Non-Public Meeting to Discuss the 2008 End-of-Cycle Plant Security Performance Assessment of Clinton Power Station
ML091190454
Person / Time
Site: Clinton Constellation icon.png
Issue date: 04/28/2009
From: Eric Duncan
Plant Support Branch II
To: Pardee C
Exelon Generation Co, Exelon Nuclear
References
Download: ML091190454 (3)


Text

April 28, 2009 Mr. Charles G. Pardee Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO), Exelon Nuclear 4300 Winfield Road Warrenville IL 60555

SUBJECT:

NON-PUBLIC MEETING TO DISCUSS THE 2008 END-OF-CYCLE PLANT SECURITY PERFORMANCE ASSESSMENT OF CLINTON POWER STATION

Dear Mr. Pardee:

This letter confirms our plans to conduct a meeting with Exelon Generation Company, LLC and the Clinton Power Station management. The purpose of the meeting is for the NRC to present the end-of-cycle security assessment results. The meeting is scheduled for May 11, 2009, at 2:30 p.m. CDT at your Clinton Power Station. This meeting is not open to the public.

Sincerely,

/RA/

Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 cc:

Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Manager Regulatory Assurance - Clinton Power Station Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General J. Klinger, State Liaison Officer, Illinois Emergency Management Agency Chairman, Illinois Commerce Commission UNITED STATES NUCLEAR REGULATORY COMMISSION LISLE, ILLINOIS 60532

Mr. Charles G. Pardee Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO), Exelon Nuclear 4300 Winfield Road Warrenville IL 60555

SUBJECT:

NON-PUBLIC MEETING TO DISCUSS THE 2008 END-OF-CYCLE PLANT SECURITY PERFORMANCE ASSESSMENT OF CLINTON POWER STATION

Dear Mr. Pardee:

This letter confirms our plans to conduct a meeting with Exelon Generation Company, LLC and the Clinton Power Station management. The purpose of the meeting is for the NRC to present the end-of-cycle security assessment results. The meeting is scheduled for May 11, 2009, at 2:30 p.m. CDT at your Clinton Power Station. This meeting is not open to the public.

Sincerely,

/RA/

Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 cc:

Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Manager Regulatory Assurance - Clinton Power Station Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General J. Klinger, State Liaison Officer, Illinois Emergency Management Agency Chairman, Illinois Commerce Commission DOCUMENT NAME: LTR 042809 CLINTON EOC MEETING.DOC G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME TEck:jb KRiemer for MRing EDuncan DATE 4/28/09 4/28/09 4/28/09 OFFICIAL RECORD COPY

Letter to Charles G. Pardee from Eric Duncan dated April 28, 2009.

SUBJECT:

NON-PUBLIC MEETING TO DISCUSS THE 2008 END-OF-CYCLE PLANT SECURITY PERFORMANCE ASSESSMENT OF CLINTON POWER STATION DISTRIBUTION:

Tamara Bloomer RidsNrrDorlLpl3-2 Resource RidsNrrPMClinton Resource RidsNrrDirsIrib Resource Patrick Hiland Kenneth OBrien Jared Heck Allan Barker Linda Linn DRSIII DRPIII Patricia Buckley Tammy Tomczak ROPreports Resource