chief, Branch 1, Division of Reactor Projects, Region III Brian Kemker Senior Resident Inspector, Clinton Enclosure